IR SA Case Study

download IR SA Case Study

of 12

Transcript of IR SA Case Study

  • 8/3/2019 IR SA Case Study

    1/12

    InfraMation 2006 Proceedings ITC 115 A 2006-05-22

    Monitoring of Surge Arresters through Thermographic Inspection Case Studies

    Tereza Cristina Leite GalindoCompanhia hidroeltrica do So Francisco Chesf

    Participants: Adolpho Calazans, Augusto Miranda, Eduardo Luiz, Esdras Rodrigues, Joo Domingos, Josu Beltro, Max Norat, Marcos Vencio,Companhia hidroeltrica do So Francisco - Chesf

    ABSTRACTIn this paper we present evaluation cases of surge arrester operational conditions, through thermographicinspections, criteria applied in the field, and analysis carried out in units removed from operation due to theproblems indicated by thermograms.

    INTRODUCTION

    Chesf (Companhia hidroeltrica do So Francisco) has been applying the thermographic inspection techniquein its substations for more than 30 years, initially in connections and later for equipment evaluation, includingsurge arresters.

    The methodology applied for the surge arrester inspection is based on a structure of possibilities from twotypes of evaluations:

    Quantitative evaluation considers the difference between the absolute temperature of the objectand the room temperature of the same;

    Comparative evaluation considers the temperature difference between similar surge arresters.

    The numeric criteria are established from the evaluations according to the table below:

    Ligntening Normal(T C)

    Critical Level 1(T C)

    Critical Level 2(T C)

    Comparative 3 3 7Quantitative 5 5 10

    DEVELOPMENTSome samples were selected to better analyze the applied criteria and the errors associated to the measuringprocess in the field:

    To carry out laboratory analyses after field intervention; To monitor the field work through interventions of porcelain surface cleaning.

    The following case studies give examples of our work. Units taken to the laboratory:

    Case 1:230 kV Surge Arrester.Substation: MRRDescription of occurrence:Inspection in 04/19/05, at 18:45h. Room temperature of 29

    oC and relative humidity of 73 %.

    Thermal critical state level 2.Action: removal of operation equipment.Thermogram carried out in the field during inspection:

  • 8/3/2019 IR SA Case Study

    2/12

    InfraMation 2006 Proceedings ITC 115 A 2006-05-22

    17,9C

    49,8C

    20

    30

    40

    J6: 41,9C

    Figure 1. Thermogram of surge arrester in critical condition

    Laboratory analyses:

    Measurement of losses it wasnt possible to carry out this analysis due to the instability at themeasuring bridge, indicator of high losses;

    Measurement of leakage current:

    Tension (kV) 1. Reading

    I (A)

    2. Reading

    I (A)

    3. Reading

    I (A)

    2.5 84.7 87.4 88.9

    5.0 58.1 53.4 46.8

    It was not possible to progress with the leakagecurrent measurer due to high current indication.

    Figure 2. Opening of the unit.

  • 8/3/2019 IR SA Case Study

    3/12

    InfraMation 2006 Proceedings ITC 115 A 2006-05-22

    Case 2:230 kV Surge Arrester. Substation: MSDDescription of occurrence:

    Inspection in 04/02/05, at 22:15h. Room temperature of 25oC and relative humidity of 96 %.Thermal critical state level 2.Action: removal of operation equipment

    17,1C

    45,8C

    20

    30

    40ase A*: 33,3C

    Figure 3. Thermogram carried out in the field duringinspection indicating significant problem.

    Laboratory analyses:

    Measurement of leakage current and dielectric losses.It was not possible to carry out the analyses due to high losses.

    Figure 4. Opening of the unit. Figure 4b. Internal Corrosion.

    InternalCorrosion

  • 8/3/2019 IR SA Case Study

    4/12

    InfraMation 2006 Proceedings ITC 115 A 2006-05-22

    Case 3:230 kV Surge Arrester. Substation: PRDDescription of occurrence:Inspection in 12/18/01, at 19:00h. Room temperature of 22

    oC and relative humidity of 74 %.

    Inspection in 01/15/2002, at 21:00h. Relative humidity of 73 %.Thermal critical state level 2.Action: removal of operation equipmentThermograms carried out in the field during inspections:

    21,2C

    32,7C

    25

    30

    A: 24,9C

    18-12-2001

    16,9C

    43,3C

    20

    30

    40A: 45,8C

    15-01-2002 - 28 dias aps a ins

    Figure 5. Thermogram of problem arrester Figure 5b. Thermogram of critical problem arrester

    Laboratory analyses:

    Measurement of leakage current:

    Superior Section:CurrentVoltage

    (kV) IP-P(mA)

    IP2(mA)

    3 h(%I60Hz)

    5 h(%I60Hz)

    7 h(%I60Hz)

    2.5 0.18

    0.06

    0.00 0.00 0.005 0.32

    0.11 0.00 0.00 0.00

    10 0.61

    0.21 0.00 0.00 0.0020 1.20 0.42 1.28 0.00 0.0030 1.72 0.60 1.69 0.00 0.0040 2.24 0.79 1.31 0.00 0.0050 2.72 0.96 1.54 0.00 0.0060 3.24 1.14 1.36 0.00 0.0070 3.72 1.31 3.42 0.00 0.0080 4.28 1.51 7.57 2.21 0.0090 5.28 1.86 15.05 5.10 1.28

    100 9.40 3.32 26.87 10.97 3.29105 14.6 5.16 32.96 14.13 3.46

  • 8/3/2019 IR SA Case Study

    5/12

    InfraMation 2006 Proceedings ITC 115 A 2006-05-22

    Inferior Section:CurrentVoltage

    (kV) IP-P

    (mA)

    IP2

    (mA)

    3 h

    (%I60Hz)

    5 h

    (%I60Hz)

    7 h

    (%I60Hz)2 2.5 0.88 0.00 0.00 1.795 6.5 2.30 0.00 0.00 2.087 9.8 3.46 0.00 0.00 2.3210 13.8 4.88 0.44 0.00 2.1812 16.0 5.65 0.47 0.00 2.4615 20.0 7.07 0.22 0.15 3.2917 21.2 7.50 0.00 0.14 4.2120 29.2 10.32 0.84 0.52 5.7925 40.0 14.14 2.68 0.84 7.61

    What became evident was the inferior section deteriorated faster with the increase of the losses, in

    comparison with the superior section.

