KER Projec Kerala St T.C.11/33 Keston R Kawdiar Thiruvan P RALA (UN MO ct Mana tate Transp 39, Sree Ba Road, Nanth P.O. anthapuram PUBLIC GO STAT NDER WOR ONTH agemen ort Project la Building hancode, m - 695003 C WOR VERNM TE TR RLD BANK LY PR AUG t Team RKS D MENT O RANSP ASSISTAN ROGR GUST 2 DEPART F KERA PORT NCE – Loan RESS 016 TMENT ALA PROJ n No. 825 S BRIE T JECT 4) EF - II

Transcript of KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE...

Page 1: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

KER

ProjecKerala StT.C.11/33Keston RKawdiar Thiruvan

P

RALA (UN

MO

ct Manatate Transp39, Sree Ba

Road, Nanth P.O. anthapuram

PUBLICGO

STATNDER WOR

ONTH

agemenort Project la Building

hancode,

m - 695003

C WORVERNM

TE TRRLD BANK

LY PRAUG

t Team

RKS DMENT O

RANSP ASSISTAN

ROGRGUST 2

DEPARTF KERA

PORT NCE – Loan

RESS016

TMENTALA

PROJn No. 825

S BRIE

T

JECT4)

EF

- II

Page 2: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

ProjecKerala StT.C.11/33Keston RKawdiar

KERA(UN

ct Manatate Transp39, Sree Ba

Road, Nanth P.O., Thiruv

PUBLIGOV

ALA STADER WOR

MONT

agemenort Project la Building

hancode, vananthapu

IC WORVERNM

ATE TRRLD BANK

THLY PAUG

t Team

uram - 6950

RKS DEMENT O

RANSPO ASSISTAN

PROGREGUST 2

003

EPARTMOF KERA

ORT PRNCE – Loa

ESS BR2016

MENT ALA

ROJECTn No. 825

RIEF

T - II 54)

Page 3: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 3 

TABLE OF CONTENTS Kerala State Transport Project-II ............................................................................................................................... 5 Project location map ...................................................................................................................................... 5 Introduction ................................................................................................................................................................ 6 1.1  Project Development Objectives ............................................................................................... 6 1.2  Outline Project Data: ................................................................................................................ 6 1.3  Overall Implementation: ........................................................................................................... 8 1.4  Project Components ................................................................................................................. 9 2.1  Project Description .................................................................................................................... 9 2.2  Sub Component A1 (US$322 mn) ............................................................................................. 10 2.3  Supervision Consultancy ......................................................................................................... 10 2.4  Sub Component A2 (US$ 91 mn) ............................................................................................. 11 2.5  Component B – Road Safety Management (US$ 22 mn) .......................................................... 11 2.6  Component C – Institutional Strengthening (US$ 10 mn) ........................................................... 11 2.7  Project Cost and Disbursement ............................................................................................... 12 3.0  Executive Summary .................................................................................................................. 14 3.1  Upgradation Works ................................................................................................................. 14 3.2  Summary of Progress (works) ................................................................................................... 15 3.3  General Issues:........................................................................................................................ 16 4.1  Current Status of Works ........................................................................................................... 17 4.2  Contract Package I ................................................................................................................ 17 4.3  Contract Details ..................................................................................................................... 17 4.4  Progress of Works up to month (July 2016) ................................................................................ 18 4.5  Schedule of Culverts and Drainage works ................................................................................ 19 4.6  Progress Considering the Contract price up to this Month (August) ........................................... 19 4.7  Physical progress Bar Chart ..................................................................................................... 20 4.8  S-Curve .................................................................................................................................. 20 4.9  Strip map ................................................................................................................................ 21 4.10  Utilities .................................................................................................................................... 21 4.11  Potential Issues ....................................................................................................................... 22 4.12  Payments to the Contractor .................................................................................................... 22 4.13  Implementation of EMP ........................................................................................................... 22 4.14  Photograph ............................................................................................................................ 25 15.1 Contract Package - 2 ..................................................................................................................................... 26 15.2  Contract Details ..................................................................................................................... 26 15.3  Progress of Works .................................................................................................................... 27 The status of CD works are stated below: ........................................................................................... 28 15.4  Work progress considering the contract price August 2016 ....................................................... 28 15.5  Physical Progress ..................................................................................................................... 29 15.6 S-Curve .............................................................................................................................................................. 29 15.7 Strip Chart.......................................................................................................................................................... 30 15.8  Utilities .................................................................................................................................... 31 15.9  Potential Issues ....................................................................................................................... 31 15.10  Payments to the Contractor .................................................................................................... 31 15.11  Implementation of EMP ........................................................................................................... 32 15.12  Photographs ........................................................................................................................... 33 16.1 KSTP/PMT/UG – III A .......................................................................................................................................... 33 16.2  Executive Summary ................................................................................................................ 34 16.3  Pre-Construction Activities ....................................................................................................... 34 16.4  Moblisation of Resources ......................................................................................................... 35 16.5  Human resources .................................................................................................................... 35 16.6  Work Progress in detail for this month ....................................................................................... 35 16.7  Work Programme .................................................................................................................... 35 16.8  Quality Control ....................................................................................................................... 35 16.9  Source and Material Approval ................................................................................................ 35 16.10  Mix Design .............................................................................................................................. 35 16.11  Implementation of EMP - Contract Package - IIIA ........................................................................ 36 17.1 KSTP/PMT/UG – III- B .......................................................................................................................................... 37 17.2  Executive Summary ................................................................................................................ 37 17.3  Pre-Construction Activities ....................................................................................................... 38 17.4  Human Resources ................................................................................................................... 38 17.5  Quality Control/ Quality Assurance .......................................................................................... 38 17.6  Source and Material Approvals ............................................................................................... 38 18.1 Contract Package IVA .................................................................................................................................... 39 18.2  Contract Details ..................................................................................................................... 39 18.3  Work Progress ......................................................................................................................... 40 

