CMS-03.11.08

58
GENERAL OVERVIEW OF CONTRACTS MANAGEMENT  A Presentation by: Reeta Bandopadhyay GM(CS/P&S)

Transcript of CMS-03.11.08

Page 1: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 1/58

GENERAL OVERVIEW OF

CONTRACTS MANAGEMENT

 A Presentation by:

Reeta Bandopadhyay GM(CS/P&S)

Page 2: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 2/58

May 23, 2012

CHANGING BUSINESSENVIRONMENT

REGULATOR IS IN PLACE  Employer’s liberties curtailed  

Tariff must reflect real cost  Closure in specified time frame 

Competitive environment resulting due to coming of private sector 

Page 3: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 3/58

May 23, 2012

CHANGING BUSINESSENVIRONMENT

MORE STRINGENT TIMEFRAME

Completion schedule reduced from 60  52  44  36 

CHANGING TAXATION STRUCTURE

Creating uncertainty 

(VAT, Service Tax, Entry Tax etc.) Increasing risks  

Page 4: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 4/58

May 23, 2012

CHANGING BUSINESSENVIRONMENT

INCREASED BUSINESS OPPORTUNITIESFOR SUPPLIERS

Able to make choice 

Business at preferred terms 

Page 5: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 5/58

May 23, 2012

CHANGING BUSINESSENVIRONMENT

INCREASED DEMAND FOR TRANSPARENCY 

Right of Information Act 2005 

Clauses relating to fraud and corruption,ineligibility, integrity pacts 

Publication of contract award details 

Debriefing  

Page 6: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 6/58

May 23, 2012

CHANGING BUSINESSENVIRONMENT

INCREASED ENVIRONMENTAL AND SOCIALIMPACTS

Need for improved technology 

Concern for natural resources limitation.

Page 7: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 7/58

May 23, 2012

PUBLIC PROCUREMENT IN INDIA

OBJECTIVES

ECONOMY

EFFICIENCY TRANSPARENCY

ACCOUNTABILITY

Page 8: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 8/58

May 23, 2012

Total value Rs. 4500 billion 

13% of national budget 

20% of GDP 

No regulatory framework  

PUBLIC PROCUREMENT IN INDIA

Page 9: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 9/58

May 23, 2012

The Govt. is the same, the procurement objectives are the same, even the specific works/goods can be the same, the bidding community is the same but the procedures and policies practiced by each agency are different.

There are about more than 150 different contract 

formats are in use by Govt. deptts. and PSE’s. 

PUBLIC PROCUREMENT IN INDIA

Page 10: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 10/58

May 23, 2012

What can be done

Introduce a public procurement law which should,as a minimum, cover the objectives, substantive 

procedural requirements to achieve them,debriefing of unsuccessful bidders and publication of contract awards. The law may also cover post award issues in contract implementation such as 

securities, timely payment, penalties & damages,dispute resolution and termination for default or conveniences.

PUBLIC PROCUREMENT IN INDIA

Page 11: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 11/58

May 23, 2012

Law to be complemented by set of regulations to replace multiplicity of rules & orders issued by different agencies of govt.

Regulations to enshrine five fundamental principles of open tendering viz.- Effective advertisement, non discriminatory tender conditions and technical specifications, public tender opening,

PUBLIC PROCUREMENT IN INDIA

Page 12: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 12/58

May 23, 2012

Evaluation only in accordance with pre-disclosed criteria and methodology and award to the lowest evaluated qualified tenderer without any 

negotiations on price or other terms.

PUBLIC PROCUREMENT IN INDIA

Page 13: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 13/58

May 23, 2012

I. PRE-AWARD CONTRACT MANAGEMENT

II. POST-AWARD CONTRACT MANAGEMENT

III. CONTRACT CLOSING

CONTRACT MANAGEMENT – An Overview  

Page 14: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 14/58

May 23, 2012

Complexity in construction of large projects may necessitate sharing of responsibilities amongst various 

specialised functions of an organisation 

DIVISION OF RESPONSIBILITIES

Page 15: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 15/58

May 23, 2012

I. CONTRACT PACKAGING

II. TENDERING

PRE-AWARD CONTRACT MANAGEMENT

Page 16: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 16/58

May 23, 2012

To optimize number of contracts to be 

handled for better planning, coordination and timely execution of whole project at optimum cost to the Employer.

WHY PAGKAGING? 

CONTRACT PACKAGING

Page 17: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 17/58

May 23, 2012

CONTRACTPACKAGE

Competitive 

Aspects 

Content of Contract Package 

Timing of Delivery 

Institutional Capability 

Market Practices Location 

CONTRACT PACKAGING CRITERIA

Page 18: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 18/58

May 23, 2012

1. CONTENT OF CONTRACT PACKAGE

Allow manufacturers to bid directly 

Bid packages should comprise equipment of similar 

type that can be procured by one manufacturer to obtain best price.

