PMI - 14-10-08
Transcript of PMI - 14-10-08
-
7/31/2019 PMI - 14-10-08
1/76
POWER PROJECT MANAGEMENT
PROGRAMME OF PMI
PROJECT APPROVAL
PROCESS
G. Krishna MoorthyDGM (CP)
14th October, 2008
-
7/31/2019 PMI - 14-10-08
2/76
PROJECT FORMULATION ANDAPPROVAL
Need for New Capacities
Site Selection
Preparation of Feasibility Report
Thermal Projects Tie-ups / Clearances
Hydro ProjectsTie-ups / Clearances Investment Approval
-
7/31/2019 PMI - 14-10-08
3/76
Need for New Capacities
G
-
7/31/2019 PMI - 14-10-08
4/76
Growth of installed capacity inIndia
1362 1713 4653
12957 16664
28448
63636
105046
132329
143061
19 4 7 19 50 19 6 1 19 6 9 19 74 19 8 0 19 9 0 2 0 0 2 2 0 0 7 Jun-0 8
(Figures in MW)NTPC starts adding
capacity in 1982
-
7/31/2019 PMI - 14-10-08
5/76
Fuel wise break-up (MW)
(Excluding captive capacity of 14636 MW connected to grid)
Thermal 91,907 64.2%
Hydro 35,909 25.1%
Nuclear 4,120 2.8%
Renewable 11,125 7.9%
TOTAL 143,061 100.0%
Sector wise break-up (MW)
State
Sector
52%
Private
Sector
14%
Central
Sector
34%
Total generation in 2007-08 704.45 BU
(All figures provisional from CEA)
Power Infrastructure in India
-
7/31/2019 PMI - 14-10-08
6/76
ALL INDIA POWER SUPPLY POSITION - PEAK
Period Peakdemand
(MW)
Peak Met
(MW)
Peak deficit/ surplus
(MW)
Peak deficit/ surplus
(%)
9th Plan end 81555 71262 -10293 -12.6
2002-03 81492 71547 -9945 -12.2
2003-04 84574 75066 -9508 -11.2
2004-05 87906 77652 -10254 -11.7
2005-06 93255 81792 -11463 -12.3
2006-07 100715 86818 -13897 -13.8
2007-08 108866 90793 -18073 -16.6
-
7/31/2019 PMI - 14-10-08
7/76
PEAK DEMAND /PEAK MET
NR (In MW)
-9.1-29672949532462NorthernRegion
-4.2-5011501200Uttarakhand
-22.8-2536856811104UP
-12.8-81555596374Rajasthan -15.4--133273408672Punjab
-25.9-50614441950J&K
-4.8-5110101061HP
-2.7-13548214956Haryana
-1.1-4540304075Delhi
00275275Chandigarh
Surplus/Deficit (-)(MW) (%)
Peak MetPeak DemandApril-March 2008State
-
7/31/2019 PMI - 14-10-08
8/76
PEAK DEMAND/PEAK METWR (In MW)
-23.2-88922938538277WesternRegion
-10.7-49408457Goa
-26.4-48661357518441Maharashtra
-10.6-76464367200MP
-26.7-3234888512119Gujarat
-9.6-23321882421Chhattisgarh
Surplus/Deficit (-)(MW) (%)
Peak MetPeakDemand
April-March 2008State
-
7/31/2019 PMI - 14-10-08
9/76
PEAK DEMAND/PEAK MET
SR (In MW)
-9.0-24092436826777SouthernRegion
0.00276276Pondichery
-15.9-1644869010334Tamil Nadu
-6.0-17627422918Kerala
-15.4-101655676583Karnataka
-9.2-929916210091AP
Surplus/Deficit (-)(MW) (%)
Peak MetPeakDemand
April-March 2008State
-
7/31/2019 PMI - 14-10-08
10/76
PEAK DEMAND/PEAK METER (In MW)
-10.4-12411069911940EasternRegion
-9.8
-4.3
-525
-3
4854
66
5379
69
West
Bengal+Sikkim
-1.4-4129392980Orissa
-14.2-123742865Jharkhand
-2.6-4918031852DVC
-32.7-60412431847Bihar
Surplus/Deficit (-)(MW) (%)
Peak MetPeakDemand
April-March 2008State
-
7/31/2019 PMI - 14-10-08
11/76
PEAK DEMAND/PEAK MET
NER (In MW)
--16.6-1807390793108866ALL India
--22.7-39513471742NE-Region
--17.5-30141171Tripura
-3.3-38891Nagaland
-40.2-395897Mizoram
--38.7--176279455Meghalaya
-18.5-2297119Manipur
-9.7-82766848Assam
-25.7-2675101ArunachalPradesh
Surplus/Deficit (-)(MW) (%)
Peak MetPeakDemand
April-March 2008State
-
7/31/2019 PMI - 14-10-08
12/76
ALL INDIA POWER SUPPLY POSITION - ENERGY
Period Energy
Requirement(MU)
Energy
Availability(MU)
Energy
deficit /surplus
(MU)
Energy
deficit /surplus
(%)
9th Plan end 522537 483350 -39187 -7.5
2002-03 545983 497890 -48093 -8.8
2003-04 559264 519398 -39866 -7.1