Page 4: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 4 

18.4  Physical Progress ..................................................................................................................... 41 18.5  S-Curve .................................................................................................................................. 41 18.6  Potential Issues ....................................................................................................................... 42 18.7  Schedule of culverts and drainage works ................................................................................ 42 18.8  Payment ................................................................................................................................ 42 18.9  Implementation of EMP ........................................................................................................... 42 18.10  Photographs ........................................................................................................................... 43 19.1  Contract Package IV .............................................................................................................. 44 19.2  Contract details: ..................................................................................................................... 44 19.3  Pre-Construction Activities: ...................................................................................................... 45 19.3.1  Utilities .................................................................................................................................... 45 19.4  Physical Progress ..................................................................................................................... 47 19.5  S-Curve .................................................................................................................................. 47 19.6  Schedule of culverts and drainage works ................................................................................ 48 19.7  Payments ............................................................................................................................... 48 19.8  Implementation of EMP ........................................................................................................... 48 19.9  Photographs ........................................................................................................................... 49 20.1 Contract Package V ....................................................................................................................................... 50 20.2  Contract details: ..................................................................................................................... 50 20.3  Work Progress ......................................................................................................................... 51 20.4  Bar chart ................................................................................................................................ 52 20.5  S-Curve .................................................................................................................................. 52 20.6  Strip Map ................................................................................................................................ 53 20.7  Schedule of culverts and drainage works ................................................................................ 54 20.8  Utilities .................................................................................................................................... 54 20.9  Key issues: .............................................................................................................................. 54 20.10  Payment to the contractor ..................................................................................................... 54 20.11  Implementation of EMP ........................................................................................................... 55 20.12  Photographs ........................................................................................................................... 56 21.1  Contract Package VI .............................................................................................................. 57 21.2  Contract details: ..................................................................................................................... 57 21.3  Physical Progress: .................................................................................................................... 58 21.4  Work Progress ......................................................................................................................... 58 21.5  Bar Chart of Physical Progress: ................................................................................................. 60 21.6  S-Curve .................................................................................................................................. 60 21.7  Schedule of Cross Drainage Works .......................................................................................... 61 21.8  Implementation of EMP ........................................................................................................... 61 21.9  Payment to contractor ........................................................................................................... 63 21.10  Photographs ........................................................................................................................... 64 22.1 Contract Package VIII ..................................................................................................................................... 65 23.1  Contract Package VII ............................................................................................................. 65 24.1 Proactive actions taken by employer: .......................................................................................................... 65 25.1 Road Safety Component – Current Status ................................................................................................... 66 26.1 Institutional Strengthening Components – Current Status .......................................................................... 67 27.1  Payment to the consultants as on end August 2016: ................................................................. 68 28.1  Restructuring of KSTP II ............................................................................................................. 68 29.1 Meetings, Site visits & Inspection .................................................................................................................... 68 30.1 Land Acquisition Status ................................................................................................................................... 69 32.1  Status on Critical Actions identified by World Bank ................................................................... 70 

Page 5: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

KeraProject lo

la Statocation map

te Trannsport Projecct-II

Page 6: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 6 

Introduction Government of Kerala has decided to take up Phase-II upgradation component of KSTP

as a standalone project, the KSTP-II. The project envisages the upgradation of 363 km of

SH and MDR, Road Safety Management and Institutional Strengthening of PWD. The total

Project cost is 445 million USD out of which 216 million USD is loan assistance from World

Bank. The project loan agreement was signed on June 19, 2013 at the DEA Office, New

Delhi. The loan effectiveness date is September 6, 2013. The project implementation

period is five years, up to 30 December 2018 and the expected loan closing date is

April 30, 2019.

1.1 Project Development Objectives The Project Development objective is to improve condition, traffic flow and road safety

with a focus on vulnerable road user on Kerala State Core road networks comprising of

363 Km of state highways. The main beneficiaries of the Project will be the users living

along the Project corridors mainly the travelling public, agricultural and industrial

producers, consumers and local community. The main benefit is in the form of reduced

transport bottlenecks, lower passenger freight transport costs, reduced travel time and

improved road safety in terms of reducing severe crashes and injury. The roads identified

for improvement passes through about 87 villages covering eight districts.