Combine equipment, supplies, and works of similar nature in one contract for economy of scale, if 

possible  Check the market on available sources of goods of 

similar type and size to obtain best price.

CONTRACT PACKAGING CRITERIA

Page 19: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 19/58

May 23, 2012

2. COMPETITIVE ASPECT

Select the right size of the package to allow maximum competition.

Include only equipment of the same or of related nature.

Allow bids for one, or a combination, or for all bid packages 

Select the least cost combination of bid packages.

CONTRACT PACKAGING CRITERIA

Page 20: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 20/58

May 23, 2012

Bidder Package Discount (Forcombined

award)

I II

A 100 150 10%

B 85 155 NO

C 80 - NO

Lowest Bid for Package-I BID C (80)

Lowest Bid for Package-II BID A (150)

Lowest Combination Bid A (100+150) – 10% = 225 Award

Example for least cost combination

Page 21: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 21/58

May 23, 2012

3. MARKET PRACTICES

Determine the procurement of supplies according to established marketing practices such as the procurement of commodities and package the supplies accordingly.

CONTRACT PACKAGING CRITERIA

Page 22: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 22/58

May 23, 2012

4.  INSTITUTIONAL CAPABILITY

Determine the capability of Employer to supervise and administer contracts.

Use Design-Build and Turnkey Contracts if the Employer does not have the capability to administer contracts simultaneously 

CONTRACT PACKAGING CRITERIA

Page 23: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 23/58

May 23, 2012

5.  LOCATION

Consider separate contract packages for civil works to be carried out in different locations, even if they 

are of similar nature.

CONTRACT PACKAGING CRITERIA

Page 24: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 24/58

May 23, 2012

6. TIMING OF DELIVERY

Combine supplies or works according to the requirement of the equipment or the works in view of 

the overall project implementation schedule  Combine equipment in one package with the same 

lead for delivery 

CONTRACT PACKAGING CRITERIA

Page 25: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 25/58

May 23, 2012

Availability of prospective bidders 

Project execution schedule 

Combination/ clubbing of equipment/ services that can be advantageously engineered 

Independence with regard to its work content 

and clear cut terminal points for interfacing 

Project financing  

FACTORS TO BE CONSIDERED 

CONTRACT PACKAGING

Page 26: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 26/58

May 23, 2012

PROJECT FEASIBILITY REPORT (FR) 

DESIGN INTENT MEMORANDA (DIM) 

PROJECT SCHEMATICS 

CASE STUDY  

BASE DOCUMENTS FOR CONTRACT PACKAGING 

CONTRACT PACKAGING

Page 27: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 27/58

May 23, 2012

Mode of Tendering 

Qualifying Requirements for Bidders 

Bidding Documents 

Invitation for Bids 

Submission, Receipt And 

Opening of Bids 

Evaluation of Bids 

Contract Award 

TENDERING

Page 28: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 28/58

May 23, 2012

SINGLE STAGE SINGLE ENVELOPE

Ideal for all clearly specified goods 

Technical and price bids in one envelope 

most common tendering procedure.

TENDERING- Mode of Tendering  

Page 29: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 29/58

May 23, 2012

SINGLE STAGE TWO ENVELOPE 

 Employed for complex equipment 

Technical and price bids in separate envelopes 

Varying practices for opening of price bids 1. Price bids opened after completion of technical evaluation 

without permitting any adjustment in quoted price.

2. Adjustment in price on account of technical features considered in technical evaluation to make bids responsive  

TENDERING- Mode of Tendering  

Page 30: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 30/58

May 23, 2012

TWO STAGE BIDDING

Price bid sought only after technical evaluation.

Suitable for turnkey contracts for large complex 

projects where alternative technical processes are a possibility.

Works of special nature where the problem of unequal technical bids is likely to be encountered.

TENDERING- Mode of Tendering  

Page 31: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 31/58

May 23, 2012

QUALIFYING REQUIREMENTS (QR) FORBIDDERS  No bidder to be awarded a contract unless the 

Employer is satisfied that the bidder is qualified to meet his obligations under proposed contract .