2004-05 591373 548115 -43258 -7.3
2005-06 631757 578819 -52938 -8.4
2006-07 690587 624495 -66092 -9.6
2007-08 737052 664660 -72392 -9.8
-
7/31/2019 PMI - 14-10-08
13/76
ACTUAL POWER SUPPLY POSITIONNR (In MU)
-10.4-22680194909217589Northern
Region
-3.3-22967947023Uttarakandl
-17.5-107955094561740UP
-2.4-8523534436196Rajasthan
-8.5-35793854142120Punjab
-28.2-3275832711602J&K
-2.9-17557715946HP
-12.5-36372551229149Haryana
-0.6-1382223622374Delhi
0014391439Chandigarh
Surplus/Deficit (-)(MU) (%)
AvailabilityRequirement
April-March 2008State
-
7/31/2019 PMI - 14-10-08
14/76
ACTUAL POWER SUPPLY POSITIONWR (In MU)
-15.8-38947208209247156WesternRegion
-1.2-3227062738Goa
-18.3-2103993895114934Maharashtra
-14.1-58613566341524MP
-16.2-111345758168715Gujarat
-4.8-6701341314083Chhattisgarh
Surplus/Deficit(-)
(MU) (%)
AvailabilityRequirement
April-March 08State
-
7/31/2019 PMI - 14-10-08
15/76
ACTUAL POWER SUPPLY POSITIONSR (In MU)
-3.2-5923181813187736SouthernRegion
0.0018401840Pondicher
y
-2.8-18266389865724TamilNadu
--2.4-3801527615656Kerala
-2.7-10893928240371Karnataka
-4.1-26286151764145AP
Surplus/Deficit (-)(MU) (%)
AvailabilityRequirementApril-March 2008State
-
7/31/2019 PMI - 14-10-08
16/76
ACTUAL POWER SUPPLY POSITIONER (In MU)
-5.0-37567201675772EasternRegion
-3.8
-4.7
-1114
-50
27865
283
28979
297
West
Bengal +Sikkim
-1.8--3441848918833Orissa
-12.5-63244165048Jharkhand-2.5-3401303313373DVC
-14.2-131279309242Bihar
Surplus/Deficit (-)(MU) (%)
AvailabilityRequirement
April-March 2008State
-
7/31/2019 PMI - 14-10-08
17/76
ACTUAL POWER SUPPLY POSITIONNER (In MU)
-9.8-72392664660737052ALL India
-12.3-108677138799NE-Region
-11.7-91686777Tripura
-11.4-43334377Nagaland
-14.6-42246288Mizoram
-24.0-38812321620Meghalaya
-5.5-29501530Manipur
-8.4-40444124816Assam
-22.8-89302391ArunachalPradesh
Surplus/Deficit (-)(MU) (%)
AvailabilityRequirement
April-March 2008State
-
7/31/2019 PMI - 14-10-08
18/76
High potential for Growth
2490
11446
6755
1440
6303
2246
594
14057
-1800 200 2200 4200 6200 8200 10200 12200 14200
World Average
USA
Australia
UK
China
Russia
Brazil
India
Source-UNDP Human Dev. Indicators 2006
Per-Capita Energy Consumption in Kwh-
2003
India targets to have per capitaavailability of 1000 KWh by 2012
664.8 Kwh in2006-07
-
7/31/2019 PMI - 14-10-08
19/76
Large Capacity addition is required to meet thedemand
Mar-07 2012 2022 2032
Source: Integrated Energy Policy GOI
132 GW220 GW
425 GW
778 GW
Demand considering 8% GDP growth
-
7/31/2019 PMI - 14-10-08
20/76
Site Selection
-
7/31/2019 PMI - 14-10-08
21/76
Broad factors influencing selection of projectsite(s)
a) Availability of suitable and adequate landb) Reliable Source of Waterc) Type and Source of fueld) Distance from Source of fuele) Port, rail and road accessf) Availability of infrastructure facilities
g) Siting Criteria of MOEFh) Environmental aspects
Siting Criteria of Thermal Power Plant
-
7/31/2019 PMI - 14-10-08
22/76
Siting Criteria of Thermal Power Plant
Should be avoided within 25 kms of theouter peripheries of
Metropolitan cities
National Park and Wildlife sanctuaries Ecologically sensitive areas like tropical
forests, biosphere reserves, National Parks& Sanctuaries, important lakes and coastal
areas rich in coral formations. 500 m of HTL, a buffer zone of 500 mts
should be kept free
-
7/31/2019 PMI - 14-10-08
23/76
Siting Criteria of Thermal Power Plant
Chimney should not fall within the approachfunnel of the runway.