1.2 Outline Project Data: The upgrading works for six roads are included in the KSTP-II. The major items of works

included are improvement to gradient, widening and strengthening the roads including

minor realignments wherever essential, reconstruction of narrow bridges and culverts and

improvements to drainage system. A Bypass also is proposed at Thiruvalla. The

carriageway proposed are generally 2 lane with 1.50 mt. slow lanes on either side with

hard shoulders and drains for a total width of 12 meters. The ROW is generally 15 Meters.

The specification for civil works are as per MORTH & IRC standards.

The land acquisition for the project roads are almost completed except in the

Perimbilavu- Pattambi- Perinthalmanna Road.

1.2.0.1 Kasargod Kanhangad Road – SH 57 Length - 27.76 km.Covers Kasargod, Pallikkara, manikoth and Kanhad areas and Tourist

destinations at Bakel Fort and Ezhimala come under this stretch.

1.2.0.2 Pilathara Pappinissery Road Length - 20.90 km. Covers Pilathara, Cheruthayam, Kunnupuram and Pappinissery.

Page 7: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 7 

1.2.0.3 Thalassery - Valavupara Road – SH 30 Length 53.12 km. It is a part of SH 30, Thalasserry – Coorg Road and passes through

Koothuparambu, Mattannor, and Irutty.

1.2.0.4 Chengannur - Ettumanoor – Muvattupuzha – SH1 Chengannur Ettumanoor Muvattupuzha stretch of SH-1, MC (Main Central) Road, one of

the most important and oldest roads in Kerala, passing through Thiruvalla,

Changanasserry, Kottayam, Ettumannor, Kuravilangad, Kuttathukulam.

Total length covered is 88 kms.

Road portion from Thiruvananthapuram (Venjaramoodu) to Chengannur was taken up

under Phase I. Bypass at Thiruvalla also forms part of this stretch. The road passes through

the plantation areas and provides access to the tourist centres Kumarakom and

Thekkady.13 bridges will be constructed in this stretch.

The improvement for this road portion is proposed in three construction packages,

Chengannor- Ettumannor(41 km), Ettumanoor-Muvattupuzha (47km) and Thiruvalla

Bypass (2.4km). Reconstruction of three Major Bridges and Nine Minor Bridges are

included in this stretch.

1.2.0.5 Punaloor - Ponkunnam – Thodupuzha – SH 8 Punaloor Ponkunnam Thodupuzha stretch of SH 8 is included in this package.

Total road length is 132 kms.

Major areas covered are Punaloor, Pathanapuram, Manimala, Pala and Thodupuzha.

Five Bridges will be constructed in this stretch. The road passes through Kollam-

Pathanamthitta, Kottayam and Idukki districts. The portion from Punalur-Ponkunnam is

proposed under PPP (modified annuity) arrangement. The bidding documents are

prepared through the Transaction Advisor and for pre-qualification of bidders is in

progress.

1.2.0.6 Perumbilavu - Pattambi – Perinthalmanna – SH 39 Perumbilavu- Pattambi-Perinthalmanna Road Link of SH 39 is included in the package

(Starts at Kuttinad Jn). The growth centre connected is Pattambi town

Length: 41 kms. The road passes through Thrissur, Palakkad and Malappuram Districts.

Page 8: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 8 

The details of approval are as under:  Project appraisal - April 2013

Loan agreement signed - 19 June 2013

Loan Effectiveness date - Sept 6, 2013

Project cost approved by World Bank - US$445 ml

World Bank (IBRD) Loan Assistance - US$216 ml

Project implementation period - 30th Oct 2013 to Dec 31, 2018

Expected closing date (Loan) - April 30, 2019

Fiscal Year FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 FY 2019

Allocation Annual 22 43 45 54 32 20 Cumulative 22 65 110 164 196 216

1.2.0.7 The Finance plus agenda of KSTP – II 1. Upgrading Punalur – Ponkunnam Road under PPP (Annuity)

2. Development of Model Safe Corridor Kazhakuttam – Adoor Section (80 km)

3. Development of Oxbow land (left out lands)

1.3 Overall Implementation:

Project Staffing: KSTP is managed by a Project Director, in the Rank of a senior level Chief

Engineer assisted by one Chief Engineer, a Superintending Engineer and other engineers

and officers. The Technical Wing headed by the Chief Engineer is responsible for activities

related to engineering, environment, social and contract management. Further, the legal

contract management cell is headed by a legal professional. KSTP has qualified and

experienced Social and Environmental Experts and a Project Management Advisor. The

Finance Wing headed by a Finance Controller (deputed from the Secretariat) has a

qualified Finance Manager with support staff. On the field, the KSTP has Two

Superintending Engineers, Five Divisions located at Kottarakkara, Muvattupuzha,

Kuttippuram, Kannur, Ponkunnam each headed by an Executive Engineer to monitor

project progress.

Project co-ordination: Govt. of Kerala has established two committees to monitor,

coordinate, and expedite project activities. The Project Steering Committee chaired by

the Chief Secretary, has its main functions to review and approval of recommendations

regarding acceptance of tenders and taking the final decisions on all matters concerning

procurement and monitoring of project activities. The members of the committee are

Additional Chief Secretary (Finance), Secretaries to Government, PWD, Law Department,

Page 9: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 9 

Revenue, Chief Engineer, R&B, Project Director, KSTP, Chief Engineer (Projects) KSTP. There

is an Evaluation Committee headed by the PWD Secretary and comprising the Project

Director, KSTP and Chief Engineer (Projects), to make recommendations on any issues on

procurement as may require approval of the Steering Committee.

