GENERAL OVERVIEW OF
CONTRACTS MANAGEMENT
A Presentation by:
Reeta Bandopadhyay GM(CS/P&S)
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 2/58
May 23, 2012
CHANGING BUSINESSENVIRONMENT
REGULATOR IS IN PLACE Employer’s liberties curtailed
Tariff must reflect real cost Closure in specified time frame
Competitive environment resulting due to coming of private sector
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 3/58
May 23, 2012
CHANGING BUSINESSENVIRONMENT
MORE STRINGENT TIMEFRAME
Completion schedule reduced from 60 52 44 36
CHANGING TAXATION STRUCTURE
Creating uncertainty
(VAT, Service Tax, Entry Tax etc.) Increasing risks
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 4/58
May 23, 2012
CHANGING BUSINESSENVIRONMENT
INCREASED BUSINESS OPPORTUNITIESFOR SUPPLIERS
Able to make choice
Business at preferred terms
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 5/58
May 23, 2012
CHANGING BUSINESSENVIRONMENT
INCREASED DEMAND FOR TRANSPARENCY
Right of Information Act 2005
Clauses relating to fraud and corruption,ineligibility, integrity pacts
Publication of contract award details
Debriefing
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 6/58
May 23, 2012
CHANGING BUSINESSENVIRONMENT
INCREASED ENVIRONMENTAL AND SOCIALIMPACTS
Need for improved technology
Concern for natural resources limitation.
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 7/58
May 23, 2012
PUBLIC PROCUREMENT IN INDIA
OBJECTIVES
ECONOMY
EFFICIENCY TRANSPARENCY
ACCOUNTABILITY
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 8/58
May 23, 2012
Total value Rs. 4500 billion
13% of national budget
20% of GDP
No regulatory framework
PUBLIC PROCUREMENT IN INDIA
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 9/58
May 23, 2012
The Govt. is the same, the procurement objectives are the same, even the specific works/goods can be the same, the bidding community is the same but the procedures and policies practiced by each agency are different.
There are about more than 150 different contract
formats are in use by Govt. deptts. and PSE’s.
PUBLIC PROCUREMENT IN INDIA
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 10/58
May 23, 2012
What can be done
Introduce a public procurement law which should,as a minimum, cover the objectives, substantive
procedural requirements to achieve them,debriefing of unsuccessful bidders and publication of contract awards. The law may also cover post award issues in contract implementation such as
securities, timely payment, penalties & damages,dispute resolution and termination for default or conveniences.
PUBLIC PROCUREMENT IN INDIA
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 11/58
May 23, 2012
Law to be complemented by set of regulations to replace multiplicity of rules & orders issued by different agencies of govt.
Regulations to enshrine five fundamental principles of open tendering viz.- Effective advertisement, non discriminatory tender conditions and technical specifications, public tender opening,
PUBLIC PROCUREMENT IN INDIA
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 12/58
May 23, 2012
Evaluation only in accordance with pre-disclosed criteria and methodology and award to the lowest evaluated qualified tenderer without any
negotiations on price or other terms.
PUBLIC PROCUREMENT IN INDIA
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 13/58
May 23, 2012
I. PRE-AWARD CONTRACT MANAGEMENT
II. POST-AWARD CONTRACT MANAGEMENT
III. CONTRACT CLOSING
CONTRACT MANAGEMENT – An Overview
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 14/58
May 23, 2012
Complexity in construction of large projects may necessitate sharing of responsibilities amongst various
specialised functions of an organisation
DIVISION OF RESPONSIBILITIES
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 15/58
May 23, 2012
I. CONTRACT PACKAGING
II. TENDERING
PRE-AWARD CONTRACT MANAGEMENT
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 16/58
May 23, 2012
To optimize number of contracts to be
handled for better planning, coordination and timely execution of whole project at optimum cost to the Employer.
WHY PAGKAGING?
CONTRACT PACKAGING
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 17/58
May 23, 2012
CONTRACTPACKAGE
Competitive
Aspects
Content of Contract Package
Timing of Delivery
Institutional Capability
Market Practices Location
CONTRACT PACKAGING CRITERIA
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 18/58
May 23, 2012
1. CONTENT OF CONTRACT PACKAGE
Allow manufacturers to bid directly
Bid packages should comprise equipment of similar
type that can be procured by one manufacturer to obtain best price.