500 mts. Away from National Highway,Railway and Flood Plains of the Riverine
Systems 10 kms away from archaeological, historical,
cultural, religious or tourist importance anddefence installations
No forest or prime agricultural land shouldbe utilized for setting up of TPS, or for ashdisposal.
Should not be on coal bearing area.
I di ti R i m t f B i I t f
-
7/31/2019 PMI - 14-10-08
24/76
Indicative Requirement of Basic Inputs forCoal based Projects
Capacity Range
LAND (acres)
Main Plant
Ash Disposal
Township
WATER
Makeup water (cusecs)
Sweetwater for coastalProjects (cusecs)
FUEL (MilionTonne/Annum)
Indigenous raw coal
1000 MW 2000 MW
650 800
500 1000
150 250
40 80
6 12
5.5 11
-
7/31/2019 PMI - 14-10-08
25/76
Indicative Requirement of Basic Inputs forGas Projects
Capacity rangeLAND (acres) Main Plant Township
WATER Cooling water
(Cusecs)FUEL (MCMD)
650 MW 1300 MW
200 300
75 80
18 35
2.9 5.8
(33 Tri.BTU) (66 Tri. BTU)
-
7/31/2019 PMI - 14-10-08
26/76
Preparation of Feasibility Report
-
7/31/2019 PMI - 14-10-08
27/76
PREPARATION OF FEASIBILITY REPORT
Topographical Survey
Soil Investigation
Environmental Impact Assessment (EIA) Study
Make-up Water Study Seismic Study
Area Drainage Study
Geological Mapping Study
Coal Transportation / Railway Siding Study
Socio-Economic Study
Feasibility Report
Sit S ifi St di /I tig ti i d
-
7/31/2019 PMI - 14-10-08
28/76
Site Specific Studies/Investigations requiredfor a New Project Site
Preliminary Topographical Survey
Broad scope of services includes
Development of contours
Land use plan
Ownership details
Preliminary Geo-technical Investigation
Field as well as laboratory investigation, analysisand interpretation of data collected and preparationof a Geo-technical report.
-
7/31/2019 PMI - 14-10-08
29/76
Site Specific Studies/InvestigationsEnvironmental Impact Assessment (EIA ) Study
Broad scope includes: Field studies Impact assessment Preparation of the EIA document covering Land Use,
Water Use, Soils, Geology, Hydrology, Sediments,Water Quality, Meteorology, Air Quality, TerrestrialEcology, Aquatic Ecology, Noise, Risk Assessment,Ash Utilization and Occupational Health and Safety.Services (based on 12 months data).
EIA report covers the existing environmental baselineconditions, impacts due to operation of the powerplant, Environmental Management Plan, post study-monitoring programme, Occupation Safety & Healthand Risk Assessment.
-
7/31/2019 PMI - 14-10-08
30/76
Site Specific Studies/Investigations
Seismic Study
Broad Scope includes Geological and seismotechtonic set-up of the sitecovering an area of not less than 150Km radius aroundthe project site.
Determination and presentation of design earthquakeparameters
Area Drainage Study Review and analysis of rainfall information to arrive atdesign storm scenarios
Preparation of digital elevation model for the studyarea
Estimation of flood hydrographs considering historicalas well as design rainfall for different return periods.
-
7/31/2019 PMI - 14-10-08
31/76
Site Specific Studies/InvestigationsSocio-economic StudyBroad scope includes :
Assessing the number of Project Affected Persons(PAPs), overall impact due to land acquisition andestablishment of the project on the affected villages andits populace in general and the PAPs , whose livelihoodis affected (directly or indirectly) in particular.
To establish base line condition, assess the social-economic impacts and to what extent, analyse theimpoverishment risk to find out the most vulnerablesection of the society and to suggest the initiatives to
address these issues. To establish social inventory of affected villages
covering the social, cultural, economic, historical,political and environmental aspects.
To identify indicators for monitoring the standards of
living of PAPs in future.
-
7/31/2019 PMI - 14-10-08
32/76
Railway SidingStudy To examine the feasibility of alternative allignments Identification of serving station on Indian Railways
and the requirement of traffic facilities at thesestations with reference to facilities already existing.