1.4 Project Components

1.4.0.1 Road Upgrading Works:

This component will include upgrading 363 kms of strategically important State Highways

to complete network connectivity in the state with the objective of reducing travel time

between key socio-economic centers.

1.4.0.2 Road Safety Management:

This component will support the strengthening of the road safety management systems in

Kerala with the objective of arresting the increase of crash fatalities in the state. This

component will finance various initiatives building on the work already undertaken during

the first project including a safe corridor demonstration project, implementation of local

level programs utilizing the challenge fund and advisory support for road safety activities.

The road section improved under KSTP-I from Kazhakuttom - Venjaramoodu-Adoor is

proposed to be developed as Safe Corridor Demonstration Project (80 km)

1.4.0.3 Institutional Strengthening The objective of this component is to improve the sustainability of Kerala’s state road

network with respect to its functional adequacy, financial viability and capacity of key

state road sector institutions to deliver road infrastructure and services that are responsive

to road user needs. The major initiatives include Modernization of Road Sector. The

development and Management of a Strategic Road Network is proposed under the

Road Sector Modernization Program.

2.1 Project Description 2.1.0.1 Road Upgradation Under Item Rate Contract

This component will include upgrading of 240 km of State Highways through FIDIC based

input contracts and conventional item rate contracts as noted below.

1. Pilathara - Pappinissery Road – 20.90 km

2. Kasaragod – Kanhangad Road – 27.76 km

3. Thalassery – Valavupara Road

Page 10: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 10 

(Rearranged as 3A & 3B – 53.10 km

4. Ponkunnam – Thodupuzha Road – 50.30 km

5. Chenganur – Ettumanoor Road – 41.00 km

6. Ettumanoor – Muvattupuzha Road – 47.00 km

7. Perimbilavu – Pattambi- Perinthalmanna Road - 41.00 km

2.1.0.2 Road upgradation under PPP (Modified Annuity) mode Punalur - Ponkunnam stretch (82 km) of Punalur – Thodupuzha Road

2.2 Sub Component A1 (US$322 mn)

Consists of the following civil contracts:

SI. No.

CONTRACT PACKAGE NAME OF WORK LENGTH (KM)

1. KSTP-II/UG-1 Kasargod – Kanhangad 27.78

2. KSTP-II/UG-2 Pilathara – Pappinisery 20.90

3. KSTP-II/UG-3A Thalassery – Kalarode 28.80

4. KSTP-II/UG-3B Kalarode - Valavupara 25.20

5. KSTP-II/UG-4 Chengannoor - Ettumannoor 45.40

6. KSTP-II/UG-5 Ettumannoor- Muvattupuzha 40.96

7. KSTP-II/UG-4A Thiruvalla Bypass along Chengannoor - Ettumannoor

2.3

8. KSTP-II/UG-6 Ponkunnam - Thodupuzha 50

9. KSTP-II/UG-7 Perumbilavu - Perinthalmanna 41

2.3 Supervision Consultancy

Under this component, 2 supervision consultancies CSC1 and CSC 2, Independent

engineering services, and Transaction Advisory Service for PPP are included. Contract

Agreement for Consultancy for CSC 1 for 190 Km of upgradation road has been executed

with M/s Egis International in JV with Egis India Consulting Engineers Pvt. Ltd on 28.02.2013

and mobilized and in place. Egis has established rented office for Team Leader at

Thiruvananthapuram near to Client’s Office and started functioning from April 2013. Also

RE offices at Kanhangad in Kasargod District for Package - 1, Pazhyangadi in Kannur

District for package – II and at Uliyil near Mattannur in Kannur District for package – III,

Pallam in Kottayam for Package IV, for Package V at Koothattukulam.

M/s MSV International USA is the selected consultant for Construction Supervision for the

Ponkunnam – Thodupuzha stretch (50 km) CSC-2. They have established their Resident

Page 11: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 11 

Engineer cum Team Leader’s office at Ponkunnam. The length of road covered is 50 km

and the assignment commenced on 15 May 2014.

2.4 Sub Component A2 (US$ 91 mn) DPR for this sub component (Punalur – Ponkunnam – 82 Km under PPP) completed and

schedule prepared by the consultants. M/s L&T Ramboll, Chennai in association with

M/s Fortress has been selected for the Transaction Advisory Services and activities in

progress. The Investor Meet was held on March 2015 at Kochi. The bidding process for

pre-qualifying bidders is in progress. There was only one qualified bidder and hence re-

bid has been invited after obtaining no objection from Bank.

2.5 Component B – Road Safety Management (US$ 22 mn) The baseline survey for the proposed safe demonstration corridor has been completed by

‘NATPAC’ and report shared with Bank. M/s VicRoads, Australia has been selected as

consultant for Road Safety Capacity Building and program management and activities in

progress. The design activities on the Safe Corridor Demonstration Project (SCDP) are

completed and works tendered and awarded.

