uke 2, time 1

download uke 2, time 1

of 28

Transcript of uke 2, time 1

  • 7/31/2019 uke 2, time 1

    1/28

    Edit this text for your titleEdit this text for your sub-title

    Presenter name, location, date etc.

    Planer for MEK 4450Marine operasjonerKvrner ASA, June 2011

  • 7/31/2019 uke 2, time 1

    2/28

    Safety moment

  • 7/31/2019 uke 2, time 1

    3/28

    Installation of flexibles and cables

    Typical productsRigid pipesFlexible pipesCable and umbilicals

    Configurations at platform

    Installation aids

    Installation and installation analyzesInstallation of end terminationsRegular laySpecial challenges: shallow water, deep water, slopes, turns etcWaiting on weather

  • 7/31/2019 uke 2, time 1

    4/28

    Typisk produktinndeling

    PipeRigidFlexible

    CableElectric

    Umbilicals

    Beam theory.Axial loadCompressionBedning moment

    Courtesy: Bredero Shaw

    Courtesy: NKT Flexibles

    Courtesy: Nexans

    Courtesy: Nexans

  • 7/31/2019 uke 2, time 1

    5/28

    Rigid pipe

    Large diamterHeavyHigh laying tension

    High bending radiusLarge deck space

    Expensive equipment

    Plastic deformations acceptableRightning before over boardingAvoid repeated plastic bending!

    Thermal isolation (wax formation)

    Concrete layers (gas pipes)

    Courtesy: Bredero Shaw

  • 7/31/2019 uke 2, time 1

    6/28

    Flexible pipes

    Low elastic bending radius

    Less expensive laying vessels / equipmentMore competition

    Separate layers forAxial loadOuter pressure

    Inner pressure

    Courtesy: NKT Flexibles

  • 7/31/2019 uke 2, time 1

    7/28

    CablesPower cables and umbilicals

    Small radius, bending radius, unit weightLess expensive vessels / equipments

    High densityHuge loads on a fully loaded vesselStructural capacity and vessel stability

    Combined functionality

    No plastic bending

    Courtesy: Nexans

  • 7/31/2019 uke 2, time 1

    8/28

    Theory slide. Installation aidsFlexible products are installed with various types of vessels equipped with means / tools for storage and controlled

    over boarding of the products. Typically, the installation of rigid steel pipes requires bigger and more expensivevessels due to the huge space and holding capacities required during deck handling and installation.

    In the following slides some typical examples are given. The first example show a laying vessels for electrical cables,where the cable are stored on a horizontal turntable. A horizontal caterpillar is used, where a tensioner will carrythe weight of the product during overboarding. The vertical U- shaped unit at the side of the vessel is called achute and prevent damages to the product when it goes into the sea.

    We notice that the vessel is equipped with huge crane and a large open deck space. This means that the vessel maybe used for other types of marine operations, like subsea lifting.

    Separate slides display the installation equipment used by this vessel. We notice the belt with the orange pads formingthe tensioner. The pads are pushed toward the cable to ensure sufficient friction. By running the belt the cable

    may be pulled in or out. The other slide shows the chute.The next slide shows an alternative configurations, where the product are routed via a vertical or almost vertical laying

    tower during over boarding. The tensioner are mountd in the laying tower.

    The third slide shows a vessels for pipe lay. Steel pipes are spooled on the enormous vertical drum in the centre ofthe vessel. The hold-back force is taken by the drum itself. In the stern part there are equipments forstraightening out the pipes if there have been plastic deformations and a laying ramp for smooth transition of theproduct to the sea.

    The last two slides shows two other options, particularly useful for laying of rigid pipes. The first case shows a vesselwhere the new pipe sections are welded to the pipe continuously during over boarding and laying. The hugestinger in the stern of the vessel will prevent critical over bending of the product,- plastic deformation is no longeracceptable as the product are going into the sea and there are no means for straightening it out again.

    The last slide displays another alternative, where huge cranes are lifting pipe segments into a vertical J-lay tower.Here the segments are welded to the pipe being laid, again continuously during laying. This solution isparticularily popular in deep water, while the previous solution may be more suited in shallow water.

  • 7/31/2019 uke 2, time 1

    9/28

    Typical installation vessels

    Installation vessel with horizontal caterpillar og chuteInstallation vessel with lay tower

    Pipe lay vessel with reel and lay ramp

    Pipe lay vessel with stinger

    Semi-submersibleAnchor vesselDP vessel

    Pipe lay vessel with J-lay tower

  • 7/31/2019 uke 2, time 1

    10/28

    Installation vessel with horizontal caterpillar and chute

    Aker Connector

  • 7/31/2019 uke 2, time 1

    11/28

    Tensioner / Caterpillar

    Used to pay in / out product, and maintaintension

    Belts with pads pushed toward the product.Friction

    Sufficient force toPull in and overcome friction over chuteKeep cable in position in a storm

    High tension + low radial load capacity =long tensioner / many pads

    Internal friction may be lower than frictionagainst pads.