Combine equipment, supplies, and works of similar nature in one contract for economy of scale, if
possible Check the market on available sources of goods of
similar type and size to obtain best price.
CONTRACT PACKAGING CRITERIA
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 19/58
May 23, 2012
2. COMPETITIVE ASPECT
Select the right size of the package to allow maximum competition.
Include only equipment of the same or of related nature.
Allow bids for one, or a combination, or for all bid packages
Select the least cost combination of bid packages.
CONTRACT PACKAGING CRITERIA
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 20/58
May 23, 2012
Bidder Package Discount (Forcombined
award)
I II
A 100 150 10%
B 85 155 NO
C 80 - NO
Lowest Bid for Package-I BID C (80)
Lowest Bid for Package-II BID A (150)
Lowest Combination Bid A (100+150) – 10% = 225 Award
Example for least cost combination
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 21/58
May 23, 2012
3. MARKET PRACTICES
Determine the procurement of supplies according to established marketing practices such as the procurement of commodities and package the supplies accordingly.
CONTRACT PACKAGING CRITERIA
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 22/58
May 23, 2012
4. INSTITUTIONAL CAPABILITY
Determine the capability of Employer to supervise and administer contracts.
Use Design-Build and Turnkey Contracts if the Employer does not have the capability to administer contracts simultaneously
CONTRACT PACKAGING CRITERIA
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 23/58
May 23, 2012
5. LOCATION
Consider separate contract packages for civil works to be carried out in different locations, even if they
are of similar nature.
CONTRACT PACKAGING CRITERIA
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 24/58
May 23, 2012
6. TIMING OF DELIVERY
Combine supplies or works according to the requirement of the equipment or the works in view of
the overall project implementation schedule Combine equipment in one package with the same
lead for delivery
CONTRACT PACKAGING CRITERIA
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 25/58
May 23, 2012
Availability of prospective bidders
Project execution schedule
Combination/ clubbing of equipment/ services that can be advantageously engineered
Independence with regard to its work content
and clear cut terminal points for interfacing
Project financing
FACTORS TO BE CONSIDERED
CONTRACT PACKAGING
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 26/58
May 23, 2012
PROJECT FEASIBILITY REPORT (FR)
DESIGN INTENT MEMORANDA (DIM)
PROJECT SCHEMATICS
CASE STUDY
BASE DOCUMENTS FOR CONTRACT PACKAGING
CONTRACT PACKAGING
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 27/58
May 23, 2012
Mode of Tendering
Qualifying Requirements for Bidders
Bidding Documents
Invitation for Bids
Submission, Receipt And
Opening of Bids
Evaluation of Bids
Contract Award
TENDERING
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 28/58
May 23, 2012
SINGLE STAGE SINGLE ENVELOPE
Ideal for all clearly specified goods
Technical and price bids in one envelope
most common tendering procedure.
TENDERING- Mode of Tendering
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 29/58
May 23, 2012
SINGLE STAGE TWO ENVELOPE
Employed for complex equipment
Technical and price bids in separate envelopes
Varying practices for opening of price bids 1. Price bids opened after completion of technical evaluation
without permitting any adjustment in quoted price.
2. Adjustment in price on account of technical features considered in technical evaluation to make bids responsive
TENDERING- Mode of Tendering
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 30/58
May 23, 2012
TWO STAGE BIDDING
Price bid sought only after technical evaluation.
Suitable for turnkey contracts for large complex
projects where alternative technical processes are a possibility.
Works of special nature where the problem of unequal technical bids is likely to be encountered.
TENDERING- Mode of Tendering
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 31/58
May 23, 2012
QUALIFYING REQUIREMENTS (QR) FORBIDDERS No bidder to be awarded a contract unless the
Employer is satisfied that the bidder is qualified to meet his obligations under proposed contract .
