Bo Teza Tu Cristian
Transcript of Bo Teza Tu Cristian
-
8/13/2019 Bo Teza Tu Cristian
1/130
"Gh. Asachi" Technical University
of IasiCivil Engineering Department
PROJECT, CONSTRUCTION AND QUALITY CONTROLIN HIGHWAY INFRASTRUCTURES
A study of earthworks on IP4, IC24 and IC25 roads
Ing. Botezatu Costel-Cristian
July 2006
-
8/13/2019 Bo Teza Tu Cristian
2/130
"Gh. Asachi" Technical University
of IasiCivil Engineering Department
PROJECT, CONSTRUCTION AND QUALITY CONTROLIN HIGHWAY INFRASTRUCTURES
A study of earthworks on IP4, IC24 and IC25 roads
Master Student:
Ing. Botezatu Costel-Cristian
Coordinator:Paulo Antnio Alves Pereira, Ph.D. - Full ProfessorRadu Andrei, Ph.D. - Full Professor
Tutors:Hugo Manuel Ribeiro Dias da Silva, Ph.D. - Assistant ProfessorJoel Ricardo Martins Oliveira, Ph.D. - Assistant Professor
This master project was developed during a Leonardo da Vinci program in Portugal at
Universidade do Minho during a five months period
July 2006
-
8/13/2019 Bo Teza Tu Cristian
3/130
I
PROJECT, CONSTRUCTION AND QUALITY CONTROL IN HIGHWAY
INFRASTRUCTURES
A study of earthworks on IP4, IC24 and IC25 roads
INDEX
1. Introduction ................................................................................................................. 12. Main stages of road infrastructure concessions .......................................................... 4
2.1.Concession model (e.g. PORTUSCALE organisation) ....................................... 42.2.Design phases ...................................................................................................... 62.3.Construction phases ............................................................................................. 9
3. Project of Highways .................................................................................................. 163.1.Design of Highways .......................................................................................... 163.2.Safety plan ......................................................................................................... 183.3.Environmental documents ................................................................................. 213.4.Affected Services ............................................................................................... 233.5.Expropriations .................................................................................................... 253.6.Pavement loads .................................................................................................. 28
3.6.1.Traffic ........................................................................................................ 283.6.2.Weather conditions (temperature, water precipitation) ............................. 29
3.7.Pavement materials ............................................................................................ 323.7.1.Earthwork materials ................................................................................... 323.7.2.Aggregates ................................................................................................. 353.7.3.Bituminous binders .................................................................................... 373.7.4.Hydraulic binders ...................................................................................... 493.7.5.Stabilized soils ........................................................................................... 423.7.6.Bituminous mixtures .................................................................................. 443.7.7.Mixtures design ......................................................................................... 46
3.8.Pavement design ................................................................................................ 493.8.1.Pavement design methods ......................................................................... 493.8.2.Subgrade .................................................................................................... 513.8.3.Temperature and weather .......................................................................... 533.8.4.Drainage ..................................................................................................... 54
4. Pavement construction technology ........................................................................... 574.1.Earthworks ......................................................................................................... 57
-
8/13/2019 Bo Teza Tu Cristian
4/130
II
4.2.Drainage works .................................................................................................. 604.3.Flexible Pavement layers ................................................................................... 63
4.3.1.Sub-Base ................................................................................................... 63
4.3.2.Base .......................................................................................................... 644.3.3.Binder and Surface course ........................................................................ 66
4.4.Interface preparation .......................................................................................... 694.5.Asphalt plant ...................................................................................................... 714.6.Engineering Structures ....................................................................................... 76
4.6.1.Retaining walls .......................................................................................... 764.6.2.Junctions .................................................................................................... 804.6.3.Viaducts ..................................................................................................... 814.6.4.Bridges ....................................................................................................... 82
5. Quality Control & Quality Assurance ....................................................................... 855.1.Definitions ......................................................................................................... 855.2.Quality documentation ....................................................................................... 875.3.Quality Control Plan minimum requirements .................................................... 875.4.Study for the final characteristics of the pavement ........................................... 89
5.4.1.Roughness .................................................................................................. 905.4.2.Skid resistance ........................................................................................... 915.4.3.Deflection .................................................................................................. 94
5.5.Final documentation submittals ......................................................................... 956. Case Study Earthworks .......................................................................................... 97
6.1.Project ................................................................................................................ 976.2.Materials .......................................................................................................... 1026.3.Construction technology .................................................................................. 1066.4.Quality Control & Quality Assurance ............................................................. 115
7. Conclusions ............................................................................................................. 123Bibliographic references ............................................................................................... 125
-
8/13/2019 Bo Teza Tu Cristian
5/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 1 -
Chapter 1
INTRODUCTION
This project refers to a portion of the new highway build in the Porto area. This road is
part of the Concession Scut do Grande Portothat congregates a group of freeways and
groups road associates in the area of Grande Porto, integrated in the National Road
Plan, with the identification reference in the location inserted in Figure 1.1:
IP4: N de Sendim
IP4: N de Sendim / guas Santas
VRI: N do Aeroporto (IC24) / IP4
IC24: Freixieiro / Aeroporto
IC24: Aeroporto / N da Maia (IP1)
IC24: N da Maia (IP1) / Alfena
IC24: Alfena / N da Ermida (IC25)
IC25: N da Ermida (IC24) / Paos de Ferreira
IC25: Paos de Ferreira / N da EN 106
IC25: N da EN 106 / N do IP9
EN 207: N do IP9 / Felgueiras (EN 101)
Figure 1.1 Highway preview
-
8/13/2019 Bo Teza Tu Cristian
6/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 2 -
Some of the roads that constitute the Concession are already in service and they will be
object of increase of the number of lanes, these being:
IC25 Paos de Ferreira/N da EN106, with the approximate extension of 6.3
km;
IP4 N da Sendim, with the approximate extension of 1 km;
IC24 Freixieiro/Airport, with the approximate extension of 4 km;
IC24 Airport/N da Maia (IP1), with the approximate extension of 3 km;
IC24 N da Maia (IP1)/Alfena, with the approximate extension of 2 km.
The remaining ones, to build from ground, integrate the following sub-sectors:
IP4 Sendim/guas Santas, with the approximate extension of 8.7 km;
VRI Knot of the Airport (IC24)/IP4, with the approximate extension of 3.5 km;
IC24 - Alfena/N da Ermida (IC25), with the approximate extension of 9 km;
IC25 - N da Ermida (IC24)/Paos de Ferreira, with the approximate extension of
10.1 km;
IC25 - N da EN106/N da IP9, with the approximate extension of 9 km;
EN 207 - Knot of IP9/Felgueiras (EN 101).
Of the group of freeways to conceive and to build, the passage of IP4 among Sendim
(N da Sendim) and guas Santas (in the divergence among the freeways A3 and A4) it
will work as a ring road for the urban area of Porto, complementing the distribution of
traffic today effectuated for VCI, Circumvallation and IC24.
In the intermediate area of the sector of IP4, starting from the knot established with EN
13 (designated Via Norte); IP4 can distribute traffic for south, in direction to Porto, and
for north in direction to Maia.
This sector of IP4 is subdivided in two sub-sectors designated for:
IP4 - Sendim/Via Norte and
IP4 - Via Norte/guas Santas,
the last one being visited thru a 4 month period and the object of the present study
project.
-
8/13/2019 Bo Teza Tu Cristian
7/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 3 -
In agreement with the available elements of traffic it was considered already, in the
contest phase and in the negotiation phase for attribution of the Concession, the
adoption of a profile with four roads in each sense.
In the terms of the Contract of Concession it is foreseen in the year of 2006 the entrance
in service of IP4 with a profile of 2 x 3 roads (with a separation of 7.60 m) occupying a
total platform 36.60 m.
In 2015, in agreement with the same contract, be introduced then more two roads in the
interior area, making a profile of 2 x 4 roads, being reduced the sifter to 0.60 m of
width, however, the total width of the platform stays in 36.60 m.