2.6 Component C – Institutional Strengthening (US$ 10 mn) 2.6.0.1 Consultancy Services

Procurement for the following Consultancy services was initiated. Some are completed

and others are at different stages of progress

1. Consultancy for Road User Perception Survey has been completed for 363 Km of

Project Roads through M/s Sherwood Consultants and report shared with Bank.

2. Consultancy for Prioritization and DPR Preparation for 1000 Km of Improvement of

State roads was entrusted with M/s Egis India Consulting Engineers Pvt. Ltd and final

report submitted. DPR for 439 km roads has been completed. The preliminary

project report for 1106 km was submitted to Government for posing for External

Financial Assistance.

3. Consultancy for Strategic Option Study (SOS) for 8570 Km newly declared MDR was

completed by M/s CDM Smith Associates Pvt. Ltd. Study report has been handed

over to PWD and further action to improve these roads will be taken by them using

their own funds.

4. Consultancy service for Developing Multi Model Integrated Transport Hub at 3

cities, Trivandrum, Kozhikode and Kochi was completed and report forwarded to

Page 12: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 12 

Government. This report was also shared with NATPAC for consideration while

preparing Comprehensive City Development Projects.

5. The EoIs for the Packages II, III and IV in SRN have been evaluated and shortlisted.

The RFP has been sent to the consultants and pre-bid conference was held on

28.03.2016. The technical bids were received. One bid was received for Package

II and one bid was qualified for Package IV. The Steering Committee rejected

these proposals and decided to rebid. For Package III, the Technical Proposal of

the three consultants were approved for Financial proposal opening.

6. The assignment for Integrated Information Management System Development is

being entrusted to NIC.

7. The Project Management Software has been installed and training given to CSC

and KSTP Engineers. The PMS is operationalized.

8. The assignment for “Community Participatory Road Safety and Asset Management

was proposed for re-bidding and held up due to court order. The Bank has issued

no objection for rebidding. The Hon’ble High Court of Kerala has up held the

decision of the Steering Committee and the Steering Committee now decided to

re-bid for the assignment. The ToR has been revised by including the TO and SO.

The final clearance for publishing the EoI in UNDB is awaited.

2.7 Project Cost and Disbursement

Sl No Claim Date

EXPENDITURE in Lakh

AMOUNT CLAIMED in Lakh

DISBURSED BALANCE FUNDS AVAILABLE FOR CLAIM (MUSD) USD in

millions

TOTAL TOTAL TOTAL TOTAL

216.00

Front end fee 0.54 215.46

1 Retroactive 15.06.12 to 15.06.13

1,863.95 1,043.00

1.69 213.77

2 1st Quarter 213.77

3 2nd Quarter 01.07.13 to 30.9.13

1,355.79 764.00

1.23 212.54

4 3rd quarter 01.10.13 to 31.12.13

1,906.01 1,071.00

1.71 210.82

5 4th quarter

01.01.14 to 20.03.14

2,696.00 1,510.00

2.50 208.32

21.03.14 to 31.03.14

53.79 30.00

0.05 208.27

6 1st Quarter 2014-15

01.04.14 to 18.06.14

1,826.41 1,023.00

1.70 206.57

19.06.14 to 30.06.14

14.69 8.23

0.01 206.56

7 2nd Quarter 01.07.14 to 30.09.14

1,405.61 787.00

1.27 205.29

8 3rd Quarter 30.09. 14 to 31.12.14 3,790.21 2,124.00

3.44 201.85

9. 4th Quarter 01.01.2015 to 3,706.35 2,076.00 3.32 201.85

Page 13: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 13 

28.02.2015

10. 4th Quarter 01.03.2015 to 31.03.2015

11. 1st Quarter 2015-16

01.04.2015 to 06.06.2015 and 30.06.2015

3,704.89 2,075.00 3.32 195.21

3534.13 1991.00 3.13 192.08 154.40 86.00 0.14

12 2nd Quarter 2015-16 30.09.2015 3527.06 1977.00 3.04 180.38

13. 3rd Quarter 01.10.2015 to 31.12.2015 10338.17 5790.00 8.51 180.90

14. 4th Quarter 01.01.2016 to 13.03.2016 6413.18 3591.00 5.38 125.00

15. 4th Quarter 14.03.2016 to 31.03.2016 2861.91 1603.00 2.41 172.50

16. 1st Quarter IInd Quarter

01.04.2016 to 10.06.2016 2037.40 1141.00 - 172.50

17. -do- 11.06.2016 to 22.06.2016 2957 1656.00 2.40 170.90

Total 47.55 168.45

Progressive Expenditure and amount Reimbursed – Status as on August 2016

Year Cumulative Expenditure (INR Crores)

Progressive Amount Reimbursed (INR Crores)

2013-14 78.75 44.42 2014-15 223.24 125.40 2015-16 491.53 275.51 2016-17 589.34 303.25 2017-18 2018-19

Estimated Actual loan allocation and disbursement received (Bank’s Financial Year (January to December) (US$ million)