TENDERING- Qualifying Requirements (QR) for Bidders
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 32/58
May 23, 2012
FACTORS FOR FRAMING OF QR
Past performance in similar type of job Financial status
Technical capability Organizational capacity QR to be written in an unambiguous manner to
avoid different interpretation during evaluation
TENDERING- Qualifying Requirements (QR) for Bidders
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 33/58
May 23, 2012
METHODS FOR DETERMINING QUALIFICATION
PRE-QUALIFICATION
Normally followed in case of contracts for civil
works and large turnkey contracts
POST-QUALIFICATION
Followed in case of equipment supply/ supply-cum-
installation contracts
TENDERING- Qualifying Requirements (QR) for Bidders
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 34/58
May 23, 2012
BIDDING DOCUMENTS
The most important ingredient of contract management function as it lays the basis for contract award and its
execution thereafter. Terms and conditions to be based on principles of
`fairness’ and `equity’
In case of contracts funded through external
assistance, SBD’s of the concerned funding agency to be followed.
TENDERING- Bidding Documents
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 35/58
May 23, 2012
CONTENT OF BIDDING DOCUMENTS
INVITATION FOR BIDS (IFB)
Standard Section not required to be changed on Package to Package basis
INSTRUCTIONS TO BIDDERS (ITB)
Standard format with package Specific details required to be filled in
TENDERING- Bidding Documents
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 36/58
May 23, 2012
BID DATA SHEET (BDS)
GENERAL CONDITIONS OF CONTRACT (GCC)
Provides package specific details to
corresponding clauses in ITB Standard conditions which shall govern the
execution of contract
TENDERING- Bidding Documents
CONTENT OF BIDDING DOCUMENTS
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 37/58
May 23, 2012
Should normally be fully descriptive and give
complete requirement in respect of Plant &Equipment/Services to be procured
TECHNICAL SPECIFICATIONS
SPECIAL CONDITIONS OF CONTRACT (SCC)
Supplements/ amends the standard conditions
in GCC for each specific package
TENDERING- Bidding Documents
CONTENT OF BIDDING DOCUMENTS
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 38/58
May 23, 2012
FORMS AND PROCEDURES (FP)
Provides formats to be filled in by the bidders to complete their bids
TENDERING- Bidding Documents
CONTENT OF BIDDING DOCUMENTS
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 39/58
May 23, 2012
Not to be kept very high so that interested bidders do not find it prohibitive. For standardization purpose,
organisation may fix the cost of bidding documents in slabs depending on estimated cost of works .
TENDERING- Bidding Documents
COST OF BIDDING DOCUMENTS
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 40/58
May 23, 2012
Ensure adequate publicity by publishing in leading national /regional newspapers
In case of ICB under WB & ADB, compliance to requirements of funding agencies such as publishing in development business of UN. Copies may also be sent to high commissions/ embassies of member
countries of funding agencies located in the country.
TENDERING- Invitation for Bids
INVITATION FOR BIDS
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 41/58
May 23, 2012
Bidding period to be decided depending upon complexity of work involved. Generally, a period of 6
weeks from IFB is considered adequate. For large and complex contracts this may be extended to 10-12 weeks.
Bids to be opened in the presence of bidder’s
representatives who choose to attend and minutes of bid opening to be prepared
TENDERING- Submission, Receipt and Opening of Bids
SUBMISSION, RECEIPT AND OPENING OF BIDS
TENDERING
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 42/58
May 23, 2012
Bids to be evaluated for determining the lowest evaluated bid in terms of specified evaluation criteria
Preliminary examination of bids to determine
Bidder’s eligibility Acceptability of bid security Completeness of bid
TENDERING- Evaluation of Bids
EVALUATION OF BIDS
TENDERING
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 43/58
May 23, 2012
Preliminary examination of bids to determine
Acceptability of Joint Venture Agreement / Joint Deed Of Undertaking (if envisaged) Computational errors in bid prices Stated deviations from bidding conditions
TENDERING- Evaluation of Bids
EVALUATION OF BIDS
TENDERING
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 44/58
May 23, 2012
Detailed evaluation for substantially responsive bids only. Evaluation to consider bid price and other
factors such as cost compensation for deviations,differential price for guaranteed parameters etc.
In case of ICB, bid prices to be converted into a single currency at the specified exchange rate.
TENDERING- Evaluation of Bids
EVALUATION OF BIDS
TENDERING
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 45/58
May 23, 2012
Domestic price preference/ purchase preference to be considered wherever applicable
In absence of pre-qualification, determine whether the lowest evaluated bidder meets the specified qr.
Post bid clarifications, if any, should not call for
material alterations in the bid.