    Figure 6. Opening of the inferior unit. Figure 6b. Bottom of inferior unit.

    Case 4:230 kV Surge Arrester. Substation: MSDDescription of occurrence:Inspection in 11/09/2005, at 19:20h. Room temperature of 29

    oC and relative humidity of 72 %.

    Thermal critical state level 1.Action: removal of operation equipment.

    Thermograms carried out in the field during inspections:

  • 8/3/2019 IR SA Case Study

    6/12

    InfraMation 2006 Proceedings ITC 115 A 2006-05-22

    18,3C

    40,2C

    20

    30

    40

    B1: 33,5C

    Lado NORTE

    18,3C

    40,2C

    20

    30

    40

    B*: 32,7C

    Lado SUL

    Figure 7. Thermogram of problem arrester,north side

    Figure 7b. Thermogram of problem arrester, southside

    Laboratory analyses:

    Measurement of leakage current and dielectric losses:

    Superior Section -2 Inferior Section -1

    Voltage(kV) Leakage

    Current(mA)

    DielectricLoss (W)

    LeakageCurrent(mA)

    DielectricLoss (W)

    10 2.37 0.3481 4.60 0.6204

    20 6.70 1.3934 9.90 2.6058

    30 26.63 3.1751 23.90 5.9656

    40 37.83 6.0296 52.40 10.925550 70.20 9.2001 95.00 18.5763

    60 111.70 167.00

    70 208.30 350.00

    Figure 8. Opening of the inferior unit.

  • 8/3/2019 IR SA Case Study

    7/12

    InfraMation 2006 Proceedings ITC 115 A 2006-05-22

    Case 5:230 kV Surge Arrester. Substation: PRDDescription of occurrence:Inspection in 09/28/2005, at 19:14h. Room temperature of 25

    oC and relative humidity of 72 %.

    Thermal critical state level 2.Action: removal of operation equipment.

    15,1C

    49,2C

    20

    40

    33,4C

    Figure 9. Thermogram carried out during field inspection.

    Laboratory analyses:

    Measurement of leakage current and dielectric losses:

    Superior SectionTension(kV)

    LeakageCurrent

    (mA)

    Dielectric

    Loss (W)10 1.5 0.1168

    20 6.2 0.4946

    30 24.0 1.2179

    40 32.1 2.4803

    50 73.2

    60 136

    70 250.3

    It was not possible to analyze the inferior section due to high losses.

  • 8/3/2019 IR SA Case Study

    8/12

    InfraMation 2006 Proceedings ITC 115 A 2006-05-22

    Figure 10. Opening of the inferior unit.

    Case 6:13, 8 kV Surge Arrester. Substation: FTZDescription of occurrence:Inspection in 06/21/2005, at 19:20h. Room temperature of 26

    oC and relative humidity of 72 %.

    Thermal critical state level 2.Action: removal of operation equipment.

    19,2C

    41,8C

    20

    30

    40ase B*: 36,0C

    Figure 11. Thermogram carried out in the field during inspection.

    Laboratory analyses:

    Measurement of leakage current and dielectric losses: It was not possible to carry out the analyses

    due to high losses. The equipment was submitted to a tension of 15 kV/3 in the laboratory and monitored with the IRCamera:

  • 8/3/2019 IR SA Case Study

    9/12

    InfraMation 2006 Proceedings ITC 115 A 2006-05-22

    Ar1:max 67.3

    29.1

    76.9 C

    40

    60

    FLIR Systems

    Figure 12. Thermal profile similar to that in the field.

    Figure 13. Opening of the unit:

    Case 7:13, 8 kV Surge Arrester. Substation: MTTDescription of occurrence:Inspection in 08/06/2002, at 18:30h. Room temperature of 23

    oC and relative humidity of 71 %.

    Thermal critical state level 2.Action: removal of operational equipment.

    19,3C

    40,1C

    20

    30

    40

    Fase C: 31,1C

    Figure 14. Thermograms carried out in the field duringinspection.

  • 8/3/2019 IR SA Case Study

    10/12

  • 8/3/2019 IR SA Case Study

    11/12

    InfraMation 2006 Proceedings ITC 115 A 2006-05-22

    18,4C

    38,1C

    20

    3029,6C

    18,4C

    38,1C

    20

    30

    Figure 17. Phase B Figure 17b. After cleaning

    18,4C

    38,1C

    20

    30FC: 31,1C

    18,4C

    38,1C

    20

    3025,3C

    Figure 18. Phase C Figure 18b. After Cleaning

    SUMMARYTo characterize heating rings in the body of the equipment it is necessary to do a study of the differentphases from different angles; Whenever possible, the cleaning procedure of the porcelain and repetition ofthe measurement is recommended, as a way to reduce doubts regarding apparent heating due to pollution;The comparative evaluation proved to be more efficient, considering as premises the similar operationalbackground, same maker and type; in all cases the cause is the loss of estanqueity with humidity penetration,increase of internal leakage current and heating.

    REFERENCEITC Infrared Training Center - Level II Course;

  • 8/3/2019 IR SA Case Study

    12/12

    InfraMation 2006 Proceedings ITC 115 A 2006-05-22