0

100

200

300

400

500

600

700

1 2 3 4

INR

CRO

R

E

YEAR

Cumulative Expenditure (INR Crores)

Progressive Amount Reimbursed (INR Crores)

Page 14: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 14 

Fiscal Year FY 2014

(Jan-Dec) FY 2015

(Jan-Dec) FY 2016

(Jan-Dec) FY 2017

(Jan-Dec) FY 2018

(Jan-Dec) FY 2019

(Jan-Dec) Allocation Annual 22 43 45 54 32 20 Cumulative 22 65 110 164 196 216 Disbursement Received so far 14.15 21.46 11.93 Cumulative

14.15 35.61 47.55

3.0 Executive Summary 3.1 Upgradation Works The work for Packages 1, 2, 3A & 3B, 4, 4A, 5 and 6 are in progress. The work in original

Package 3 was terminated due to poor performance of the contractor, and arranged as

3A and 3B. The work for Package 8 is under PPP (Hybrid Annuity) and bidding is to

prequalify contractors is in progress. The due date of receipt of application is 24.10.2016.

The work for Package 8 is not taken up as upgradation, due to non availability of land.

This is being taken up as Heavy Maintenance within the available land (surface

strengthening).

363 Km of upgradation civil works are divided into 9 Contract packages:

SI. No.

CONTRACT PACKAGE NAME OF WORK CONTRACTOR

1. KSTP-II/UG-1 Kasargod – Kanhangad M/s RDS Projects, Kochi

2. KSTP-II/UG-2 Pilathara – Pappinisery M/s RDS Projects, Kochi

3. KSTP-II/UG-3A Thalassery – Kalarode M/s Dinesh Chandra R. Agrwal

4. KSTP-II/UG-3B Kalarode – Valavupara M/s EKK Infrastructure Pvt. Ltd.,

4. KSTP-II/UG-4 Chengannoor - Ettumannoor M/s Delma - Sreedhanya JV

5. KSTP-II/UG-5 Ettumannoor- Muvattupuzha M/s NAPC Ltd, Chennai

6. KSTP-II/UG-4A Thiruvalla Bypass along (Chengannoor – Ettumannoor) M/s EKK & Co, Kochi.

7. KSTP-II/UG-6 Ponkunnam - Thodupuzha M/s GHV – EKK JV

8. KSTP-II/UG-7 Perumbilavu – Perinthalmanna (EPC) LA initiated and proposed as strengthening of existing road surface

9 KSTP-II/UG-8 Punalur – Ponkunnam (PPP) Bidding to quality bidders is in progress.

The works are being executed under FIDIC (5th edition) Conditions of Contract. The work

involves improvement of State Highways including geometrical improvements and

realignments to standard 2 lane of 7 m carriageway and 1.5 m paved shoulders. The

Construction Works include:

Page 15: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 15 

Widening the existing pavement where it is less than design width;

Scarification, clearance, earthworks,

Granular sub-base, wet mix macadam base course, bituminous mix surfacing,

Construction of overlays to the existing pavement, inclusive of regarding to a designed vertical profile;

Geometrical realignments at specific locations;

Construction of paved shoulders;

Construction and maintenance of diversion roads

Construction of lined and unlined longitudinal drains, covered drains and footpaths in urban areas;

New culverts, new bridges and rehabilitation of existing bridges/culverts and protective works

Provision of road signs and markings;

Provision of traffic safety features - road furniture and other road safety appurtenances,

Routine maintenance and maintenance during Defects Rectification Period.

Environmental protection measures and Social enhancement works/ landscaping works etc.

3.2 Summary of Progress (works) The following tables present the summary of progress in each contract package during the month under report (August 2016).

Contract packages Contract value (Rs. Crore)

Achieved cumulative percentage upto end

August 2016

Balance period (months)

KSTP/PMT/UG-I 1,33,05 55.80% -

KSTP/PMT/UG-II 118.20 50.78% -

KSTP/PMT/UG-IIIA 156.59 - 22

KSTP/PMT/UG-IIIB 209.58 - 22

KSTP/PMT/UG-V 171.49 42% 5

KSTP/PMT/

UG-IVA 31.80 52% 1

KSTP/PMT/UG-VI 227.13 101.05% 5

KSTP/PMT/UG-IV 293.58 43.90% 15

Page 16: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 16 

3.2.0.1 Details of Supervision Consultancy Assignments:

Name of consultant

Contract signed

Contract Period

Commencement Date

Contract Amount (Rs.) Work Package

CSC-1 – M/s Egis International in JV with M/s Egis India Pvt. Ltd.

28.02.2013 42 months 04.04.2013 18,36,04,600

I, II, III, IV, IVA & V

(190 km)

CSC-2 – M/s MSV International USA 14.05.2014 30 months 14.05.2014 4,41,88200

VI (50 km)

3.3 General Issues: The progress is not as per programme. The major factors that hindered the progress of

works were:

1. Delay in obtaining statutory clearances for erection of plants and crushers from the

State Pollution Control Board, Mining and Geology Department and local bodies.