The temporal macro objectives established are next:
Project Phase Concluded: December 2004
Expropriation Phase concluded: December 2004
Construction start: November 2003
Construction deadline: September 2006
Negotiation volume of ACE with the Concessionaire was fixed at 545.26 millions of
euros (Project, Construction, traffic counting equipment, expenses and coordination) for
a total length of the constructed highway of 55.6 km.
-
8/13/2019 Bo Teza Tu Cristian
8/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 4 -
Chapter 2
THE MAIN STAGES OF ROAD INFRASTRUCTURE CONCESSIONS
2.1 Concession model (PORTUSCALE organization)
The main entities involved in the concession process will be presented in this first part
of the report, as well as their contractual relationships and obligations. In Portugal, the
Portuguese State, represented by the EP Estradas de Portugal (Portuguese Road
Administration), is the entity which attributes the concessions through its Department of
Concessions.
The entities, to which the concessions have been given, are called Concessionaires. In
Portugal, four of these entities are the following: i) AENOR for the Northern
concessions; ii) LUSOSCUT CP for Costa de Prata concessions; iii) LUSOSCUT
BLA for Beira Litoral e Altaconcessions; iv) LUSOSCUT GP for Grande Porto
concessions. These types of concessionaires have, as associated members, several
Construction Companies and some Banks, which finance the construction.
The contractors (ACE) are the entities responsible for the execution of the Project and
Construction of the Highways. The contractors of the Concessionaires previously
described are these ones: i) NORACE for the Northern concessions; ii) VIANOR for
Costa de Prataconcessions; iii) LUSITNIA forBeira Litoral e Altaconcessions; iv)
PORTUSCALE for Grande Porto concessions (used as an example in this project
report). All these four entities have construction companies as associated partners.
The construction companies associated with the ACE are called Subcontractors and areresponsible for the constructions of the concessions several roads. The ACE Designers
are the entities responsible for the conception and elaboration of the project for the
highways construction.
In this concession model, the road administration (in this case EP) gives a Concession
Contract (CC) to the Concessionaire to regulate their relationships (rights and duties),
which can be divided into three sub-contracts with the following objectives: i)
-
8/13/2019 Bo Teza Tu Cristian
9/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 5 -
conception, design and construction of the highway; ii) financial support of the
construction; iii) maintenance and exploitation of the conceded highways.
This concession model is commonly used when the government (in this case, the
Portuguese Road Administration) does not want to use directly huge amounts of money
to support financially the construction of a new highway. Thus, the State gives the
highway in concession for a certain period (in this case, thirty years). During this
period, the Concessionaires have the duty of maintaining the highways at a good service
level and the benefits of the road exploitation (by receiving money for each car which
goes by on the conceded highway, paid directly by the road users Highway toll or by
the Portuguese State SCUTS).
The Project and Construction Contract (PCC) regulates the relationship between the
Concessionaire (e.g. LUSOSCUT GP) and the ACE (e.g. PORTUSCALE) and it has as
objective the conception, design and construction of the highway by PORTUSCALE in
a fixed and global price system, before a certain deadline of conclusion. This contract
represents an integral Back to Back of the concessionaire obligations before the State,
concerning the conception, project and execution of the highway. This contract is a part
of the Concession Contract.
The conception and project contract between PORTUSCALE and Designers has as
objective the elaboration of the required projects to start building the highway. The
relationships between PORTUSCALE and the companies responsible for the highway
conception and design (Coordinators, Verifiers and Designers) are regulated by the
project contract.
The sub-contractors objective is the execution and conclusion of all the construction
works for the several highway sections. The sub-contract agreement controls the
relationship between PORTUSCALE and Subcontractors, thus being an entire Back to
Back of the PORTUSCALE obligations before the concessionaire and, consequently,
before the State, concerning the construction of the different highway sections.
-
8/13/2019 Bo Teza Tu Cristian
10/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 6 -
The sub-contractor has the responsibility of constructing the highway sections in
conformity to the project and before the established deadlines, always by following
strictly the safety and environmental rules.
PORTUSCALE (ACE) duties are: the coordination of the different agents of the
constructing process, to assure the reliability of the projects, procedures and inspections.
PORTUSCALE activity consists of the design and execution phases, which are included
in the PCC (Project and Construction Contract) and are planed out in the construction
programme. This is also named Studies and Projects Plan (in Portuguese, Plano de
Estudos e Projectos PEP) and it discriminates the duration of the construction and
design phases.
The concessionaire assures convenient relationships with the road administration (EP)
and the financing Banks, being an intermediary and advocate of the ACEs (Portuscale)
rights near them. They assume the position of Owner of the Works. The road
administration (EP) has the responsibility of carrying out the expropriations and giving
approval to all the necessary studies and projects to the concession.
The concession phases (design, construction and exploitation) are integrant parts of the
CC (Concession Contract) and comprise:
the Construction Programme, which encloses the studies and projects,expropriations
and execution of the road works;
the Programme of Major Maintenance and Enlargements, which also encloses the
respective project.
2.2 Design phases
Essentially, a project is formed by a specific number of volumes, presented in Table 2.1.
Each of them has a descriptive memoir and drawings with specific details for each type
of work. A RECAPE (in Portuguese,Relatrio de Conformidade Ambiental do Projecto
de Execuo), which is a report about the environmental conformity of the execution
project, must be attached to the end.
-
8/13/2019 Bo Teza Tu Cristian
11/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 7 -
Table 2.1 Contents of a projectVolume Name of the volume
1 Synthesis2 Introduction and survey approval3 Geological and Geotechnical studies
4 General lay-out5 Junctions6 Re-establishments, utilities and parallel roads7 Drainage8 Pavement9 Landscape integration
10 Safety equipments11 Signalling12 Counting and classification of traffic equipment and closed TV circuit13 Telecommunications
14 Lighting15 Fences16 Affected services17 Normal concrete works (passageways over and under highways)18 Special concrete works (viaducts and long bridges)19 Other projects20 Expropriations21 Project with measures to reduce the impact on environment22 Assistance and maintenance centre23 Service and station areas
24 Tunnels
The project organization is coordinated by the PORTUSCALE Project Administration,
with the main objective of guaranteeing that the studies and projects are executed before
the deadline, with the requested quality and as estimated in the budget. The relationship
between the main entities involved in the project is presented in Figure 2.1.
Executive commission
Project Management Contractors
Project Coordination
Designers Verifiers
Figure 2.1 Organization of the main entities involved in the project phase
-
8/13/2019 Bo Teza Tu Cristian
12/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 8 -
The beginning of the construction depends on the design phase, concerning three
fundamental points:
delivery/approval of the expropriations project to begin the expropriations process, of
the responsibility of EP, which should be carried out within a period of 6 months;
delivery/approval of the complete projects of the affected services reestablishment, to
allow the contract with the several entities (responsible for the services) on time and
their immediate removal at the beginning of the construction works;
delivery/approval of the execution project or, at least, the necessary designs for the
first construction works.
The expropriation project is carried out by PORTUSCALE (by proposing an amount of
money for the expropriated lands), but it is essential that EP (the State) approves the
expropriations project and carries out the expropriations (by paying the money to the
land owners). After the EP approval of the expropriation project, there is a period of 6
months to complete these expropriations.
If an owner does not accept the offer of the State, the land can be taken out, according to
a law which declares that if a highway is of national interest, the land needed to
construct that highway can be taken out immediately. When an inhabited house is in the
land, the expropriation can only be carried out after the habitants leave their house, after
mutual agreement between owners/habitants and EP, concerning the value of the land
and the house. Sometimes, the decision about the expropriation can be taken in court of
law, thus extending the period of expropriation more than 1 year. If the inhabited house
is rented, the habitants can be compensated with money or with a new house. The
decision about the compensation can also be taken in court of law, which will send an
evacuation order after the final verdict.
Works usually begin before the expropriation phase ends without the possibility of
demolishing the houses or closing some road accesses, thus harming the normal
execution of the highway construction. In this case, if the works deadline is exceeded
by expropriation causes, PORTUSCALE is compensated by the State, concerning these
delays (e.g. by extending the exploitation period).