Survey of the selected alignment Assessment of land requirement
Hydrological Study Specific information about the river water levels,
bed profile (river across-section), velocity of water(magnitude and direction) silt load and gradationetc. during various periods of the year
To locate and design rationally, intake-well andother associated structures required for the drawalof water.
Site Specific Studies/Investigations
CONTENTS OF FR
-
7/31/2019 PMI - 14-10-08
33/76
CONTENTS OF FR Need and Justification of the Scheme.
Preliminary Analysis of Alternatives
Linkage/Availability of Various Inputs
Availability of Various Clearances.
Energy Absorption Plan
Energy Evacuation Plan
Financial and Executing Capabilities Plant Technical Features incl. Bill of Quantities
Environmental Aspects
Project Execution and Mgt. incl Implementation
Schedule Cost Estimates
Financial Package
Tariff Calculations.
Establishment Project Viability
-
7/31/2019 PMI - 14-10-08
34/76
Thermal Projects Tie ups /Clearances
INPUTS / LINKAGES TO BE TIED UP
-
7/31/2019 PMI - 14-10-08
35/76
INPUTS / LINKAGES TO BE TIED UP
Input Agency
Land Availability State Government
Water Availability State Irrigation Deptt.CWC / MOWR
Coal Linkage Dept. of Coal (SLC)
Gas/Liquid FuelAvailability
Ministry of Petroleum &Natural Gas
Fuel Transportation Railways /
GAIL/Oil Companies
CLEARANCES REQUIRED
-
7/31/2019 PMI - 14-10-08
36/76
CLEARANCES REQUIRED
Clearance Agency
Clearance for Chimneyheight
Airports Authority of
India
Defence Clearance Ministry of Defence
Public Hearing SPCB
Environment Clearance MOEF
Forest Clearance State ForestDepartment / MOEF
R&R of displaced family Concerned State Govts
OTHER REQUIREMENTS
-
7/31/2019 PMI - 14-10-08
37/76
OTHER REQUIREMENTS
Item Agency
Power Evacuation Powergrid/CEA
Power Purchase
Agreement
Beneficiaries
Financing MOP/DEA
ICB Clearance MOP
Mega Certificate,wherever applicable
MOP
MEGA POWER PROJECTS: REVISED POLICY
-
7/31/2019 PMI - 14-10-08
38/76
MEGA POWER PROJECTS: REVISED POLICYGUIDELINES
The following conditions are required to be fulfilled by the developer
for grant of mega project status:-
a) an inter-state thermal power plant of a capacity of 700 MW or more,located in the States of Jammu and Kashmir, Sikkim, ArunachalPradesh, Assam, Meghalaya, Manipur, Mizoram, Nagaland andTripura; or
b) an inter-state thermal power plant of a capacity of 1000 MW or more,located in States other than those specified in clause (a) above; or
c) an inter-state hydel power plant of a capacity of 350 MW or more,located in the States of Jammu and Kashmir, Sikkim, Arunachal
Pradesh, Assam, Meghalaya, Manipur, Mizoram, Nagaland andTripura; or
d) an inter-state hydel power plant of a capacity of 500 MW or more,located in States other than those specified in clause (c) above
MEGA POWER PROJECTS REVISED POLICY
-
7/31/2019 PMI - 14-10-08
39/76
MEGA POWER PROJECTS: REVISED POLICYGUIDELINES
Pre-conditions for availing the benefits:
Goods required for setting up of any mega powerproject, qualify for the above fiscal benefits afterit is certified by an officer not below the rank of aJoint Secretary to the Govt. of India in the
Ministry of Power that
(i)the power purchasing States have constitutedthe Regulatory Commissions with full powers tofix tariffs;
(ii)the power purchasing States undertakes, inprinciple, to privatize distribution in all cities, inthat State, each of which has a population ofmore than one million, within a period to be fixed
by the Ministry of Power.
MEGA POWER PROJECTS: REVISED POLICY
-
7/31/2019 PMI - 14-10-08
40/76
MEGA POWER PROJECTS: REVISED POLICYGUIDELINES
Fiscal concessions/benefits available :
Zero Customs Duty : In terms of the notification of theGovernment of India in the Ministry of Finance (Department ofRevenue) No.21/2002-Customs dated 1st March, 2002 readtogether with No.49/2006-Customs dated 26th May, 2006, theimport of capital equipment would be free of customs duty for
these projects.Deemed Export Benefits: Under Chapter 8(f) of theForeign Trade Policy, Deemed Export Benefits is available todomestic bidders for projects both under public and privatesector on following the stipulations prescribed therein.
Price preference to domestic PSUs bidders: In order toensure that domestic bidders are not adversely affected, pricepreference of 15% would be given for the projects underpublic sector. The domestic bidders would be allowed to
quote in US Dollars or any other foreign currency of theirchoice.