TENDERING- Qualifying Requirements (QR) for Bidders 

Page 32: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 32/58

May 23, 2012

FACTORS FOR FRAMING OF QR

Past performance in similar type of job  Financial status 

Technical capability  Organizational capacity  QR to be written in an unambiguous manner to 

avoid different interpretation during evaluation 

TENDERING- Qualifying Requirements (QR) for Bidders 

Page 33: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 33/58

May 23, 2012

METHODS FOR DETERMINING QUALIFICATION

PRE-QUALIFICATION 

Normally followed in case of contracts for civil 

works and large turnkey contracts 

POST-QUALIFICATION  

Followed in case of equipment supply/ supply-cum- 

installation contracts 

TENDERING- Qualifying Requirements (QR) for Bidders 

Page 34: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 34/58

May 23, 2012

BIDDING DOCUMENTS

The most important ingredient of contract management function as it lays the basis for contract award and its 

execution thereafter. Terms and conditions to be based on principles of 

`fairness’ and `equity’  

In case of contracts funded through external 

assistance, SBD’s of the concerned funding agency to be followed. 

TENDERING- Bidding Documents 

Page 35: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 35/58

May 23, 2012

CONTENT OF BIDDING DOCUMENTS

INVITATION FOR BIDS (IFB)  

Standard Section not required to be changed on Package to Package basis  

INSTRUCTIONS TO BIDDERS (ITB)  

Standard format with package Specific details required to be filled in 

TENDERING- Bidding Documents 

Page 36: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 36/58

May 23, 2012

 BID DATA SHEET (BDS) 

GENERAL CONDITIONS OF CONTRACT (GCC)  

Provides package specific details to 

corresponding clauses in ITB   Standard conditions which shall govern the 

execution of contract 

TENDERING- Bidding Documents 

CONTENT OF BIDDING DOCUMENTS 

Page 37: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 37/58

May 23, 2012

Should normally be fully descriptive and give 

complete requirement in respect of Plant &Equipment/Services to be procured 

TECHNICAL SPECIFICATIONS  

SPECIAL CONDITIONS OF CONTRACT (SCC)  

Supplements/ amends the standard conditions 

in GCC for each specific package  

TENDERING- Bidding Documents 

CONTENT OF BIDDING DOCUMENTS

Page 38: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 38/58

May 23, 2012

FORMS AND PROCEDURES (FP) 

Provides formats to be filled in by the bidders to complete their bids 

TENDERING- Bidding Documents 

CONTENT OF BIDDING DOCUMENTS

Page 39: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 39/58

May 23, 2012

Not to be kept very high so that interested bidders do not find it prohibitive. For standardization purpose,

organisation may fix the cost of bidding documents in slabs depending on estimated cost of works .

TENDERING- Bidding Documents 

COST OF BIDDING DOCUMENTS

Page 40: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 40/58

May 23, 2012

Ensure adequate publicity by publishing in leading national /regional newspapers  

In case of ICB under WB & ADB, compliance to requirements of funding agencies such as publishing in development business of UN. Copies may also be sent to high commissions/ embassies of member 

countries of funding agencies located in the country.

TENDERING- Invitation for Bids 

INVITATION FOR BIDS

Page 41: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 41/58

May 23, 2012

Bidding period to be decided depending upon complexity of work involved. Generally, a period of 6 

weeks from IFB is considered adequate. For large and complex contracts this may be extended to 10-12 weeks.

Bids to be opened in the presence of  bidder’s 

representatives who choose to attend and minutes of bid opening to be prepared 

TENDERING- Submission, Receipt and Opening of Bids 

SUBMISSION, RECEIPT AND OPENING OF BIDS

TENDERING

Page 42: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 42/58

May 23, 2012

Bids to be evaluated for determining the lowest evaluated bid in terms of specified evaluation criteria 

Preliminary examination of bids to determine 

Bidder’s eligibility  Acceptability of bid security  Completeness of bid 

TENDERING- Evaluation of Bids 

EVALUATION OF BIDS

TENDERING

Page 43: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 43/58

May 23, 2012

Preliminary examination of bids to determine  

Acceptability of Joint Venture Agreement / Joint Deed Of Undertaking (if envisaged) Computational errors in bid prices  Stated deviations from bidding conditions  

TENDERING- Evaluation of Bids 

EVALUATION OF BIDS

TENDERING

Page 44: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 44/58

May 23, 2012

Detailed evaluation for substantially responsive bids only. Evaluation to consider bid price and other 

factors such as cost compensation for deviations,differential price for guaranteed parameters etc.

In case of ICB, bid prices to be converted into a single currency at the specified exchange rate. 

TENDERING- Evaluation of Bids 

EVALUATION OF BIDS

TENDERING

Page 45: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 45/58

May 23, 2012

Domestic price preference/ purchase preference to be considered wherever applicable 

In absence of pre-qualification, determine whether the lowest evaluated bidder meets the specified qr.