-
8/13/2019 Bo Teza Tu Cristian
13/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 9 -
The affected services are mainly formed by: gas pipes, water pipes, electricity cables,
telecommunications and sanitation. All the projects of the affected services
reestablishment are carried out by Portuscale design companies. The
telecommunications and electricity works are done by the companies responsible for
those services, which are paid afterwards by the LUSOSCUT GP concessionaire. The
gas, water and sanitation works are performed by the sub-contractor companies which
work for Portuscale.
Basically, concerning affected services, PORTUSCALE has the role of mediator, by
trying to solve the problems with the several companies, by offering the services as
quickly as possible (to avoid delays at the construction work) and by asking the fair
prices for the works.
The affected services main stages are the following: i) 1st phase (between the
conclusion of the preliminary study and the beginning of the geometrical lay-out)
Seeking information about the services in entities and companies; ii) 2ndphase (at the
beginning of the execution project) Emission of the project of the services cadastre;
iii) 3rdphase (until the end of the execution project) Emission of the project of the
services relocation.
2.3 Construction phases
The organization of the construction processes is coordinated by the Postuscales
construction administration, whose main objective is to guarantee the execution of the
construction works before the deadline, with the requested quality and as estimated in
the budget.
The Postuscale activity during the construction phase consists, fundamentally, in the
achievement of the following objectives:
to guarantee the accomplishment of the contractual deadline through an adequate
Planning of the Construction and by following the work evolution;
to guarantee a final product with the requested quality through inspections and tests
and through adequate solutions to the non-conformity situations;
to control and to process the work invoices to the sub-contractors and to theconcessionaire;
-
8/13/2019 Bo Teza Tu Cristian
14/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 10 -
to guarantee hygiene and safety conditions at the work place;
to follow the environmental and archaeological occurrences at the highway work
without affecting the normal work evolution;
to guarantee the correct management of the insurance policy.
Concerning the planning of the Highway construction, the contractor must emit and
submit to Portuscale an Initial Work Plan until the 30thday after the reception of the
execution project (with the limit of 10 days before the consignation). Once approved,
this work plan becomes the base document of the construction. The initial work plan is
constituted by: i) descriptive and explanatory memory; ii) work programme with
physical and financial chronological diagrams; iii) charts of equipment needs and labour
force; iv) project of the work yard and plans of accesses, circulation and signalling;
v) organisational diagram; vi) expropriations chronological diagram.
The Portuscale has two procedures to follow-up the construction work, namely
Actualizations of the Work Programme (performed monthly) and Revisions of the Work
Programme (performed every three months).
Concerning the Actualizations of the Work Programme, the sub-contractor must
schedule the initial work programme monthly and submit it to Portuscale until the 10 th
day of each month, with the analyses which justify the work delays and the respective
measures to recover the lost time. These Actualizations must always show the initial
work plan or the last approved revision of the plan, registered as "Baseline", by
underlining the essential sequence of procedures.
Concerning the Revisions of the Work Programme, it must be revaluated every three
months or every time Portuscale considers it is necessary. The sub-contractor must
submit the Reviewed Work Programme 30 days after it has been required by Portuscale.
Those Revisions must explain the work delays and the respective measures and
deadlines to recover the lost time, with the indication of the necessary equipment and
the labour force reinforcements to respect the work deadline established in the initial
contract. The essential sequence of procedures must be underlined.
-
8/13/2019 Bo Teza Tu Cristian
15/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 11 -
To allow the weekly planning of Portuscale activities and the appropriate monitoring of
works, the sub-contractors are requested to submit to ACE a fortnightly work
programme, which contains information about the current or new work fronts within the
analysed period, the stop points (for Quality Control and Health and Safety Assessment)
and all the necessary interventions, regarding the Affected Services. The Work
Programme for the next fortnightly period must be submitted fortnightly, by the
Sub-contractor to the Portuscale, until the penultimate working day of every week, with
the indication of the active work fronts, in order to allow the coordination of the activity
of the several work agents.
In order to avoid eventual delays in the beginning of works, it is necessary to guarantee
the delivery of several documents among the different parts involved in the construction
of the Highway concession (Lusoscut GP, Portuscale and Sub-contractors). Portuscale
assumes the commitment of delivering the group of documents presented in Table 2.2 to
the Sub-contractor at the consignment date (this is independent from previous deliveries
of the same documents in other phases of the process).
Table 2.2 Documents emitted by Portuscale and submitted to the Sub-Contractor
Documents Time limitApproved execution project UndefinedModels for the emission of the measurement reports, listing the articlesand unitary costs settled with the Sub-contractors
Undefined
Sub-contractors quality manual UndefinedThe verification of the supporting polygonal (road line) UndefinedThe verification of the expropriations polygonal (area) UndefinedHealth and Safety Plan UndefinedCD with the Work Quality Manual, sub-contract agreement and contractof project and construction
Undefined
Application of laboratorial management Highways Undefined
The preparation, compilation and approval of the documents, presented in Table 2.2,
imply the intervention of other entities and documents, such as those presented in
Table 2.3, which the Sub-contractor must deliver to Portuscale.
The documents to be delivered by the Concessionaire (Lusoscut GP) to Portuscale, and
vice-versa, are presented respectively in Tables 2.4 and 2.5 (some documents do not
have an explicit deadline).
-
8/13/2019 Bo Teza Tu Cristian
16/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 12 -
Table 2.3 Documents emitted by the Sub-Contractor and submitted to Portuscale
DocumentsDelivery time limit relatively
to the beginning of works
Surrounding conditions until 45 days beforePreliminary work programme until 45 days before
Preliminary chart of labour force until 45 days beforePreliminary chart of equipment needs until 45 days beforeInformation concerning preliminary communication until 12 days beforeCrises management Emergency plan until 10 days beforeSafety management Organisational Diagram until 10 days beforePlan of works with special risks until 10 days beforeProject of the work yard and plans of accesses, circulationand signalling
until 10 days before
Sub-contractor quality plan until 30 days beforeWorking procedures until 60 days before
Definitive working plan until 10 days before
Table 2.4 Documents emitted by the Concessionaire and submitted to PortuscaleDocuments Time limit
Document with specifications approved by EP Undefined
Execution project approved by EP Undefined
Table 2.5 Documents emitted by the Portuscale and submitted to the ConcessionaireDocuments Time limit
Sub-contractor quality Manual UndefinedInspection and test plans Undefined
Sub-contractor quality plan Undefined
Descriptive report Undefined
Definitive working programme 28 days after consignment
There are some fundamental definitions related to inspection, tests and non-conformity
solution which must be understood, namely the following:
Inspections and Tests Plan or PIE (in Portuguese,Plano de Inspeces e Ensaios) a document which contains a compilation of specifications with verifications, which
demonstrate the conformity of an activity with the work quality manual, with the
execution project of each highway section and with the working procedures of the
sub-contractor;
Documental analysis an evaluation of the previous documents necessary to begin
an activity, by verifying the conformity of the materials, equipments, constructive
methods or the work plan proposed by the sub-contractor;
-
8/13/2019 Bo Teza Tu Cristian
17/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 13 -
Stop point situation of the work, in which the sub-contractor needs a special
authorization from Portuscale to begin or continue the activity;
Nonconformity (NC) a product which does not conform to the specifications;
serious or imminent danger situations;
Anomalya failure which occurs during the work execution. If it is not corrected, it
will lead to a NC;
Correcting action or AC (in Portuguese,Aco Correctiva) an action which
eliminates the causes of nonconformity, anomaly or another unwanted situation in
order to avoid its repetition;
Derogation (DRG) a written authorization to use or deliver a product which does
not conform to the specifications.
Concerning inspections and tests, the sub-contractor effectuates them, according to the
traditional control methodology and warranting the total accomplishment of the PIE.