-
7/31/2019 PMI - 14-10-08
41/76
Hydro Projects Tieups /Clearances
-
7/31/2019 PMI - 14-10-08
42/76
Site Selection for Hydro Projects
Broad factors influencing site selectiona) Installed capacity and dependable energyb) Project cost and cost of energy
c) Accessibility and existing infrastructured) Type of development i.e. storage or Run of
River (ROR)e) Type of structures i.e. dam height, length
of water conductor, type of power houseetc.
f) Environmental considerations and R&R
-
7/31/2019 PMI - 14-10-08
43/76
STUDIES FOR HYDRO POWERPROJECTS
Topographical Study
Geological & Geotech Study
Hydrological Study
Meteorological Study
Seismic Study
Socio-Economic Study
EIA Study Construction Material Survey
Transportation Study
Disaster Management Studies
-
7/31/2019 PMI - 14-10-08
44/76
CLEARANCES REQUIRED FOR HYDROPROJECT
Land confirmation from StateGovernment
Water clearance from State Government
Clearance from MOWR & CWC regardingwater availability from Inter-State /International Treaty angle.
Defence clearance, if applicable
-
7/31/2019 PMI - 14-10-08
45/76
CLEARANCES REQUIRED FOR HYDROPROJECT
Clearance from Ministry of Social Justice andTribal Affairs, if tribal population is involved.
Environment Clearance from Ministry of
Environment & Forests Forest Clearance from MOE&F
TEC from CEA
For Projects costing more than Rs 500Crs (Allottedthrough MOU route)
For Projects costing more than Rs 2500 Crs(Allotted through competitive bidding route)
-
7/31/2019 PMI - 14-10-08
46/76
CEAs TECHNO-ECONOMIC CLEARANCE
Appraisal is based on Technical Feasibility Comprehensiveness Tie-up of Inputs Availability of Clearances Consent from GSI on Geological aspect Consent from CWC on Hydrology Cost Estimates Comparison with other Similar Projects
(Least Cost Solution) Power Evacuation Arrangement
-
7/31/2019 PMI - 14-10-08
47/76
Investment Approval
-
7/31/2019 PMI - 14-10-08
48/76
Investment Approval prior to accordanceof Navratna Powers
Pre-PIB (Inter-Ministerial) headed byJS&FA, MOP
PIB (Inter-Ministerial) headed by Secretary
(Expenditure), MOF CCEA
Investment Approval
Simhadri & Faridabad were the lastprojects approved through this route
Enhanced Delegations of Powers to Navratnas
-
7/31/2019 PMI - 14-10-08
49/76
Enhanced Delegations of Powers to Navratnas(From July, 1997; revised w.e.f 5.8.05)
Identified Navratna PSEs incl. NTPC have beendelegated powers including to Incur capital expenditure on purchase of new items or for
replacement without any monetary ceiling.
Establish Financial JVs and wholly owned subsidiary inIndia or abroad with the stipulation that the ceiling ofequity investment of the PSE shall be 15%(5% earlier) ofthe net worth of the PSE limited to Rs1000crs (Rs.200 Crs.earlier) in any one project and 30%(15% earlier) of the net
worth of the PSE in all JVs
Wavier of Ceiling of Rs 1000Crs for participating in biddingof Ultra Mega Projects (s.t implementation of 2 projects)(Special approval conveyed on 14.11.2006)
-
7/31/2019 PMI - 14-10-08
50/76
Enhanced Delegations of Powers to Navratnas(From July, 1997; revised w.e.f 5.8.05)
Powers for mergers and acquisitions(5.8.05) s.t
(i) it should be as per the growth plan and in thecore area of functioning of the PSE,
(ii) Conditions / limits would be as in the case ofestablishing joint ventures/subsidiaries, and
(iii) the CCEA would be kept informed in case of
investments abroad.Powers to be exercised in such a manner that it should not
lead to any change in the public sector character of theconcerned PSEs (28.5.07)
CONDITIONS APPLICABLE FOR NAVRATNA
-
7/31/2019 PMI - 14-10-08
51/76
POWERS
Restructuring of the Board
Establishment of Audit Committee with membershipof non-official directors
Proposals must be with an analysis of relevantfactors and quantification of the anticipatedresults and benefits.
Proposals should be prepared by or with theassistance of professionals and experts and should
be appraised, in suitable cases, by financialorganisations with expertise in the areas. Theappraisal should also preferably be by institutionsfunding through loans or equity participation.
CONDITIONS APPLICABLE FOR NAVRATNA
-
7/31/2019 PMI - 14-10-08
52/76
POWERS CONTD. Government Directors, Finance Director and the
concerned Functional Director (s) must be presentwhen major decisions are taken
Decisions should preferably be unanimous.Otherwise a majority decision may be taken but atleast two-thirds of the Directors should be present.