  • 7/31/2019 uke 2, time 1

    12/28

    ChuteCable installation

    Smooth and even load distributionVessel heading restriction

    At maximum design tensionChute structural capacityProduct integrity (bending + axial load)

    Over bending at tip of chuteTop angle from analyses

  • 7/31/2019 uke 2, time 1

    13/28

    Installation vessel with lay tower

    Scandi Neptune

    Pertinacia

    Seven Seas

  • 7/31/2019 uke 2, time 1

    14/28

    Pipe lay vessel with reel and lay ramp

  • 7/31/2019 uke 2, time 1

    15/28

    Pipe lay vessel with stinger

  • 7/31/2019 uke 2, time 1

    16/28

    Stinger

    Stable support for pipes

    Checking with analysis

    Rollers to reduce frictionPoint loads

    Stinger radius below elastic bending radius

    Departure angle high enough to ensure smooth exitAvoid lift-up of pipe in whole stinger

    May impact vessel motion characteristics

    NOTE: picture shows stinger in elevated, not operational mode

  • 7/31/2019 uke 2, time 1

    17/28

    Pipe lay vessel with J-lay tower

  • 7/31/2019 uke 2, time 1

    18/28

    Typical laying situation

    Picture displaying vessel, water depth, product, and keygeometric parameters

  • 7/31/2019 uke 2, time 1

    19/28

    A salesman's death

    RwH

    HDw

    H1sin

    )sin(1

    DwT

    )sin(

    )cos(1ln

    RX

    Bunnstrekk:

    Toppvinkel:

    Toppstrekk:

    Avstand til touchdown:

    hvorH = Horisontalt strekk i produktet i touchdown [N]w = Neddykket produktvekt [N/m]R = Minste byeradius over touchdown (i sag bend) [m] = Produktvinkel med vertikalen [radianer]D = Vanndyp [m]T = Produktstrekk i verste ende [N]X = Avstand mellom toppunktet og touchdown

    Oppgaven var: en selger vil skaffe firmaet ditt en jobb der en kabel med gitt en gitt kabel skal installeres av et farty som tler etgitt toppstrekk. Br du gripe inn?

    D=1000mW=10 kg/mR=5m

    H=500N

    =0.29 deg!T=100500N

    X=29.98m

  • 7/31/2019 uke 2, time 1

    20/28

    Installation analyses

    Establish weather criteria and a plan for laying. (Layingtables)

    Ensure robust and safe operations for personnel, equipmentand flexible product.

    Low tension: over bending, axial compression, loop formation

    High tension: rupture, tensioner capacity, free spans

    Determine and verify survival conditions

  • 7/31/2019 uke 2, time 1

    21/28

    Survival conditionCutting of product.

    More critical for power cables and umbilicals

    Installation of buoyancy elementsEstablish flexible S- shaped configurationStep by step analysis to ensure product capacity while overboarding buoyancyAnalysis gives guidance in when to pay in / pay out after

    installationAnalyses: can the vessel maintain heading and position?

  • 7/31/2019 uke 2, time 1

    22/28

    Steep slopes

    Uncontrolled sliding of the productAxial compressionFree span formation

    Anchor at top of slope?

    Another anchor further down?

  • 7/31/2019 uke 2, time 1

    23/28

    Other special considerations

    Deep waterHigh top tension, tensioner and chute capacityCombined tension and bending at vessel interface

    Curve laySliding of productLow laying tensionLaying around preinstalled piles etc

  • 7/31/2019 uke 2, time 1

    24/28

    Power cable/umbilical from shore to offshoreFirst end to shore:

    Shallow conditions:Attach buoyancy elementsFloating

    Onshore winch pulls in through ditches or tunnelsFriction, uncertain factor

    Actual bottom topography, strong currents etc may lead tochanges in vessel position. Robustness needed

    Last end to shore:

    More complicated floating

  • 7/31/2019 uke 2, time 1

    25/28

    Power cable/umbilical from shore to offshorePlatform end:

    Installation through platform J- tubesPlatform winch and forerunner through J- tubes

    Coupling of power cable / forerunner at vessel deck.

    Pull-in through J- tubes by platform winch.

    Challenges:Plans for vessel positions changed due to wind, platformmanagers and other unsteady phenomenon.

    Floating platform offset

    Clash with mooring lines, other risers etcOver bending at start of J tube

  • 7/31/2019 uke 2, time 1

    26/28

    Power cable/umbilical from shore to offshoreInstallation of buoyancy elements:

    A S- shaped cable configurations at platform may berequired.

    Buoyancy elements in final stages

    Use of clump weights or sea bed abnchoring may also berequired

  • 7/31/2019 uke 2, time 1

    27/28

    Power cable/umbilical from shore to offshoreChallenges

    Compression / overbending near termination of buoyancyelements, touch down etc

    Clump weight tangles up

    Analyses to determine vessel movements and clump weight

  • 7/31/2019 uke 2, time 1

    28/28

    Power cable/umbilical from shore to offshoreSubsea termination

    Heavy end termination for subsea plug-inBending restrictor or similar at neck

    Focus on bending moments at neck

    Lowered by the cable: head fall over

    Lowered by crane more controlled, but requires separation

    Analysis

    Reveal need for crane

    Determine required separation between crane tip andtermination during lowering

    Calculate design loads for product loading