The Portuscale has the obligation of verifying if they are effectively and correctly
accomplished. The PIE defines the inspections and tests to be necessarily performed by
the sub-contractor and those to be performed by Portuscale. It regulates the inspection
of Portuscale and presents the responsible persons for every inspection action. The PIE
must also present how to evaluate (and who evaluates) the qualitative service of thesub-contractor, by showing explicit rules to accomplish the referred inspection. It refers
the registers and how to register the tests and inspections.
The Portuscale will evaluate the sub-contractors system of quality assurance and will
execute its own inspections and tests on a sampling basis (10 to 20%), which is
considered to be representative of every activity, in order to validate the sub-
contractors tests and inspections. In the case of a stop point, the Portuscale interventionwill always consist in a previous audit of the sub-contractor (by obtaining from the
sub-contractor previous copies of the inspections registers). Moreover, Portuscale can
carry out the same verifications to confirm those done by the sub-contractor.
Another phase of the construction process is the invoice, in which the Concessionaire
(Lusoscut), Portuscale and Sub-contractors interfere. The methodology adopted in the
process of obtaining the authorization to emit the monthly works invoice is
schematically illustrated in Figure 2.2.
-
8/13/2019 Bo Teza Tu Cristian
18/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 14 -
Figure 2.2 Methodology used in the monthly invoice process
Concerning safety and prevention, Portuscale has the aim of establishing the activities
which should be adopted in the planning and implementation of prevention and safety atworkplace, namely by applying the Health and Safety Plan which allows getting higher
levels of health, safety and comfort.
This principium is applied to: i) all the project and construction works of the highway
sections and roads associated with the concession; ii) all the areas considered to be work
yards (lands or places which support the works execution); iii) all the areas near the
work yards and workplaces (in order to control the risks of human accidents).
1 Sub-contractorElaboration of the monthly report of
measurement
2 Sub-contractorSend, before the 22ndday, the monthlyreport of measurement to Portuscale
- Measurement report- Quantities justifications- Declarations of quality
- Measurement report- Declarations of quality
Protocol
Invoice
Start
Protocol
Invoice
End
3 PortuscaleTo verify the quantities constructed on the
month
4 PortuscaleElaboration of the monthly report of
measurement (Project + Construction)
5 Portuscale
Send the monthly report of measurementto Lusoscut
6 LusoscutApproval and emission of the payment
certificates of the monthly report ofmeasurement (Project + Construction)
7 PortuscaleSend the invoice to Lusoscut
8 PortuscaleSend the approval and payment
certificate of the monthly report ofmeasurement of the sub-contractor
9 Sub-contractorSend the invoice to Portuscale
-
8/13/2019 Bo Teza Tu Cristian
19/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 15 -
The agents responsibilities and the Portuscales acting in terms of safety are described
in a specific document (Manual Prprio) by DPS (Department of Prevention and
Safety).
-
8/13/2019 Bo Teza Tu Cristian
20/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 16 -
Chapter 3
PROJECT OF HIGHWAYS
3.1 Design of Highways
Geometric design is primarily concerned with relating the physical elements of the
highway to the requirements of the driver and the vehicle. It is mainly concerned with
those elements which make up the visible features of the roadway, and it does not
include the structural design of the facility. Features which have to be considered in
geometric design are, primarily, horizontal and vertical curvature, the cross-section
elements, highway grades and the layout of intersections.
Proper geometric design will inevitably reduce the number and severity of highway
accidents while ensuring high traffic capacity with the minimum of delay to vehicles.
While these are the main factors to be considered, care must also be taken that the
highway presents an aesthetically satisfying picture to both the driver and the onlooker.
The aim should be to design a facility that blends harmoniously with the topography and
not one that leaves an ugly scar on landscape.
The design for capacity defines the ability of a road to accommodate traffic under given
circumstances. Factors which must be taken into account in determining the governing
circumstances are the physical features of the road itself and the prevailing traffic
conditions. Poor physical features which tend to cause a reduction in capacity are
narrow traffic lanes (3.65 m are now accepted as being the minimum), inadequate
shoulders (too narrow shoulders alongside a road cause vehicles to travel closer to the
centre of the carriageway), side obstructions (poles, bridge abutments, retaining walls orparked cars that are located within about 1.75 m of the edge of the carriageway
contribute towards a reduction in the effective width of the outside traffic lane) and
imperfect horizontal or vertical curvature (result in inadequate sight distance).
Unlike the physical features of the highway, which are literally fixed in position and
have definite measurable effects on uninterrupted and interrupted traffic flows, the
prevailing traffic conditions are not fixed but vary from hour to hour throughout theday. The flows at any particular time are a function of the speeds of vehicles, of the
-
8/13/2019 Bo Teza Tu Cristian
21/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 17 -
composition of the traffic streams and the manner in which the vehicles interact with
each other, as well as the physical features of the roadway itself. As we can see in
Figure 3.1, the traffic varies in composition (trucks, small cars, etc.) and in
concentration in different directions. The term concentration used the same as the term
density is defined as the number of vehicles occupying a unit length of a traffic lane at
a given instant. Concentration is usually expressed in vehicles per kilometer.
Figure 3.1 A3 Highway in Portugal
The vertical alignment design refers to the design of the tangents and curves along the
profile of the road. The primary aim of this profile design is to ensure that a
continuously unfolding ribbon of road is presented to the motorist so that hisanticipation of directional change and future action is instantaneous and correct. Roller-
coaster types of profile should be avoided as they are dangerous as well as aesthetically
unpleasing. In vertical design, gradients should be the most important factor taken in
consideration since grades of up to about 7 % have relatively little effect on the speeds
of passenger cars but the speeds of commercial vehicles are considerably reduced when
long gradients, with grades in excess of about 2 % are included (the speed of traffic is
often controlled by the speeds of the slower commercial vehicles). Most highwayauthorities now accept a gradient of 4 % as being the maximum desirable on major
highways; hence this criterion is usually a controlling feature of highway design.
Cross-section elements are those features of the highway which form its effective width
and which affect vehicle movement. The constituent parts, as we can see in Figure 3.2,
of primary interest are the number and width of traffic lanes, the central reservation,
shoulders, camber of the carriageway and, where necessary, the side slopes of cuttingsor embankments.
-
8/13/2019 Bo Teza Tu Cristian
22/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 18 -
Figure 3.2 Typical transversal profiles
Horizontal curvature design is one of the most important features influencing the
efficiency and safety of a highway. Improper design will result in lower speeds and a
lowering of highway capacity. The importance of curve design upon safety is reflected
by the accident statistics, which shows that the sharper the curve the greater the
tendency for accidents to occur. The maximum comfortable speed on a horizontal curveis primarily dependent upon the radius of the curve and the super elevation of the
carriageway. In addition, vehicle speeds and safety on high-speed roads are aided by the
presence of such features as extra carriageway widths at the curves themselves and the
insertion of transition curves between straights and curves, some examples of such
curves can be seen in Figure 3.3.
Figure 3.3 Horizontal curves in Portugal highways
3.2 Safety plan
In the decree of Ministry of the Social Safety and Workare few points that explain the
legislation in this matter, described shortly forward. Safety's conditions in the developed
work in temporary construction yards are frequently very deficient and they are in the
origin of a preoccupying number of the serious work accidents and fatalities, provoked
above all by falls in height, crushes and entrench. Face to the imperious need of
-
8/13/2019 Bo Teza Tu Cristian
23/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 19 -
reducing the professionals risks in the sectors with larger accident rates, the agreement
about work conditions, hygiene and safety in the work and combat of the mortalities,
have been reviewed and improved the safety specific norms in the work in the sector of
the building site and public works, as well as the reinforce of the means and of the fiscal
activity in this and in other sectors more affected for the incidence of work accidents
and professional diseases.