PSE not to depend upon budgetary support (orGovernment guarantees earlier).
Wherever Govt. guarantee is required by externaldonor agencies, such guarantee shall not affectNavratna status( 5.8.05)
Budgetary support to implement Govt. sponsoredprojects of national interest and R&D projects willnot disqualify Navratna status; Such projects to be
approved by Govt. (28.5.07)
REVISED SYSTEM UNDER NAVRATNA POWERS
-
7/31/2019 PMI - 14-10-08
53/76
REVISED SYSTEM UNDER NAVRATNA POWERS
Preparation of FRs/ DPRs incl. Studies & Investigationfor New / Expansion Projects
MonetaryLimit
Rs 500 lakh for a project
Scope Expenditure towards Topographical Survey,
Socio-economic Survey, Geo-technicalInvestigations, Detailed Environment ImpactAssessment Studies, Hydrological Studies,Area Drainage Study, Seismic Study,Oceanographic Study, Model Studies,Preparation of FR/DPR and payment offees/charges for statutory clearances etc. forNew / Expansion of Projects etc.
ApprovingAuthority
CMD
REVISED SYSTEM UNDER NAVRATNA POWERS
-
7/31/2019 PMI - 14-10-08
54/76
REVISED SYSTEM UNDER NAVRATNA POWERS
FR/DPR
On current as well as estimated completion cost basis. FR/DPR to be approved by the Project Sub-Committee of
the Board comprising Chairman & Managing Director,Director (Finance), Director (Projects), Director
(Operations), Director (Technical), Director (Commercial),Joint Secretary (Thermal) and One (1) Non-Official/Part-time Director as Members. The Chairman & ManagingDirector shall be the Chairman of the Project Sub-
Committee. The quorum for the Sub-Committee shall befour (4) Members including one (1) Part-time Director.
REVISED SYSTEM UNDER NAVRATNA POWERS
-
7/31/2019 PMI - 14-10-08
55/76
REVISED SYSTEM UNDER NAVRATNA POWERSAdvance Expenditure for Projects for which FR/DPR isapproved by Project Sub-Committee
MonetaryLimit
Rs 15 Crs for a project
Scope Activities related to development ofinfrastructure (such as construction power,construction water, construction stores,construction office, approach road, siteprotection etc.), processing and servicecharges (advance payments) for land
acquisition, Site establishment etc.,including advance action for NIT for sitedevelopment/infrastructure activities, evenin cases where cost estimate is more than
Rs.15 crore.
REVISED SYSTEM UNDER NAVRATNA POWERS
-
7/31/2019 PMI - 14-10-08
56/76
REVISED SYSTEM UNDER NAVRATNA POWERS
Advance Expenditure for Projects for which FR/DPR isapproved by Project Sub-Committee
Pre-requisites
FR/DPR submitted to CEA, whereverapplicable
FR/DPR approved by Project Sub-Committee of the Board.
Project identified in the Annual Plan.
ApprovingAuthority
CMD
REVISED SYSTEM UNDER NAVRATNA POWERS
-
7/31/2019 PMI - 14-10-08
57/76
REVISED SYSTEM UNDER NAVRATNA POWERSAdvance Expenditure for Projects which havereceived TEC of CEA, wherever applicable / appraisal
by independent agency has been done incase of otherprojects
MonetaryLimit
Rs 50 Crs (uncl. Earlier expenditure) for aproject
Scope Infrastructural development (ApproachRoad, Site Protection, Fencing/BoundaryWall, Drainage, Construction Water / Power/ Stores / Office, Construction townshipand other enabling works etc.) including onland acquisition of priority land, sitelevelling, initial expenditure on R&R, Green
Belt, Site establishment etc.
REVISED SYSTEM UNDER NAVRATNA POWERS
-
7/31/2019 PMI - 14-10-08
58/76
REVISED SYSTEM UNDER NAVRATNA POWERS
Advance Expenditure for Projects which havereceived TEC of CEA, wherever applicable / appraisalby independent agency has been done incase of otherprojects
Pre-requisites
FR/DPR approved by Project Sub-Committee of the Board.
Techno-Economic Clearance from
CEA, wherever applicable. For otherprojects, Appraisal by independent
agency.
