Welcome to the Public Scoping Meeting LAX United Airlines (UAL) East Aircraft Maintenance and Ground Support Equipment (GSE) Project Tuesday, December 19, 2017 6:00 pm to 8:00 pm

Transcript of Public Scoping Meeting LAX United Airlines (UAL) East ... · Source: United Airlines, FSB, July...

Page 1: Public Scoping Meeting LAX United Airlines (UAL) East ... · Source: United Airlines, FSB, July 2017. Prepared by: CDM Smith, November 2017. DN Legend AIRCRAFT MAINTENANCE BUILDING

Welcome to the Public Scoping Meeting

LAX United Airlines (UAL) East Aircraft Maintenance and Ground Support

Equipment (GSE) Project

Tuesday, December 19, 2017 6:00 pm to 8:00 pm

Page 2: Public Scoping Meeting LAX United Airlines (UAL) East ... · Source: United Airlines, FSB, July 2017. Prepared by: CDM Smith, November 2017. DN Legend AIRCRAFT MAINTENANCE BUILDING

Public Workshop Objectives

� Provide information about the LAX United Airlines East Aircraft Maintenance and GSE Project

� Provide information on the California Environmental Quality Act (CEQA) process

� Discuss Initial Study conclusions and environmental resource areas being carried forward in the Draft EIR

� Collect community comments on the information and analyses presented in the Initial Study

Page 3: Public Scoping Meeting LAX United Airlines (UAL) East ... · Source: United Airlines, FSB, July 2017. Prepared by: CDM Smith, November 2017. DN Legend AIRCRAFT MAINTENANCE BUILDING

Project Site and Purpose

� Consolidate existing UAL aircraft maintenance facilities into one facility on an existing UAL leasehold.

� Modernize UAL’s existing East Maintenance Facility.

Pershing Dr

Imperial Hwy

Westchester Pkwy

Sep

ulve

da B

lvd

World Way West

Century Blvd

Avia

tion

Blv

d

Lincoln Blvd

Runway 6L-24R

Runway 6R-24L

T3T1

T4 T5 T6 T7 T8

TBIT

Runway 7R-25L

Runway 7L-25R

Arbor Vitae St

Airp

ort B

lvd

98th St

96th St

T2

LAX/El Segundo

Dunes

Vista del Mar

Century Fwy

111th St

La C

iene

ga B

lvd

Manchester Ave

PacificOcean

42

PROJECTSITE

WESTCHESTER

1

405

105

PLAYA DEL REYO0 0.25 0.5

Miles

Legend UAL East Maintenance Facility UAL West Maintenance Facility LAX Property BoundarySource: CDM Smith, November 2017. Prepared by: CDM Smith, November 2017.

Page 4: Public Scoping Meeting LAX United Airlines (UAL) East ... · Source: United Airlines, FSB, July 2017. Prepared by: CDM Smith, November 2017. DN Legend AIRCRAFT MAINTENANCE BUILDING

Figure

8LAX UAL East Aircraft Maintenance and GSE Project Proposed Floor Plan - Level 2

Source: United Airlines, FSB, July 2017.Prepared by: CDM Smith, November 2017.

NDND

Legend

AIRCRAFT MAINTENANCE

BUILDING FUNCTION

CIRCULATION

FACILITIES MAINTENANCE

GSE

OTHER

STORES

SHARED

Parking Structure F

United Airlines Cargo

Roof

HangarRoof

OPEN BELOW

Proposed Project Components � Demolish the existing buildings associated with the East Maintenance Facility

� Quonset Hut will not be affected

� Construct and operate a new aircraft and GSE maintenance facility, totaling approximately 411,000 square feet to include:

� Two wide-body aircraft hangar bays and permanent GSE maintenance facility

� Aircraft maintenance shops, aircraft parts/supplies stores, fire suppression water tank, and supportive facilities

� The new maintenance building will be designed to meet LEED Silver standards

� Relocate provisioning (i.e., storage) to a portion of the exisiting UAL Cargo building

Facility

Existing Facilities Proposed Facilities

Approximate Building Area (ft²)

Aircraft Parking Positions

Approximate Building Area (ft²)

Aircraft Parking Positions

West Maintenance Facility 593,046 15 NA NA

East Maintenance Facility 133,750 19 411,000 23

Total 728,796 34 411,000 23

Figure

7LAX UAL East Aircraft Maintenance and GSE Project Proposed Floor Plan - Level 1

Source: United Airlines, FSB, July 2017.Prepared by: CDM Smith, November 2017.