Plan of safety and health constitutes one of the fundamental instruments of the planning
and of the organization of the safety in the work in temporary construction yards or
movable, to the disposal of the coordination system of safety, what justifies the need to
improve the respective regulation. The plan should be elaborated starting from the phase
of the project of the work, being later developed and specified before passing to the
execution of the work, with the opening of the construction yard. The owner of the work
will name safety's coordinator through in work of a written declaration that identifies it
before all the intervening in the construction yard. Safety's coordinator in work and the
safety and health plan are not obligatory in works of smaller complexity in than the
risks are usually more reduced. However if there is a issue to execute those works
determined by works that implicate special risks, the entity performer owes records of
procedures of safety that indicate the necessary measures of prevention to execute those
works.
The prevention of the professional risks depends of the knowledge of the technical
characteristics of the work, so that can be identified the potential risks and adopt work
processes that avoid them or minimize, insofar as possible. The works in construction
and mainly in civil engineering domain consist in basely in excavation, earthmoving,
construction, enlargement, modification, demolition, repairing, restore, conservationand cleaning of buildings, assembly and disassembly of prefabricated elements,
scaffolds, cranes, etc.
Safety's plan and health should foresee measures appropriate to prevent the special risks
for the safety and the current workers health, these risks being those that implicate:
Exposing the workers to entrenchment, of sinking or of fall in height (Figure 3.4),
particularly worsened by the nature of the activity or of the used means, or of the halfinvolving of the position, or of the situation of work, or of the construction yard;
-
8/13/2019 Bo Teza Tu Cristian
24/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 20 -
Figure 3.4 Work on a viaduct
Working in the proximity of electrical lines of average and high tension (in Figure
3.5 can be observed power lines which is achievable by machines that are working in
their proximity);
Figure 3.5 Electrical lines in construction area
Working in roads, rail or road that are in use, or in they proximity (in Figure 3.6 can
be observed works near a rail track and a highway that are not being closed during
construction faze);
Figure 3.6 Works carried out under circulation
-
8/13/2019 Bo Teza Tu Cristian
25/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 21 -
Exposing the workers to chemical risks or biological hazards of causing professional
diseases;
Exposing the workers to ionized radiations, when the designation areas are
obligatory to be controlled or watched;
Dive with equipment or that implicate drowning risk;
Work in wells, tunnels, galleries or caisson of compressed air;
Use of explosives, or they originate derived risks of explosive atmospheres (in Figure
3.7 we can see works with explosives the textile materials are applied to reduce the
risks of flying debris, also reducing dust emission);
Figure 3.7 Works involving explosives
Assembly and disassemble of prefabricated elements or other, whose form,
dimension or weigh expose the workers to serious risk.
Any other work can be included here if the owner of the work, the author of the project
or any of the coordinators of safety, consider to be capable of constitute serious risk for
the safety and health of the workers.
3.3 Environmental documents
Environment Sector elaborates a PGA - Plano de Gesto Ambiental (Plan of
Environmental Administration), for each section of highway that begins. This document
is the base of the functions of Sector and it is a brief summary of the most important
aspects of RECAPE (Report of Environmental Conformity of Project of Execution) that
the Builders have to accomplish completely. In the intention of minimizing theenvironmental impact during the planning phase and execution of the Work, Portuscale
-
8/13/2019 Bo Teza Tu Cristian
26/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 22 -
gives to the Builder the Plan of Environmental Administration, in our case of the Lot 2 -
IP4 through NORTE/GUAS SANTAS.
This document makes the synthesis of the environmental documents of Execution
Project of the lot in cause, making possible the planning of the procedures, of the
processes and of the resources to use to develop, to implement and to monitor his
implementation efficiently in all of the phases of the work from the consignment to the
temporary reception on the part of the Concessionaire. This report, it should be
permanently available in the work shipyard.
Before begin of the work must be give to the builder documents such as Plan of
construction yard, Integrated plan of Administration of Residues (management of
coming residues of the shipyards like dumps, mud, asphalts, oils, lubricants, fuels,
chemical products and other residual materials of the work), Plan of Environmental
Emergency (actions in case of accident with it spills or emission of pollutant substances
considering all the possible risk situations), Official report to the Population (inhabitants
located inside of a strip of 200m of the limit of the plan should be informed on the
occurrence of the construction operations), Reports of Rising water table or Flow of the
existent Underground Receptions along the tracing, Plan of Monitoring (Hydro
Resources and Waters Quality, Sound Environment, Wells, Spring and Holes), Plan of
landscape recuperation of the Areas of construction yard and other Degraded Areas,
Machines Park and Temporary Access roads.
Also during the construction phase are documents that must be giving to builder like
Projects of Execution of Fencing, Projects of Execution of Loans, Reports of
Attendance of water table, Rising or Flow of the existent Underground Receptionsalong the Plan (the Builder should give to PORTUSCALE in the end of each season, the
Report of Monitoring of the water table of the existent underground receptions along the
continuity plan), Report of Monitoring of the Emissions of the Central of Manufacture
of Bituminous Mixtures, Report of Monitoring of the Emissions of the Central of
Manufacture of Bituminous Mixtures, Reports of Monitoring (Hydro Resources and
Waters Quality, Sound Environment, Wells, springs and Drillings) and Implementation
of Landscape Integration Project.
-
8/13/2019 Bo Teza Tu Cristian
27/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 23 -
To minimize the environmental impact the location of construction yards preferentially
should coincide with areas already waterproof/paved that are not occupied (former
industrial areas without activity, abandoned quarries or other works, etc). In case they
have to be built, these should be waterproof properly and be located in areas away from
places with lines of water and receptions. After the conclusion of the works, the soils of
the no paved areas of the construction yard and of vehicles and machines circulation
should be clean and objective of de-compaction of the soil, for form recover more
quickly of their natural characteristics. Eventual noxious effects of the discharge in
natural waters of residual waters can be avoided through the construction of appropriate
systems for the respective drainage and treatment. It should be preceded with an
installation that collects and treats the waters that contemplates the industrial and
domestic effluents and for the water from machines and vehicles wash should be used a
clearing tank. In the case of bituminous mixtures plant, the kettle of the headquarters,
the deposits of fuel, the asphalt deposits, deposits of bitumen and emulsions, they
should be put on concrete flagstones with a retention wall and for the filer in excess
should suffer a specific treatment with the use of humidification that will transform the
powder in mud.
Before the beginning of the work should be mentioned the place of bituminous asphalt
plant (won't be located in the proximity of habitation areas or of isolated houses) and all
the deposit and loan places should be presented and identified before execution, to
Portuscale, for evaluation.
3.4 Affected services
As was mentioned in chapter 2, affected services are formed by gas pipes, water pipes,electricity mains, telecommunications and sanitation. These services can interfere with
the highway line and because of that they must be repositioned or relocated. Some of
these services cannot be repositioned until the expropriations are finalized (Figure 3.8,
Figure 3.9 and Figure 3.10), the working being carried out around those services.
Telecommunications and electricity works are being done by the company that holds
them and are paid afterwards by the concessionaire.
-
8/13/2019 Bo Teza Tu Cristian
28/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 24 -
Figure 3.8 Power lines that constitute a part of affected services
In Figure 3.8 can be observed some power lines that couldnt be repositioned, because
dismantling them will affect the houses after those lines. Also in Figure 3.9 can be
observed a telephone line which is still in service during construction and serves the
houses near by construction site.
Figure 3.9 Telecommunication line obstructing construction
The gas, water and sanitation are being effectuated by the constructing companies. In
Figure 3.10 left can be seen two red lines that symbolize the gas pipe crossing the area
where the highway will be and in Figure 3.10 right can be observed a sanitation conductwhich is disaffected (in the central of the image).
-
8/13/2019 Bo Teza Tu Cristian
29/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 25 -
Figure 3.10 Gas pipe (left) and sewage (right) pipe
Portuscale its having in affected services a role of mediator, because some companies
can ask more money on some works or they want to use expensive materials or they can
delay the work progress by dont doing these repositioning at time. Affected services
stages begin with geometrical lay-out followed by issuance of cadastral project (its at
the beginning of execution project) and at the end with the issuance of services
repositioning project.