2. Unprecedented unseasonal rains affected adversely works in all the contract

Packages in the initial stages

3. Resistance in identifying, erecting and operating crushers and quarry from the

local people.

4. Poor cash flow problems with the contractors at the initial stages

5. Shortage of machinery, labour force in most of the contracts.

6. Frequent changes made in key personnel in some of the contracts by the

contractor

7. Migrant labours working in all packages and labourers not available during festival

season for long duration.

8. Lack of planning and managerial issues in contracts I, II & V

9. Work Contract-III terminated. Balance works procured under two contract

(3A & 3B)

10. Delay in getting Environmental Clearance from Government Agency for

excavation and conveyance of earth from borrow area.

All these issues are now sorted out and the works are in progress now. The contractors

were instructed to speed up the works to show better results. Contract Package-III

terminated due to poor performance of the contractor and rearranged as IIIA and IIIB

and work in progress.

Page 17: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 17 

Scope of Works Viaduct – 1

Major Bridge – 2

Minor Bridge _ 2

Widening Bridge – 2

New culverts _ 16

Widening Slab culverts – 16

Reconstruction _ 9

Foot path _ 6.7 Km

Drain – 22.20 Km

Solar Lights

THE FOLLOWING SECTIONS DESCRIBE CIVIL WORKS CONTRACT PACKAGES IN DETAIL:

4.1 Current Status of Works 4.2 Contract Package I

Upgradation of Road from Kasargod to Kanhangad of SH 57  

4.3 Contract Details Letter of Acceptance Date

:: 06.03.2013

Agreement Date :: 01.04.2013

Name of Contractor :: M/s RDS Projects Ltd, Kochi

Contract Price :: Rs.133,05,79,485/-

Notice to Commence :: 24.04.2013

Total Length :: 27.78 Km

Contract Period :: 24 months

Completion Date :: 23-04-2015 extended to 30.06.2016

Defect Liability Period :: 365 days

1st Milestone :: Km. 0+000 – Km. 10+000

2nd Milestone :: Km. 0+000 – Km. 20+000 - 23 Oct 2014 revised to 23 Feb 2016

3rd Milestone Km. 0+000 – Km. 27+780 - 26th April 2015 and revised to 31.03.2017

The contractor has been given a final chance to complete the works by end March 2017

Page 18: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 18 

4.4 Progress of Works up to month (July 2016)

4.4.0.1 Structure - progress during the current month Viaduct at Km.3+392 –All major Structure works and bituminous wearing coat over deck

slab completed. The Miscellaneous works including slip road, crash barrier on

approaches are yet to be completed and opened to traffic.

Chithari Bridge at Km.18+400 – Deck Slab Completed. Protection works & safety

installations works are in progress and opened to traffic.

MS- I Box Culverts – All culverts are completed out of 16nos – Box Culvert at Km.1+076,

Km.1+750, Km.1+974, Km. 2+215, Km. 2+454, Km. 2+704, Km. 4+970, Km. 5+500, Km. 5+737,

Km. 6+630, Km. 8+894, Km. 11+620 and Km.11+820 have been substantially completed.

Pipe Culvert 01 no. – Km.4+320 is completed.

Slab Culverts 05 nos. – Km. 7+015, Km. 7+463, Km. 8+093, Km. 8+679 and 9+921 are

completed.

MS- II Box Culverts – Km. 13+830, Km.15+490, Km.16+427, km.17+816, km.18+011,

km.19+364 and km.20+365 Completed. km.21+065 crash barrier wok balance.

MS- III Box Culverts – 03 no’s culverts are in progress (km 27+085 & km 27+675 Deck Slab

completed), 5 no’s yet to be started.

Box cell Minor Bridges

Km. 2+600 – Slab completed at BHS.

Km. 6+510 – Slab completed at LHS and RHS retained.

On 04th march 2016, the Engineer has issued notice to correct under clause 15.1 of GCC

to the Contractor to make good the delays by 15th March 2016. Further Engineer letter

dated 10th March 2016, the date of notice to correct and make good the failure is revised

to 31st March 2016

A summary of progress for major items is as follows:

Milestone

I (Km. 1+000 to Km.

2+800 and Km. 3+800 to Km.

12+000)

II (Km. 12+000 to Km.

22+000)

III (Km. 0+000 to Km.

1+000, Km. 2+800 to Km. 3+800 and Km. 22+000

to Km. 27+780)

Length in km 10 20 27.78

Length handed over to contractor in km 10 20 27.78

Unencumbered land available to the contractor in km

10 20 27.78

FW HW FW HW FW HW

Page 19: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 19 

Milestone

I (Km. 1+000 to Km.

2+800 and Km. 3+800 to Km.

12+000)

II (Km. 12+000 to Km.

22+000)

III (Km. 0+000 to Km.

