[2] CE 124 part 1
-
Upload
chrislene-divino-calivo -
Category
Documents
-
view
221 -
download
0
Transcript of [2] CE 124 part 1
-
8/6/2019 [2] CE 124 part 1
1/41
PROGRESS REPORT NO. 8April 2001
CONSTRUCTION SUPERVISION OF
RIZAL/ARGONAUT HIGHWAY
WIDENING AND SBF EXPRESSWAY
EXTENSION PROJECT
Cabunilas, Anfy M.Calivo, Chrislene D.
-
8/6/2019 [2] CE 124 part 1
2/41
-
8/6/2019 [2] CE 124 part 1
3/41
-
8/6/2019 [2] CE 124 part 1
4/41
PROJECT DATA
Construction of Rizal / Argonaut Highwayand SBF Expressway Extension
Contract Package RB-01
Existing road consisted of asphalt pavedroad with some sections showing defectsand a new construction (By-Pass section)
approx. 1.22 km
-
8/6/2019 [2] CE 124 part 1
5/41
PROJECT PROFILE 3 existing roads: from 2 to 4 lanes, aggre.
length = 4.22 km
improvement of 1.737 km existing roadsection
new construction of 1.81 km by-pass road
construction of: 6 new concrete bridges, bored pile found.,
approx. total length = 415.60 m 6 utility bridges on 4 bridge locations
relocation of affected existing public utilities
signalized intersections on 6 major junctions
-
8/6/2019 [2] CE 124 part 1
6/41
-
8/6/2019 [2] CE 124 part 1
7/41
REASON FOR SLIPPAGE
Delay in the issuance of the Tree CuttingPermit
resolved only last February 15, 2001
4 month time extension subject for
approval by FAPO-PMO
-
8/6/2019 [2] CE 124 part 1
8/41
RECOMMENDATION
Mobilize more equipment
construction of bridges and by-pass
section
-
8/6/2019 [2] CE 124 part 1
9/41
-
8/6/2019 [2] CE 124 part 1
10/41
PROJECT UPDATE
As of April 30, 2011:
slippage: -33.64%
actual cum. accomplishment: 15.88% sched. accomplishment: 49.520%
Revised Bar Chart/S-Curve:
slippage: -2.259%
actual accomplishment: 15.879% sched. accomplishment: 18.138%
% time elapsed: 41.228%
-
8/6/2019 [2] CE 124 part 1
11/41
-
8/6/2019 [2] CE 124 part 1
12/41
CONTRACTORS
WORKACCOMPLISHMENT
-
8/6/2019 [2] CE 124 part 1
13/41
PART A. FACILITIES FOR THEENGINEER
Operations and Maintenance of FieldOffice, Laboratory, and Staff Quarters
Operation and Maintenance of ServiceVehicles
Furnishing of Progress Photographs
-
8/6/2019 [2] CE 124 part 1
14/41
PART C. EARTHWORKS
Road Section A (Basin St.Binictican Br.)
clearing and grubbing, Sta. 0+340.00Sta.
0+560.00
-
8/6/2019 [2] CE 124 part 1
15/41
PART C. EARTHWORKS
Road Section C (Boton Br.By-Pass Rd.)
excavation, common materials (Sta. 0+595
Sta 0+770)
rock embankment (Sta. 0+980Sta. 1+280)
granular materials formation (Sta. 1+586
Sta. 1+793)
laying of RCPC, various diameters construction of RCBC, Sta. 1+300.00
-
8/6/2019 [2] CE 124 part 1
16/41
PART C. EARTHWORKS
Road Section D (Boton Br.Tarlac Rd.)
removal of existing trees
-
8/6/2019 [2] CE 124 part 1
17/41
PART F. BRIDGECONSTRUCTION
Kalalake Bridge
bored pile construction at Abutment A
Installation of reinforcing steel for pile cap
at Pier 1
Removal of Structure/Obstruction
-
8/6/2019 [2] CE 124 part 1
18/41
PART F. BRIDGECONSTRUCTION
Malawaan Viaduct
bored pile construction at Pier 5, bore hole
no. 2
installation of reinforcing steel and pouring
of concrete for Prestressed Type V AASHTO
Girders
construction craneway
-
8/6/2019 [2] CE 124 part 1
19/41
PART F. BRIDGECONSTRUCTION
Boton 1 Bridge
bored pile construction, Abutment A
casting of Prestressed concrete girder
Malawaan 2 Bridge
preparation works for pile bent driving the
Detour Bridge
-
8/6/2019 [2] CE 124 part 1
20/41
PART F. BRIDGECONSTRUCTION
Binictican Bridge
construction of Abutments A & B of the
Utility Bridge
construction of Detour Bridge and
Approaches
-
8/6/2019 [2] CE 124 part 1
21/41
PART G. DRAINAGE AND
SLOPE PROTECTIONSTRUCTURES
Construction of Type A Lined Canal atBasin St.Binictican Rd.