3.5 Expropriations
In this matter will be developed a memory ho seeks to present the topographicalcharacteristics concisely, cadastral, cultural and infra-structural, situations of urban
occupation, industrial and commercial, and other relevant situations that condition and
they influence the lands affected for the work. The plan can grow on some lands with
agricultural occupation in the periphery of urban agglomerates, the urban center, houses
that will be expropriated, and workshops. Inside of the territory under jurisdiction of the
municipal districts the portions interfere in urban areas are predominantly residential,
industrial, green areas, architectonical, equipment areas, etc. In Figure 3.10 can be seenhow the line of the highway (the area hatched with red) crosses an area with houses
positioned in construction zone. These houses couldnt be expropriated on time so the
construction began before their demolition. The roads which are visible in the picture
are roads constructed for trucks and vehicles of the construction yard and will be
demolished when they will not be necessary.
-
8/13/2019 Bo Teza Tu Cristian
30/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 26 -
Figure 3.10 Highway crossing a populated area (guas Santas)
Also for this type of problems must be presented an evaluation bases, intend to justify
the unitary values of lands, improvements, indemnity and other compensations to apply
in the work. In the determination of the prices to apply are consulted market indicators,
as well as the values practiced by the expropriate entity or for another one with identical
purpose in several projects in the area were the work will be developed. Presented
values must be calculated as "fair indemnity", acceptable on the part of expropriated, for
the expropriations to develop with the minimum of conflicts. To reduce costs in some
areas can be applied some solutions like gabions and air-placed concrete (Figure 3.11)
in zones of cut and fill. These solutions have the advantage of occupying a small area of
land on the sides of highway and they are used to stabilize the slopes. Usual retainingwalls can be also used but they occupy a bigger area during construction and are more
difficult to build.
Figure 3.11 Solutions for reduce of expropriations area
Expropriation project begin with topographical delimitation of areas in cause, this
project belonging to Portuscale, who makes the calculation for the lands and propose
these sums of money to the government because he will be paying these lands, but the
-
8/13/2019 Bo Teza Tu Cristian
31/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 27 -
government approve these money and effectuates the expropriations. A delimited
expropriation area can be seen in Figure 3.12, the zones marked with red being those
which must be expropriated.
FREG. DE GUAS SFREG. DE S. MAMEDEINFESTA
Figure 3.12 Areas of expropriation object
The government has 6 months at disposal to effectuate these expropriations after he will
approve expropriation project. When the owners of the houses object to expropriate
dont accept the offer of government, then the land can be taken by reason of a law in
which is define that if a work is in national interests, then this land can be taken
immediately, but when on the land is an inhabited house, they must wait until the trial is
over. However, if the house is rented, the court can send an evacuation decision, phase
which can still take 1 year. In some cases the works begin along those houses without
demolish them or closing access roads, going forward only few stages (for example
earth works, as we seen in Figure 3.10). If the deadline is exceeded by expropriate
causes then Portuscale is absolved by these delays.
-
8/13/2019 Bo Teza Tu Cristian
32/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 28 -
3.6 Pavement loads
3.6.1 Traffic
The traffic to be considered includes axle loads, the number of load repetitions, tire
contact areas, and vehicle speeds. Trucks for example can have single axle with single
tires, single axle with dual tires or tandem axles with dual tires and special heavy-duty
trucks, tridem axles consisting of a set of three axles, each spaced at a particular
distance.
In the design of flexible pavements by layered theory, only the wheels on one side, say
at the outer wheel path, need to be considered; where as in the design of rigid
pavements by plate theory, the wheels on both sides, are usually considered.
Loads are the vehicle forces exerted on the pavement (for example by trucks, small cars,
etc.). Since one of the primary functions of a pavement is load distribution, pavement
design must account for the expected lifetime traffic loads. Loads, the vehicle forces
exerted on the pavement, can be characterized by tire loads, axle and tire configurations,
load repetition, traffic distribution across the pavement and vehicle speed. Tire loads are
the fundamental loads at the actual tire-pavement contact points. While the tire contact
pressure and area is of concern, the number of contact points per vehicle and their
spacing is critical. As tire loads get closer together their influence areas on the pavement
begin to overlap, at which point the design characteristic of concern is no longer the
single isolated tire load but rather the combined effect of all the interacting tire loads. In
the matter of trafficdistribution on any given road, one direction typically carries more
loads than the other. Furthermore, within this one direction, each lane carries a differentportion of the loading. The outer lanes often carry the most trucks and therefore are
usually subjected to the heaviest loading.
Regarding Vehicle speed in general, slower speeds and stop conditions allow a
particular load to be applied to a given pavement area for a longer period of time
resulting in greater damage. If mix design or structural design has been inadequate, this
behavior is sometimes evident at bus stops (where heavy buses stop and sit while
-
8/13/2019 Bo Teza Tu Cristian
33/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 29 -
loading/unloading passengers) and intersection approaches (where traffic stops and
waits to pass through the intersection).
Pavement structural design requires a quantification of all expected loads a pavement
will encounter over its design life. This quantification can be usually done in two ways,
equivalent single axle loads (ESALs) or load spectra.
The first approach converts wheel loads of various magnitudes and repetitions ("mixed
traffic") to an equivalent number of "standard" or "equivalent" loads based on the
amount of damage they do to the pavement. The commonly used standard load is the
18,000 lb. equivalent single axle load. Using the ESAL method, all loads (including
multi-axle loads) are converted to an equivalent number of 18,000 lb. single axle loads,
which is then used for design. A "load equivalency factor" represents the equivalent
number of ESALs for the given weight-axle combination. As a rule-of-thumb, the load
equivalency of a particular load (and also the pavement damage imparted by a particular
load) is roughly related to the load by a power of four (for reasonably strong pavement
surfaces). For example, a 36,000 lb. single axle load will cause about 16 times the
damage as an 18,000 lb. single axle load. Buses tend have high load equivalency factors
because although they may be lighter than a loaded 18-wheeler, they only have two or
three axles instead of five.
The second approach characterizes loads directly by number of axles, configuration and
weight. It does not involve conversion to equivalent values. Structural design
calculations using load spectra are generally more complex than those using ESALs
because loading cannot be reduced to one equivalent number. Both approaches use the
same type and quality of data but the load spectra approach has the potential to be moreaccurate in its load characterization.
3.6.2 Weather conditions (temperature, water precipitation)
A pavement must function within its environment. The environment can vary greatly
across the country at any one time and it can also vary greatly throughout time at any
one place. Environmental variations can have a significant impact on pavementmaterials and the underlying subgrade, which in turn can drastically affect pavement
-
8/13/2019 Bo Teza Tu Cristian
34/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 30 -
performance. The key environmental parameters of concern are typically temperature,
frost action and moisture. Temperature acts on pavements in two principal ways. First,
temperature extremes can affect asphalt binder rheology and second, temperature
variations which can cause pavement to expand and contract. Asphalt binder rheology
varies with temperature. Therefore, estimated temperature extremes and their effects are
a primary consideration when selecting an appropriate asphalt binder. For flexible
pavements, older asphalt binder grading systems did not directly account for
temperature effects and thus various empirical systems and thumb-rules were
developed.
Pavements, like all other materials, will expand as they rise in temperature and contract
as the fall in temperature. Small amounts of expansion and contraction are typically
accommodated without excessive damage, however extreme temperature variations can
lead to catastrophic failures. Flexible pavements can suffer transversal cracks as a result
of excessive contraction in cold weather as can be observed in Figure 3.13.
Figure 3.13 Cracks from excessive pavement contraction
Frost action can be divided into "frost heave" and "thaw weakening". "Frost heave" is
an upward movement of the subgrade resulting from the expansion of accumulated soil
moisture as it freezes, while "thaw weakening" is a weakened subgrade condition
resulting from soil saturation as ice within the soil melts.
-
8/13/2019 Bo Teza Tu Cristian
35/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 31 -
Frost heaving of soil is caused by crystallization of ice within the larger soil voids and
usually a subsequent extension of this ice to form continuous ice lenses, layers, veins, or
other ice masses. As depicted in Figure 3.14, an ice lens grows and thickens in the
direction of heat transfer until the water supply is depleted or until freezing conditions at
the freezing interface no longer support further crystallization.