Necessary Budgetary Provision
ApprovingAuthority
CMD
REVISED SYSTEM UNDER NAVRATNA POWERS
-
7/31/2019 PMI - 14-10-08
59/76
REVISED SYSTEM UNDER NAVRATNA POWERS
Approval for issue of NIT
CMD shall approve issue of NIT for variouspackages including Main Plant Package in caseof New/Expansion Projects before Boards
investment approval after FR/DPR is approved
by Project Sub-Committee of the Board subjectto following and relevant Govt. guidelines :
i) FR approved by Project Sub-Committee of theBoard.
ii) CEAs TE Clearance for the project is available,
wherever applicable / Appraised byindependent agency in case of other Projects
REVISED SYSTEM UNDER NAVRATNA POWERS
-
7/31/2019 PMI - 14-10-08
60/76
REVISED SYSTEM UNDER NAVRATNA POWERS
Investment Approval
Monetary Limit : No limit
Scope New / Expansion Projects
Pre-requisites
Views of Project Sub-Committee afterconsidering various aspects of the proposal
taking into account following pre-requisites ofthe Proposal.
Availability of InputsLand availability confirmation.Water linkage from State Irrigation Dept. and Concurrenceof CWC/MOWR, if it is inter-State jurisdiction.Fuel linkage, wherever applicableSigning of Fuel Supply Agreement, wherever applicable
REVISED SYSTEM UNDER NAVRATNA POWERS
-
7/31/2019 PMI - 14-10-08
61/76
REVISED SYSTEM UNDER NAVRATNA POWERS
Investment Approval (..contd)
Availability of ClearancesSPCB clearance.
MOEF clearance
Forest clearance, if necessaryCivil Aviation Clearance, wherever applicable
Defence/Archaeological clearance, if necessary.
CEAs Techno-Economic Clearance, whereverapplicable
REVISED SYSTEM UNDER NAVRATNA POWERS
-
7/31/2019 PMI - 14-10-08
62/76
REVISED SYSTEM UNDER NAVRATNA POWERS
Investment Approval (..contd)
Others
PPA should have been signed
Satisfactory Financing Plan
Fuel Transportation clearance particularly where long
distance transportation involved, wherever applicable Associated Transmission System (ATS)CEAs
Techno-Economic Clearance, where necessary
Satisfactory Financial Appraisal of the project
No net budgetary support from GOI for the Project
Approving Authority : Board
Projects approved through Navratna Powers
-
7/31/2019 PMI - 14-10-08
63/76
Projects approved through Navratna Powers
Under Navratna Powers NTPC Board hasapproved approval for 20 projects withestimated cost of about Rs 86000 Crs
Project Capacity in MW
Talcher-II 2000
Ramagundam-III 500Rihand-II 1000
Vindhyachal-III 1000
Unchahar-III 210
Kahalgaon-II Phase-I 1000
Kahalgaon-II Phase-II 500
Sipat-I 1980
Sipat-II 1000
Projects approved through Navratna Powers
-
7/31/2019 PMI - 14-10-08
64/76
Project Capacity in MW
Barh 1980
Korba-III 500Farakka-III 500
NCTPP-II 980
Simhadri-II 1000
Mauda 1000
Bongaigaon 750
Barh-II 1320
Koldam 800
Loharinag Pala 600
Tapovan Vishnugad 520
Further investment in 4 JV Projects of 4000 MW capacity approvedexcl. investment in RGPPL
SNAPSHOT OF XI PLAN PROJECTS
-
7/31/2019 PMI - 14-10-08
65/76
SNAPSHOT OF XI PLAN PROJECTS
Category (MW)
Commissioned 2490
On-Going Projects 16180
Projects for which Main Plant Bids havebeen received/invited.
3760
TOTAL 22430Back up projects:Rihand-III-U2(500MW), Vindhyachal-IV (2x500 MW), Vallur-II(1x500 MW), Muzaffarpur Exp. (2x250 MW)& Renewable : 100 MW
2600
Critical units for comm. in XI Plan: 2820 MW- NorthKaranpura-U1, Barh-II-U2, Mauda -U2, Rihand-III- U2and Vindhyachal-IV- U2
Capacity at the end of XI Plan- 49834 MW - Coal -39879 MW, Gas-8035 MW and Hydro 1920 MW
ON GOING PROJECTS
-
7/31/2019 PMI - 14-10-08
66/76
Project Capacity(MW)
Balance CapacityIn XI Plan (MW)
Kahalgaon-II 1500 500Sipat-I 1980 1980
Barh 1980 1980
Korba-III 500 500
Bhilai Exp.- JV 500 250
NCTPP-II 980 980
Farakka-III 500 500
Simhadri-II 1000 1000Aravali STPP-JV 1500 1500
Vallur-I -JV 1000 1000
ON GOING PROJECTS
-
7/31/2019 PMI - 14-10-08
67/76
Project Capacity(MW)
BalanceCapacity In XI
Plan (MW)
Nabinagar-JV 1000 1000
Bongaigaon 750 750
Mauda* 1000 1000Barh-II** 1320 1320
Koldam HEPP 800 800
LohariNag Pala 600 600
TapovanVishnugad
520 520
TOTAL 16180* LOI issues, LOA yet to be placed.