TENDERING- Evaluation of Bids
EVALUATION OF BIDS
TENDERING
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 46/58
May 23, 2012
Contract to be awarded to the lowest evaluated technically and commercially responsive bid.
Process of evaluation and approval of award recommendation including concurrence of funding agency (wherever applicable) and post-bid discussions with successful bidder to be completed
within bid validity period.
TENDERING- Contract Award
CONTRACT AWARD
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 47/58
May 23, 2012
AREAS OF CONCERN
Lack of unified system/multiplicity of practices
Lack of comprehensive and well articulated public procurement policies
Lack of comprehensive legal regime
Weak capacity of procurement staff
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 48/58
May 23, 2012
Lack of accountability
Loose institutional and organizational arrangements for processing procurement and for collective decision making in awarding of contracts
Absence of independent appeals body
Lack of independent procurement auditing function
AREAS OF CONCERN
POST AWARD
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 49/58
May 23, 2012
MAJOR POST –
AWARD ACTIVITIES Signing of contract agreement
Obtaining performance and advance securities
Approval of manufacturing / construction drawings
Finalisation and approval of quality plans
Amendments / modifications to contract as may
be necessitated during contract execution
POST – AWARDCONTRACT MANAGEMENT
POST AWARD
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 50/58
May 23, 2012
Inspection and testing of equipment at manufacturer’s works
Entire co-ordination of work at project site including monitoring
of receipt of material, identifying space for contractor’s site office establishment, ensuring timely receipt of contractors’s erection/ construction equipment, review of manpower deployment of contractor, providing site fronts and other inputs/owner issue material etc., Supervision/ monitoring of
erection/ construction work, start-up activities, trial operation/ commissioning, performance and guarantee tests.
POST – AWARDCONTRACT MANAGEMENT
MAJOR POST –
AWARD ACTIVITIES
POST AWARD
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 51/58
May 23, 2012
POST-AWARD CONTRACT PLANNING & MONITORING
Periodic contract review meetings (CRMs) between employer and contractor
Submission of monthly progress reports by contractor indicating progress achieved and work on hand
POST – AWARDCONTRACT MANAGEMENT
POST AWARD
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 52/58
May 23, 2012
Project review team (PRT) meetings of the project authority on monthly basis
Preparation of exception reports indicating hold ups/bottle necks for close monitoring of critical areas
POST-AWARD CONTRACT PLANNING & MONITORING
POST – AWARDCONTRACT MANAGEMENT
POST AWARD
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 53/58
May 23, 2012
Contract price may vary due to : Addition/ deletions in items of work
Change in quantity of work
Change in technical parameters resulting in changed design features, materials etc.
COST CONTROL SYSTEM
POST – AWARDCONTRACT MANAGEMENT
POST AWARD
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 54/58
May 23, 2012
Due care is to be taken while finalising technical specifications to avoid post award changes in ordered quantities.
Changes during detailed engineering to be closely monitored while releasing construction drawings with respect to quantities reflected in drawings vis-à-vis BOQ
Engineering progress of each contract to be essentially
monitored at identified intervals
POST – AWARDCONTRACT MANAGEMENT
POST AWARD
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 55/58
May 23, 2012
CONTRACT BUDGETING SYSTEM
Contract budgeting is essential for proper forecasting and planning of funds on monthly/quarterly/annual
basis.
Yearly budget for a contract to be prepared based on detailed payment schedule tied-up with the contractor
Budgeted expenditure (be) for a financial year to be finalised much before the start of financial year.
POST – AWARDCONTRACT MANAGEMENT
POST AWARD
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 56/58
May 23, 2012
CONTRACT BUDGETING SYSTEM (contd.)
Review the budgeted expenditure during middle of financial year and prepare revised expenditure taking
into account the physical progress of work.
POST – AWARDCONTRACT MANAGEMENT
7/31/2019 CMS-03.11.08
http://slidepdf.com/reader/full/cms-031108 57/58
May 23, 2012
All concerned departments/ functions of project authority involved in contract execution to issue certificates certifying fulfillment of respective obligations by the contractor.
Contractor to furnish ‘no claim certificate’ to the employer
Contractor to be discharged of its obligations under the contract after completion of defect liability period.
CONTRACT CLOSING