Figure 3.14 Formation of ice lenses in a pavement structure
As the ice lens grows, the overlying soil and pavement will heave up potentially
resulting in a rough, cracked pavement (see Figure 3.14).
Figure 3.14 Frost Heave
Frost heave occurs primarily in soils containing fine particles (often termed frost
susceptible soils), while clean sands and gravels (small amounts of fine particles) are
-
8/13/2019 Bo Teza Tu Cristian
36/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 32 -
non-frost susceptible. Thus, the degree of frost susceptibility is mainly a function of the
percentage of fine particles within the soil.
Thawing can proceed from the top downward, or from the bottom upward, or both.
How this occurs depends mainly on the pavement surface temperature. During a sudden
spring thaw, melting will proceed almost entirely from the surface downward. This
type of thawing leads to extremely poor drainage conditions. The frozen soil beneath
the thawed layer can trap the water released by the melting ice lenses so that lateral and
surface drainage are the only paths the water can take.
3.7 Pavement materials (identification, behavior, tests)
3.7.1 Earthwork materials
"Backfill Foundation" means the ground upon which said backfill shall be executed.
The following areas are distinguished on the backfill being its geometry defined on the
design:
Lower part of backfill (EB) - Is the area where the foundation lays (usually it is
considered to be formed by the two first backfill layers). Whenever the clearing
works have been previously carried out the layers situated bellow the natural ground
level shall also be included.
Body - means the backfill part situated between the base and the top of the backfill.
Top part of backfill (ET) - Is the area (about 40-85cm) which supports the capping
layer and includes the pavement foundation and influences its behavior.
Capping layer - It is the last "layer" of the backfill. Its function to grant the pavement
foundation good conditions not only in what the service conditions are concerned but
also the assembly conditions on site which must allow an easy and adequate
compaction of the first pavement layer and thus assuring the appropriate conditions
for the site traffic. For construction reasons the capping layer can be formed by one
or several layers. The top of the backfill and the capping layer form the pavement
foundation.
Sides - Is lateral area of the embankment body that includes the slopes and can
occasionally work as a stabilizer.
-
8/13/2019 Bo Teza Tu Cristian
37/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 33 -
The materials to be used for the backfill shall be the ones defined on the design and
should be imported or from site excavations. The borrow pits chosen by the Contractor
should be previously submitted to the Supervision for approval. The materials to for the
backfill must be preferably insensitive to water (which determines that the percentage of
the material passing the sieve nr. 200 can not exceed 30%) especially when there is the
possibility of floods and/or soaking the adjacent land. Also materials to be used must
have geologic characteristics which allow them to reach immediately after their
assembly the strengths, in particular the mechanical, assuring the relevant requirement.
This means that materials must be correctly spread and compacted bearing in mind that
is necessary a maximum dimension ho allows the layers to be leveled and that its
thickness is compatible with the power of the rollers used.
The soils or materials to be used shall be clean of branches, leaves, trunks, roots, herbs,
rubbish or organic debris and the maximal dimension of the material elements to be
applied shall not be higher than 2/3 of the layer thickness once compacted. At the sides
materials compatible with the estimated slopes geometry shall be used so that instability
and or erosion risks can be avoid. When by economic and/or environmental reasons it is
absolutely necessary to reuse currents soils (fine and sensitive to water) for backfill
construction, with high water contents in its natural state, treatment techniques can be
used (in situ or in the plant) with lime or hydraulic binders can be used in order to
guarantee the traffic conditions and to reach the required conditions for its placement on
site.
The materials for backfill are (under a grading point of view) soils, rock materials (rock
fill) and hardcore materials. Under this specification soils mean the materials that mustfulfill the condition in which the material retained by the sieve 19 mm (3/4") ASTM to
be less than 30%. Regarding the water content, in its natural state, can be observed:
Soils incoerentes: 0.8 WopmWnat1.2 Wopm
Soils coerentes: 0.7 WopnWnat1.4 Wopn
where:
Wopm- optimum water content referring to the Modified Proctor test
Wopn- optimum water content referring to the Normal Proctor test
-
8/13/2019 Bo Teza Tu Cristian
38/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 34 -
Whenever this requirement is not verified on the currents soils case treatment
techniques with lime or lime combined with cement can be used.
Considering its reuse for backfill and also the definition of the assembly conditions the
rocky materials can be characterized as to determine their strength characteristics,
fragility and changeability. The material to be used in rock backfill should come from
the excavation areas and shall be homogeneous, of high quality, without waste, organic
matters or any other harmful substances.
Under a grading point of view the hard core materials shall be those showing a
continuous grading and obeying to the following grading conditions:
Material retained by sieve 19 mm (3/4") ASTM - between 30% and 70%;
Material passing the sieve 0,075 mm (no 200) ASTM - between 12% and 40%;
The maximum dimension of the blocks shall not exceed 2/3 of the thickness of the
layer after compaction not to be superior to 0.40 m.
These materials which are formed by a mixture of soils and rock and that usually come
from blasting shall comply with the required specification for each fraction, rock or soil.
Rocky materials (rock fills) are not allowed at the completion of the "earth fills"
execution. It is also forbidden the use of the "sandwich" type continuous and alternated
use of different materials in order to guarantee a uniform and continuous behavior of the
embankment. On the top of backfill to a thickness between 40 to 85 cm soils with
higher geotechnical characteristics shall be used.
Sandwich embankments are those using different materials whose characteristics and
location are defined in the design. Examples that can be given: the fill where the body is
formed by materials of the hardcore soils type and the sides by rocky materials or the
backfill body built with soils, the sides built with treated soils. Characteristics admitted
in design regarding properties content are pure compression, point load test; porosities,
volume and expandability must be checked on site. Special concern must also be given
to crushing strength, wearing at a moister environment.
Technical fill are those to be carried out in difficult access areas where it is impossibleto operate normally with current spreading and compaction equipment. Among other
-
8/13/2019 Bo Teza Tu Cristian
39/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 35 -
technical fills are those near abutments or any other buried structure type as well as
those near retaining walls, small or big diameter hydraulic passages, cattle creeps, etc.
3.7.2 Aggregates
One definition of an aggregate is that it is a material such as broken stone, slag, gravel,
sand or other like which, when held together by a binding agent, forms a substantial part
of such materials as concrete, asphalt, coated macadam or like. This definition means
that any hard material, whether it is natural or artificial, may be classified as an
aggregate. In practice, however, the materials suitable for use as road aggregates may be
limited in a particular area.
By far the majority of road aggregates are formed from natural rock. Geologists have
classified rocks into three main groups, based on their method of origin; these are
known as igneous, sedimentary and metamorphic rocks.
Igneous rocks were formed at or below the earth's surface by the cooling of molten
material, called magma, which erupted from, or was trapped, beneath the earth's crust.
Igneous rocks formed at the earth's surface when the magma came into contact with the
atmosphere are called extrusive rocks, while those formed below the earth's surface are
intrusive rocks. Extrusive magma cooled rapidly at the earth's surface and as a result the
rocks formed are very often glassy or vitreous (without crystals) or partly crystalline
and partly vitreous. In contrast with the extrusive rocks, the intrusive rocks are entirely
crystalline, having been formed as a result of the magma cooling slowly under the
protective cover of the earth's crust. Igneous rocks can also be separated on the basis of
their being acidic or basic depending of silica (SiO) content. In preparing bituminousmixtures, acidic aggregates can be difficult to coat with binder in contrast with the
hydrophobic or water-hating aggregates formed from a rock such as basalt.