Legend

AIRCRAFT MAINTENANCE

AIRCRAFT MAINTENANCE HANGAR

BUILDING FUNCTION

CIRCULATION

EXTERIOR

FACILITIES MAINT.

GSE

OTHER

SHARED

STORES

Parking Structure F

United Airlines Cargo

United AirlinesCargoYard

GSE Yard

Stores Yard

Hangar

Avion Drive

PROPOSED LEVEL 1 FLOOR PLAN

PROPOSED LEVEL 2 FLOOR PLAN

Page 5: Public Scoping Meeting LAX United Airlines (UAL) East ... · Source: United Airlines, FSB, July 2017. Prepared by: CDM Smith, November 2017. DN Legend AIRCRAFT MAINTENANCE BUILDING

� Apron improvements

� Replace/resurface/restripe a portion of the apron area

� Reconfigure the apron and include aircraft parking positions in the hangar

� Total of 23 future aircraft parking positions on the leasehold

� Construct a jet blast deflector (also called a blast fence)

� Relocate, remove, and install utilities

� Vacate the east-west portion of Avion Drive north of Parking Lot H

� Relocate employee parking to Parking Structure F, located at the southeast corner of Century Boulevard and Avion Drive

Proposed Project Components

CONCEPTUAL SITE PLAN

Page 6: Public Scoping Meeting LAX United Airlines (UAL) East ... · Source: United Airlines, FSB, July 2017. Prepared by: CDM Smith, November 2017. DN Legend AIRCRAFT MAINTENANCE BUILDING

CEQA Overview

� Purpose is to inform decision-makers, agencies, organizations, and the public of the environmental effects of a project

� Applies to discretionary projects

� Identifies potential effects on the environment

� Identifies ways to avoid or reduce potential significant effects through mitigation measures or alternatives

No Impact/Less Than Significant(No Further Analysis)

Analysis Being Carried Forward in EIR

�Aesthetics �Agricultural/Forestry Resources �Biological Resources �Cultural Resources

� Archaeological Resources � Paleontological Resources

�Hydrology and Water Quality � Land Use and Planning �Mineral Resources �Noise �Population and Housing �Public Services �Recreation

�Air Quality �Cultural Resources

� Historical resources �Greenhouse Gas Emissions � Transportation/Traffic �Cumulative Impacts

�Geology and Soils �Hazards and Hazardous Materials

� Tribal Cultural Resources �Utilities and Service Systems

�Other CEQA Considerations

Page 7: Public Scoping Meeting LAX United Airlines (UAL) East ... · Source: United Airlines, FSB, July 2017. Prepared by: CDM Smith, November 2017. DN Legend AIRCRAFT MAINTENANCE BUILDING

Schedule & Anticipated Milestones

NOP/Initial Study

Draft EIR

Final EIR

Start of Construction

Public Release December 7, 2017

Scoping Meeting December 19, 2017

Public Release Mid-2nd Quarter 2018

Late 3rd Quarter 2018

4th Quarter 2018

We Are Here

Page 8: Public Scoping Meeting LAX United Airlines (UAL) East ... · Source: United Airlines, FSB, July 2017. Prepared by: CDM Smith, November 2017. DN Legend AIRCRAFT MAINTENANCE BUILDING

Public Comments on the NOPComments can be submitted:

� At this Scoping Meeting on comment cards � Online at: http://www.lawa.org/ourLAX/Comments.aspx � Mailed to the following contact:

Los Angeles World Airports Attention: Maritza Lee, Project Planner One World Way, P.O. Box 92216 Los Angeles, CA 90009-2216

Comments must be received by (not postmarked by) 5:00 pm, Monday, January 8, 2018