** LOA for SG issued. LOA for TG expected by July08.
PROJECTS FOR WHICH MAIN PLANT BIDS
-
7/31/2019 PMI - 14-10-08
68/76
PROJECTS FOR WHICH MAIN PLANT BIDSHAVE BEEN RECEIVED/INVITED
Project Capacity(MW)
Capacity InXI Plan(MW)
NorthKaranpura 1980 660
Rihand-III 1000 500
Kawas-II 1300 1300
J. Gandhar-II 1300 1300
TOTAL 3760
-
7/31/2019 PMI - 14-10-08
69/76
-
7/31/2019 PMI - 14-10-08
70/76
THANKING YOU
Mega Benefits- Typical 1000 MW TPPR i C
-
7/31/2019 PMI - 14-10-08
71/76
S.
No.
Description Cost
Mega
Cost
Non-mega1 Civil Works 770 770
2 Equipment 3200 3200
Contingency 98 110
3 Taxes & Duties 78 503
Customs duty 133 #
Excise Duty 1 302 #
CST 77 68IDC, Proj. Mgt. 846 926
4 Total Project Cost 4992 5509
Rs in Crs.
# Considering 30% Imported component of BTG
Purchase Preference
-
7/31/2019 PMI - 14-10-08
72/76
Since 1971 Price Preference not exceeding 10%was admissible to products and services producedby a CPSE and being offered to other CPSEs.
Consequent to economic liberalization, this wasreviewed in 1991.
Purchase Preference Policy was introduced inJanuary, 1992 replacing the Price Preference Policy
with validity for 3 years. Under this if the price quoted by a CPSE was within
10% of the lowest valid bid price (L-1) in a tender,other things being equal, preference to be accordedto CPSE at L-1 price.
This is to enable CPSEs to adjust to newenvironment of competition in the wake ofGlobalization (falling tariff/custom duties) andliberalized industrial policy (pruning the list ofindustries reserved exclusively for public sector)
Purchase Preference
-
7/31/2019 PMI - 14-10-08
73/76
Subsequently extended several times;presently valid till 31.3.2008. it was
stipulated that it will be terminated w.e.f31.3.2008. (18.7.05) Presently it is valid for contracts of the
value of Rs 5 Crs and above but not
exceeding Rs 100 Crs. A minimum value addition of 20% by the
CPSE would be a pre-requisite. MOP is granted exemption from PPP, s.t
condition that they will place certainorders upon BHEL on a negotiated basisprice benchmarked throughcompetitvely bid projects every year.
Price Preference
-
7/31/2019 PMI - 14-10-08
74/76
World Bank/ADB Guidelines ICB to be followed
Evaluation of tenders to be done with out duties(customs duty & excise duty)
Price Preference of 15% to domestic biddersallowed with the stipulation that value addition ismore than 20%.
Price Preference is to offset domestic duty/leviessuch as sales tax, octroi, etc and certaindisadvantages due to inadequate infrastructure andhigher cost of finance
Mega Policy understood to have borrowed bidding
provisions of World Bank funded Projects In the Evaluation, 15% of CIF price difference is
loaded to the foreign bidder.
NTPCs XII PLAN CAPACITY ADDITION
TARGET (MW)
-
7/31/2019 PMI - 14-10-08
75/76
TARGET (MW)
Cumulative capacity targeted by end
12th
Plan
75000
NTPCs capacity as of March07 (endof 10thPlan (29394 MW as of now)
27404
Capacity addition target in 11th Plan
(incl. 2600 MW Gas. & excl. 2500 MWBack up projects identified.
22430
Cumulative capacity by end 11th plan
(49734 if back up considered in placeof Gas)
49834
Capacity addition required in 12th Plan 25166
Capacity identified for 12th Plan 15011
Capacity to be firmed up for 12th Plan ~10000
CAPACITY IDENTIFIED FOR XII PLAN
-
7/31/2019 PMI - 14-10-08
76/76
Sl.No PROJECT CAPACITY (MW) IN XIIPlan
REMARKS
I Firmed up Projects
1. North Karanpura 1320 Capacityfirmed up15011 MW
2. Tanda-II 13203. Meja 1320
4. New Nabinagar 1980
5. Solapur 1320
6. Lata Tapovan 171
7. Rammam-III 1208. RupsiyabagarKhasiyabara
260
9 Darlipali 3200
10 Lalitpur 4000
II Other projects
11. Gadarwara 1980 Balancecapacityidentified19430 MW.Out of this10000 MW
12. RGCCPP-II 1950
13. Lara 4000
14. Markanam 4000
15. Etalin & Attunil 4500
16 N l P 2000