Sedimentary rocks were formed when the products of disintegration and/or
decomposition of any type of rock were transported and redeposit, and then
consolidated or cemented into a new rock type. Sedimentary rocks may be sub-divided
by various means, but from the highway engineer's point of view the most convenientone is that based on the predominant rock mineral. This allows three main rock sub
-
8/13/2019 Bo Teza Tu Cristian
40/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 36 -
classifications, the calcareous, siliceous and argillaceous groups. Calcareous rocks were
formed as the result of great thicknesses of the remains of small marine animals being
deposited on the ocean floors. It is most suitable as an aggregate for bituminous
surfacing. The predominant mineral is calcite, CaCO, and this renders the rocks basic
and in general it is most suitable as an aggregate for bituminous surfacing. Some types
of calcareous rocks, are however too porous to be used as road aggregates.
Siliceous rocks were formed from deposits of sand and silt which became lithified as a
result of pressure by overlying strata, or by the deposition of cementing material
between the grains. The predominant mineral in these rocks is either quartz or
chalcedony, both SiO, and this may tend to make adhesion between these aggregates
and bituminous binders relatively difficult.
Argillaceous rocks are those who formed when fine-grained particles of soil were first
deposited as clays or mud and then consolidated by pressure from overlying deposits.
They are rarely used as road aggregates, and never in bituminous surfacing. Also
included under the title of sedimentary rocks are the natural gravels and sands.
Metamorphic rocks are igneous or sedimentary rocks which, as a result of being
subjected to tremendous heat (thermal metamorphism), or heat and great pressure
combined (regional metamorphism), were transformed into new types of rock by the re
crystallization of their constituents. Metamorphism in any particular instance may have
been aided by the presence of permeating solvents which worked through the rock and
promoted new mineral growth. Metamorphic rocks which were altered by heat alone are
in considerable demand as road aggregates.
Aggregates can also be divided in groups like basalt, flint, gabbro, granite, gritstone,
hornfels, limestone, porphyry, quartzite and schist group. Each one of these groups has
a specific number of members.
The aggregates used in construction in general must be clean, hard, not due to changes
under the action of weather agents, of uniform quality and free of decomposed
materials, of organic matter and other harmful substances. The use of non-traditionalgranular materials, such as demolition products, crushed concrete, slag of steelworks,
-
8/13/2019 Bo Teza Tu Cristian
41/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 37 -
not foreseen in the project of the highway, may be approved as long as the proposal for
its use is duly justified.
The concept of nominal dimension (d/D) means that it is admissible up to 10% of the
material retained in the sieve of larger dimensions (D) and up to 10% of the material
that passes through the sieve of smaller dimensions (d); however, the addition of the
two percentages must be less than 15%.
The use of crushed pebbles in bituminous mixture it is conditioned by the use of an
additive in the bitumen, in order to ensure the adequate adhesion to the bituminous
binder. The checking will be carried out from Marshall Stability tests, before and after
immersion of the Marshall Test specimens in water at 60Cfor 24 h, where the quotient
of the stability values of the normal test and of the post-immersion test should be equal
to or greater than 75% (variant to the test ASTM D 1075). Besides the Marshall test will
have to be carried out the test of passive adhesion, where the mixture of aggregates with
filler and bitumen is placed inside a container with water at 100 C and stirred for 2 min
and by visual observation shall be made an analysis of the percentage of bitumen
displaced from the particles of aggregates. The adhesion shall be considered if there is
no ungluing of the bitumen particles. For mortars and concrete in Portugal the
aggregates must be in compliance with the specification LNEC E 373, where is
mentioned that 50% of the sand must be of siliceous nature.
3.7.3 Bituminous binders
The most careful specifications with regard to the design and construction of a
bituminous road surfacing are of little value if the properties of the bituminous binderused in the design are not adequately controlled. To aid the engineer in ensuring that the
material obtained has the desired qualities, a number of tests have been devised which
attempt to measure various binder properties for particular reasons. As is unfortunately
the case with so many highway engineering test specifications, there are variations from
organization to organization with regard to how exactly these binder tests should be
carried out, although there is general agreement as to their significance. Most usually
tests on binders are those regarding consistency (penetration, viscosity and softening
-
8/13/2019 Bo Teza Tu Cristian
42/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 38 -
point tests), composition (distillation, water content, loss-on-heating, ash content and
solubility tests), specific gravity test andflash and fire point tests.
The material supply on site must always be accompanied by a test bulletin, which
characterizes the fabrication lot. The supplied material must be in compliance with the
given provisions. The characteristics of the bitumen must be in compliance with the
specification LNEC E 80 - Laboratorio Nacional de Engenharia Civil (National
Laboratory of Civil Engineering). The bitumen in use must be of the type defined on the
Road project, normally 35/50 or 50/70 for all bituminous mixtures or 160/220 in the
cases when it is destined to the execution of superficial surfacing or semi-penetrations.
In the case of bituminous mixtures of high module, the bitumen to be used shall in
principle be of the type 10/20 and possibly with additive. The use of bitumen of a type
different from those given will be limited to the implementation of possible proposals
by the Contractor, dully justified and submitted for the approval of the Supervision. The
tests bulletin, which accompanies the supply of the bitumen, must always state the
temperatures at which the material presents the viscosity of 170 20 cSt and of 280
30 cSt.
Modified bitumen used in the production of bituminous mixtures (draining, roughened,
etc.) it is modified with polymers be in compliance with the given provisions. For
example the bituminous binder used in draining bituminous mixtures must have
modifiers that grant to the mixture a smaller thermal susceptibility, a greater flexibility
and to improve other characteristics. These specifications which must be complied for
bituminous binder used in draining bituminous mixtures are:
a) Penetration, at 25 C, 100g, 5s (0.1 mm) 55-70
b) Softening temperature, minimum 55Cc) Fragility point of Frass, maximum -10C
d) Plasticity interval, minimum 65C
e) Viscosity, at 135 C, minimum 850 cSt
f) Stability in storage difference on the value of temperature
of softening, maximum 5C
g) Elastic recovery, at 25 C, minimum 25%
-
8/13/2019 Bo Teza Tu Cristian
43/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 39 -
Fluidized bitumen must have his characteristics in compliance with the specification E
98 of LNEC. The fluidized bitumen to be used in impregnation irrigation of granular
base must be of the type defined on the Paving project, normally MC-30 or MC-70.
The bituminous emulsions can be used in impregnating coats, in tack coats, semi-
penetrations, superficial bituminous surfacing, stabilization of base, curing of base
treated with cement, gluing and impregnation of geo-textiles, as well as in bituminous
mixtures or micro-agglomerates at low temperature. As an example for impregnating
coats of granular base, the emulsion to be used must be a cationic type with low
viscosity and slow failure or for tack coats the emulsion used must be of the cationic
type with sudden failure normally type ECR - 1.
Modified bituminous emulsions must be storage in a system which is provided with the
necessary means to ensure its stability and the non-sedimentation of the bitumen
particles. The distillation residue in this type of emulsions must be obtained by
evaporation at 163 C. The characterization tests of these products must be carried out
in a laboratory, which is certified or approved by the Supervision. Usually these
modified bituminous emulsions are used for tack coats, bituminous micro-agglomerate
at low temperature or superficial surfacing and for gluing and impregnation of geo-
textiles (with the purpose of with the purpose of obtaining an anti-cracking interface).
The emulsion used in tack coats for gluing irrigation between a bituminous layer with
modified bitumen and another bituminous layer must be a bituminous emulsion
modified with the incorporation of adequate polymers, in order to grant a high adhesion
power and the bituminous emulsion used in the gluing and impregnation of geo-textiles
shall be in principle of the cationic type of sudden failure, modified with theincorporation of adequate polymers.
3.7.4 Hydraulic binders
The most used hydraulic binder is without any doubt the cement. Cement is a material
which, if added in a suitable form to a no coherent assemblage of particles, will
subsequently harden by physical or chemical means and bind the particles into a
coherent mass. This definition, which is very broad in scope, allows such diverse
-
8/13/2019 Bo Teza Tu Cristian
44/130
Project, Construction and Quality Control in Highway Infrastructure Botezatu Costel-Cristian
- 40 -
materials as bitumen, tar and lime to be grouped together under the umbrella of
cement. In road construction these are used mainly in soil stabilization. For this
reason will use the term cement to refer only to the Portland and high-alumina cement