BotonBy-Pass Rd.:
excavation for pipe
structural excavation for box
laying of pipe culverts
construction of RCBC, Sta. 1+300.00
-
8/6/2019 [2] CE 124 part 1
22/41
PART I. SPECIAL PROVISIONS
Installation of concrete pedestal for streetlighting
-
8/6/2019 [2] CE 124 part 1
23/41
PART K. RELOCATION ANDINCLUSION OF PUBLIC UTILITIES
Telecom
excavation for conduits and manhole
Electrical
provision and erection of concrete electric
poles
Water Line
construction of sewage lift station
-
8/6/2019 [2] CE 124 part 1
24/41
OTHER ACTIVITIES
Cutting and bending of reinforcing barsfor bridges, culverts, and manholes
Pre-casting of street lights and streetpedestals
Pre-casting of concrete sheet piles
-
8/6/2019 [2] CE 124 part 1
25/41
PROJECTDESCRIPTION
-
8/6/2019 [2] CE 124 part 1
26/41
A. ROADWORKS 3 existing road sections: from 2 to 4 lanes
const. of a by-pass road that runs on a newalignment
SECTIONS: Basin St.Binictican Bridge(Rizal Hway, ~2.26
km) George Dewey St.Causeway St. (Argonaut
Hway, ~1.19 km)
BotonTarlac Section (Argonaut Hwayextension, ~2.34 km) BinicticanBoton Section (By-Pass Rd., ~1.22
km)
-
8/6/2019 [2] CE 124 part 1
27/41
B. BRIDGES
Kalalake Bridge (along Argonaut Hway)
47.74 m, three-span
superstructure resting on 2 bored piles
(1200mm dm. by 44 m, 1500mm dm. by 49
m resp.)
span 1: 16.00m RDG girder; span 2: 18.40
steel girder; span 3: 12.50m RCDG existing will be removed and replaced
-
8/6/2019 [2] CE 124 part 1
28/41
B. BRIDGES
Binictican Bridge (along Rizal Hway)
30.80 m, 3-span
bored piles: 1000mm by 40.0m, at piers and
400mm by 400mm precast piles, ~30.0 m
long abutments
deck is flat slab
-
8/6/2019 [2] CE 124 part 1
29/41
B. BRIDGES
Malawaan Bridge (along ArgonautHway)
25.80 m, 3-span
bored piles: 1000mm by 40.0m, at piers and
precast piles, 30.0 m long at abutments
deck is flat slab
-
8/6/2019 [2] CE 124 part 1
30/41
B. BRIDGES
Boton II Bridge (along Argonaut Hway)
40.80 m, 5-span
bored piles: 900mm by 47.0 m, at piers and
precast piles, 47.0 long at abutments
deck is flat slab
-
8/6/2019 [2] CE 124 part 1
31/41
B. BRIDGES
Malawaan Viaduct (along the By-PassRd.)
240 m, 7-span
bored piles: 1800mm by 43.0 m
prestressed concrete girders, 32 m long
-
8/6/2019 [2] CE 124 part 1
32/41
B. BRIDGES
Boton I Bridge (Along the By-Pass Rd.)
singe-span, 32.90m
bored piles: 1800mm by 44 m
prestressed concrete girders 32.0 m long
-
8/6/2019 [2] CE 124 part 1
33/41
C. CRANEWAY
made of coco logs
Malawaan Viaduct, Kalalake Bridge
(made of steel sheet piles)
Boton I Bridge (using Steel H-Piles)
-
8/6/2019 [2] CE 124 part 1
34/41
D. DETOUR ROADS ANDBRIDGES
locations:
Boton II
Malawaan II
Binictican
-
8/6/2019 [2] CE 124 part 1
35/41
E. UTILITY BRIDGES
Along:
Binictican
Boton II
Malawaan II
Kalalake
-
8/6/2019 [2] CE 124 part 1
36/41
F. UTULITIES
Water and Sewer Pipelines
Fuel Pipelines
Elecrical Poles and Cables
Telecom Cable
CATV Cables
-
8/6/2019 [2] CE 124 part 1
37/41
-
8/6/2019 [2] CE 124 part 1
38/41
-
8/6/2019 [2] CE 124 part 1
39/41
-
8/6/2019 [2] CE 124 part 1
40/41
-
8/6/2019 [2] CE 124 part 1
41/41