MICE VC 10-Oct-2013 Alain Blondel 1 MICE NEWS VC 162 S OF THINGS HAPPENED! e arrived at RAL: EMR (see report today) AFC2 see pictures SS2 see pictures RF amplifier from Daresbury (see pictures) been published emittance measurement paper been passed Magnetic field mitigation review (see also MICE note 419) Tom Taylor et al endorsed decision to go ahead with Partial Return Yoke warned of potential forces to magnets (report is posted on indico page under my name) http://indico.cern.ch projects MICE field mitigation review e been burned HTS lead on SS1 magnet warm up, new leads in order (4 weeks) (not new) Decay solenoid had a burned cold lead: requires opening and surger to be repaired until February/April 2014

description

MICE NEWS VC 162. LOTS OF THINGS HAPPENED! have arrived at RAL: -- EMR (see report today) -- AFC2 see pictures -- SS2 see pictures -- RF amplifier from Daresbury (see pictures) has been published -- emittance measurement paper has been passed - PowerPoint PPT Presentation

Transcript of MICE NEWS VC 162

Page 1: MICE NEWS VC 162

MICE VC 10-Oct-2013 Alain Blondel 1

MICE NEWS VC 162

LOTS OF THINGS HAPPENED!

have arrived at RAL:-- EMR (see report today)-- AFC2 see pictures-- SS2 see pictures-- RF amplifier from Daresbury (see pictures) has been published -- emittance measurement paper

has been passed -- Magnetic field mitigation review (see also MICE note 419) Tom Taylor et al endorsed decision to go ahead with Partial Return Yoke warned of potential forces to magnets (report is posted on indico page under my name) http://indico.cern.ch projects MICE field mitigation review

have been burned-- HTS lead on SS1 magnet warm up, new leads in order (4 weeks)-- (not new) Decay solenoid had a burned cold lead: requires opening and surgery. to be repaired until February/April 2014

Page 2: MICE NEWS VC 162

MICE VC 10-Oct-2013 Alain Blondel

Provisional MICE SCHEDULE update: June 2013

STEP I

STEP IV

(possibly w/o field: Q2 2014) Q1 2015to Q1 2016

STEP VI

Run date:

EMR run Oct 2013

Under construction:

Target date Q3 2019Step V run possible 2018

Slip since october 2012 = 2 months

we are here!

Page 3: MICE NEWS VC 162

MICE VC 10-Oct-2013 Alain Blondel 3

Page 4: MICE NEWS VC 162

MICE VC 10-Oct-2013 Alain Blondel 4

AFC2 at RAL

John Cobb: “it looks just like #1”

AFC1 did not pass the acceptance criteria and will be sent back to Tesla

Page 5: MICE NEWS VC 162

MICE VC 10-Oct-2013 Alain Blondel 5

RF amplifier from Daresbury

First amplifier installed last week

Simplified TIARA configuration accepted by RF group - powering into one load reduces stress on deadline and uses fewer components and decouples from mods to mezzanine floor.

Waveguides and dummy load components received from UMISS last week

Prefabricated water panel arrives from DL end next week

Air system components are all here,

Installation can begin after EMR run #2

(i.e. next week)

Page 6: MICE NEWS VC 162

MICE VC 10-Oct-2013 Alain Blondel 6

installation of first MICE RF amplifier behind the north wall (=right bank of the «muon river»)

Page 7: MICE NEWS VC 162

MICE VC 10-Oct-2013 Alain Blondel 7

Dear MICE,

I'm sure you'll all be very happy to hear that the emittance paper has now been published in EPJC, and is viewable at

http://dx.doi.org/10.1140/epjc/s10052-013-2582-8 http://link.springer.com/article/10.1140%2Fepjc%2Fs10052-013-2582-8

Many, many thanks to everyone who helped get it there!

Best, Victoria

Page 8: MICE NEWS VC 162

MICE VC 10-Oct-2013 Alain Blondel 8

Page 9: MICE NEWS VC 162

MICE VC 10-Oct-2013 Alain Blondel 9

Upcoming MICE VCs

Thursday 24 October we will have a special MICE Video conferenceto present the main conclusions of the reports to MPB and RLSR

Next collaboration meeting 6-8 November Organization: V. Blackmore, A-B. J. CobbSoftware workshop 4-5 November.

registration is open

-- 13 November RLSR -- 14 November MPB -- 15 November FAC

Upcoming Agenda