Post bid clarifications, if any, should not call for 

material alterations in the bid. 

TENDERING- Evaluation of Bids 

EVALUATION OF BIDS

TENDERING

Page 46: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 46/58

May 23, 2012

Contract to be awarded to the lowest evaluated technically and commercially responsive bid.

Process of evaluation and approval of award recommendation including concurrence of funding agency (wherever applicable) and post-bid discussions with successful bidder to be completed 

within bid validity period. 

TENDERING- Contract Award 

CONTRACT AWARD

Page 47: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 47/58

May 23, 2012

AREAS OF CONCERN

Lack of unified system/multiplicity of practices 

Lack of comprehensive and well articulated public procurement policies 

Lack of comprehensive legal regime 

Weak capacity of procurement staff 

Page 48: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 48/58

May 23, 2012

Lack of accountability 

Loose institutional and organizational arrangements for processing procurement and for collective decision making in awarding of contracts 

Absence of independent appeals body 

Lack of independent procurement auditing function 

AREAS OF CONCERN

POST AWARD

Page 49: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 49/58

May 23, 2012

MAJOR POST  –

AWARD ACTIVITIES   Signing of contract agreement 

Obtaining performance and advance securities 

Approval of manufacturing / construction drawings 

Finalisation and approval of quality plans 

Amendments / modifications to contract as may 

be necessitated during contract execution  

POST  – AWARDCONTRACT MANAGEMENT

POST AWARD

Page 50: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 50/58

May 23, 2012

Inspection and testing of equipment at manufacturer’s works 

Entire co-ordination of work at project site including monitoring 

of receipt of material, identifying space for  contractor’s site office establishment, ensuring timely receipt of  contractors’s erection/ construction equipment, review of manpower deployment of contractor, providing site fronts and other inputs/owner issue material etc., Supervision/ monitoring of 

erection/ construction work, start-up activities, trial operation/ commissioning, performance and guarantee tests.

POST  – AWARDCONTRACT MANAGEMENT

MAJOR POST  –

AWARD ACTIVITIES  

POST AWARD

Page 51: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 51/58

May 23, 2012

POST-AWARD CONTRACT PLANNING & MONITORING 

Periodic contract review meetings (CRMs) between employer and contractor 

Submission of monthly progress reports by contractor indicating progress achieved and work on hand 

POST  – AWARDCONTRACT MANAGEMENT

POST AWARD

Page 52: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 52/58

May 23, 2012

Project review team (PRT) meetings of the project authority on monthly basis 

Preparation of exception reports indicating hold ups/bottle necks for close monitoring of critical areas  

POST-AWARD CONTRACT PLANNING & MONITORING 

POST  – AWARDCONTRACT MANAGEMENT

POST AWARD

Page 53: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 53/58

May 23, 2012

  Contract price may vary due to :   Addition/ deletions in items of work 

Change in quantity of work 

Change in technical parameters resulting in changed design features, materials etc.

COST CONTROL SYSTEM 

POST  – AWARDCONTRACT MANAGEMENT

POST AWARD

Page 54: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 54/58

May 23, 2012

Due care is to be taken while finalising technical specifications to avoid post award changes in ordered quantities.

Changes during detailed engineering to be closely monitored while releasing construction drawings with respect to quantities reflected in drawings vis-à-vis BOQ 

Engineering progress of each contract to be essentially 

monitored at identified intervals 

POST  – AWARDCONTRACT MANAGEMENT

POST AWARD

Page 55: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 55/58

May 23, 2012

 CONTRACT BUDGETING SYSTEM 

Contract budgeting is essential for proper forecasting and planning of funds on monthly/quarterly/annual 

basis.

Yearly budget for a contract to be prepared based on detailed payment schedule tied-up with the contractor 

Budgeted expenditure (be) for a financial year to be finalised much before the start of financial year. 

POST  – AWARDCONTRACT MANAGEMENT

POST AWARD

Page 56: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 56/58

May 23, 2012

CONTRACT BUDGETING SYSTEM  (contd.)  

Review the budgeted expenditure during middle of financial year and prepare revised expenditure taking 

into account the physical progress of work.

POST  – AWARDCONTRACT MANAGEMENT

Page 57: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 57/58

May 23, 2012

All concerned departments/ functions of project authority involved in contract execution to issue certificates certifying fulfillment of respective obligations by the contractor.

Contractor to furnish  ‘no claim  certificate’  to the employer 

Contractor to be discharged of its obligations under the contract after completion of defect liability period.

CONTRACT CLOSING

Page 58: CMS-03.11.08

7/31/2019 CMS-03.11.08

http://slidepdf.com/reader/full/cms-031108 58/58

 THANK YOU