CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki...

32
CCC status report 14/12/2004 D.Manglunki AB/OP 1 Status of the CERN Control Centre D.Manglunki AB/OP

Transcript of CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki...

Page 1: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 1

Status of the CERN Control Centre

D.Manglunki AB/OP

Page 2: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 2

ACKNOWLEDGEMENTS:

R.Bailey, J.-L.Baldy, M.Bätz, B.Frammery,R.Saban, L.Serio

M.Delrieux, R.Giachino, S.Knoops, E.Liénard, L.Randot, L.Stewart

M.Clark, D.Hartley, J.Wood

René Ballet, A.Bland, P.Charrue, J.J.Cloye, C.Frisk, R.Hopkins

S.Anghelone, M.Poehler,P.Vachetta

L.Burguete-Oliete, M.Colin, R.Forrest, R.Lauckner

Page 3: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 3

Outline

• Update on OP days 4-5/3/2004• Current plan:

– 874 extension– Control desks– Layout

• Staff• Schedule• Remaining issues

Page 4: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 4

Current building extension plan

• No budget for original plan – No closing of ex-CCR and ex-PCR– Loss of > 200m2

– No visitors’gallery– Combine conference room/remote

MD/videoconference – No sacrifice on operators‘ facilities

Page 5: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 5

Current building extension plan

Page 6: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 6

Current building extension plan

Page 7: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 7

Current building extension plan

Page 8: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 8

Current building extension plan

Page 9: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 9

Control system

• Standard consoles for all desks… • …But different OS

– 2006 start-up with existing 2004 applications

• 4 different Access systems– SPS & EA as is– PS panels emulated– LHC new system

Page 10: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 10

Control Desks• 3 screens control display

• 3 screens fixed display (shared by 2)

• 1 administrative PC(shared by 2)

• 5.0 m radius

• 0.65 m deep (+0.65 m)

• 0.72 m high

Page 11: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 11

Control Desks

Page 12: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 12

Control Desks: 4 firms selected for tendering

Page 13: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 13

Control Desks: 4 firms selected for tendering

Page 14: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 14

Layouts• 1 GTD• 2 CCD

• 2 CCC-WG

• 1 IDOC• Workshop held on 5/11

CCC-WG, IDOC, CCD, S.Baird

Page 15: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 15

Layout

• 35 control console modules

• 5 access console modules

• 4 Mail/etc PC tables

• 1 social area

• Storage furniture

Laura Stewart AT/ECR

Page 16: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 16Laura Stewart AT/ECR

Page 17: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 17

Room ergonomics• Lighting

– 7x11 direct/indirect (20%-80%) from ceiling provide background 200+ Lux

– task lighting at workstation level

• Acoustics– Ceiling, walls, floor & furniture acoustically treated– Acoustic screens behind consoles– RT<0.6s

• Interior decoration– 3 Harmonious colour scheme – 4th chosen by IDOC

Page 18: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 18Mike Clark CCD

Page 19: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 19Mike Clark CCD

Page 20: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 20Mike Clark CCD

Page 21: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 21Mike Clark CCD

Page 22: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 22

Staff policy• Mandate: “Define the operating scenario of the

CCC and make recommendations about the management and possible harmonization of the various categories of personnel corresponding to the different CCC usages”

• WG recommendation: 1 single group as soon as possible– merging TCR + MCR teams in 2005

• Method: establish scenario for 2010+ (“LHC steady state”) then study transition

Page 23: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 23

Staff policy: LHC steady state (2010+)• 10 shift workers:

– 6 senior operators: LHC, SPS, PS, PSB, TI, Cryo

– 3 junior operators SPS, PS, TI/Cryo– 1 LHC EiC

• Shift coordinator among senior operators– Experience of running accelerators– Good understanding of TI & Cryo– CP D

PSBooster

PS SPS LHCTech.

Infrastr.Cryo

JuniorSPS

JuniorPS

JuniorTI/Cryo

Page 24: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 24

Staff policy: PS/SPS shutdown (2005)

PSBooster

Tech.Infrastr.

JuniorPSB

AB/OP CRYO/OP

Senior

Junior

CryoACR

CryoACR

CryoECR

MCR Local control rooms

3x8 shift also during SD (minimum 2 TI in MCR)

3x8 shift1x8

On-call2x8Shift

legend

Page 25: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 25

Staff policy: LHC Hardware commissioning (2006-2007)

PSBooster

PS SPSTech.

Infrastr.

JuniorSPS

JuniorPS

AB/OP CRYO/OP

Senior

Junior

CryoACR

CryoACR

CryoECR

CCC Local control rooms

HC LHC

Field CR Field CR

3x8 shift also during SD (minimum 2 TI in MCR)

3x8 shift1x8

On-call2x8Shift

legend

Page 26: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 26

Staff policy: LHC start-up (2007-2008)

PSBooster

PS SPS LHCTech.

Infrastr.

JuniorSPS

JuniorPS

JuniorTI

CryoECR

CryoACR

AB/OP CRYO/OP

Senior

Junior

CryoACR

CryoECR

CCC

3x8 shift1x8

On-call2x8Shift

legend

Page 27: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 27

Staff policy: LHC steady state (2010+)

PSBooster

PS SPS LHCTech.

Infrastr.

JuniorSPS

JuniorPS

JuniorTI/Cryo

AB/OP

Senior

Junior

SeniorCryo

CRYO/OP

CryoAcceler.

CryoExper.

CCC

3x8 shift1x8

On-call2x8Shift

legend

Page 28: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 28

The (very tight) Planning: 59 weeks to go

• 31/12/2004: CE Studies completed, call for tenders out, preparatory works completed; start of civil engineering

• 1/11/2005: building ready; installation begins, followed by commissioning

• 1/2/2006: CCC commissioned, ready for OP

Page 29: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 29

Planning: 59 weeks to go

Page 30: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 30

Status of the work• Concrete slab poured• PCR empty• Servers in BA3• IT for consoles going

out• … so far so good!

Page 31: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 31

Remaining issues

• Operators chairs

• Access systems

• Control system: when to converge?

• Communications

• Fast analog signals

• Parking / Office space

Page 32: CCC status report 14/12/2004D.Manglunki AB/OP 1 Status of the CERN Control Centre D. Manglunki AB/OP.

CCC status report 14/12/2004 D.Manglunki AB/OP 32

Conclusions• The CCC project is now well on its way• Tight schedule but respected so far