1+000, Km. 2+800 to Km. 3+800 and Km. 22+000

to Km. 27+780)

GSB completed in km 10.000 - 5.583 1.646 2.490 0.690

WMM completed in km 10.000 - 5.187 2.048 2.470 0.620

DBM completed in km 10.000 - 5.187 2.048 2.000 1.080

BC completed in km 10.000 - 4.710 0.430 2.000 -

CD completed in Nos. 22 07

4.5 Schedule of Culverts and Drainage works

4.6 Progress Considering the Contract price up to this Month (August)

Up to previous Month This Month Cumulative to end of this Month

Target Achieved Target Achieved Target Achieved 55.57% 54.63% 2.44% 1.170% 58.620% 55.80%

   Nature of work     

Total num

ber 

No. dwgs app

roved

Num

ber completed

  

Num

ber in progress

Num

ber remaining

Total N

umbe

No. dwgs app

roved

Num

ber completed

  

Num

ber in progress

Num

ber remaining

Total num

ber 

No. dwgs app

roved

Num

ber completed

  

Num

ber in progress

Num

ber remaining

Culverts

Widening Slab/Box Culverts            9             9             9            ‐              ‐              ‐                    ‐              ‐              ‐              ‐                 1                1            ‐                 1                   ‐   

Reconstruction Slab/Box            7             7             7            ‐              ‐               7                   7             6             1            ‐                 3                2            ‐                 2                     1 

New Box Culvert/Pipe culvert

           6             6             6            ‐              ‐               1                   1             1               3               ‐              ‐                ‐                       3 

Total culverts          22           22           22            ‐              ‐               8                   8             7             1            ‐                 7                3            ‐                 3                     4 

Bridges/ROB Retained**            2            ‐              ‐              ‐              ‐               2                  ‐              ‐              ‐              ‐                ‐                 ‐              ‐                ‐                     ‐   

Bridges Widening ***            2             2             2            ‐              ‐              ‐                    ‐              ‐              ‐              ‐                ‐                 ‐              ‐                ‐                     ‐   

New Bridges/Viaduct*           ‐              ‐              ‐              ‐              ‐               1                   1             1            ‐              ‐                 1                1             1              ‐                     ‐   

Milestone ‐ I (1 to 2.8Km and 3.80 to 12.0Km )

Milestone ‐ II (12 to 22Km.)Milestone ‐ III 

(0 to 1.0Km, 2.80 to 3.80Km and 22 to 27.78Km.)

Page 20: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 20 

4.7 Physical progress Bar Chart

4.8 S-Curve

104992.95

33785

22457

51841.2

47972.99

9607

7417

10783.014

103450.60

33785

22457.00

51533.00

47362.00

9607.00

7417.00

10723.06

334052

52246.87

94397

63492

79468

26990

14823

14334

0 50000 100000 150000 200000 250000 300000 350000 400000

Excavation (cum)

Embankment (cum)

Subgrade (cum)

GSB (cum)

WMM (cum)

DBM (cum)

BC (cum)

Concreting (cum)

Estimated BOQ Quantity

Cumulative target to end of this Month

Cumulative Achieved to end of this Month

Page 21: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 21 

4.9 Strip map

4.10 Utilities

Shifting of utilities such as water lines, telephone cables and associated accessories are in

progress. Relocation of electric lines/poles and cutting of trees are in progress during this

month. Electrical Poles shifted in Mile Stone I are 344 nos, 366 nos in Mile Stone II & 105 nos

0 100

200

300

400

500

600

700

800

900

1000

1100

1200

1300

1400

1500

1600

1700

1800

1900

2000

2100

2200

2300

2400

2500

2600

2700

2800

2900

3000

3100

3200

3300

3400

3500

3600

3700

3800

3900

4000

4100

4200

4300

4400

4500

4600

4700

4800

4900

5000

5100

5200

5300

Bituminous Concrete ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Dense Bituminous Macadam ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Wet Mix Macadam ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Granular Sub base ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Subgrade ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

EW - Embankment ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Pothole repair & patching

Pothole repair & patchingEW - Embankment ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Subgrade ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Granular Sub base ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Wet Mix Macadam ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Dense Bituminous Macadam ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Bituminous Concrete ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

RIG

HT

SID

EL

EFT

SID

EChainage (Km)

Culverts & Bridges

5300

5500

5600

5700

5800

5900

6000

6100

6200

6300

6400

6500

6600

6700

6800

6900

7000

7100

7200

7300

7400

7500

7600

7700

7800

7900

8000

8100

8200

8300

8400

8500

8600

8700

8800

8900

9000

9100

9200

9300

9400

9500

9600

9700

9800

9900

1000

010

100

1020

010

300

1040

010

500

1060

010

700

Bituminous Concrete ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Dense Bituminous Macadam ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Wet Mix Macadam ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Granular Sub base ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Subgrade ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

EW - Embankment ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Pothole repair & patching

Pothole repair & patchingEW - Embankment ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Subgrade ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Granular Sub base ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Wet Mix Macadam ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Dense Bituminous Macadam ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Bituminous Concrete ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

RIG

HT

SID

E

Culverts & Bridges

Chainage (Km)

LEFT

SID

E

1080

010

900

1100

011

100

1120

011

300

1140

011

500

1160

011

700

1180

010

700

1100

011

300

1150

011

700

1190

012

000

1210

012

200

1230

012

400

1250

012

600

1270

012

800

1290

013

000

1310

013

200

1330

013

400

1350

013

600

1370

013

800

1390

014

000

1410

014

200

1430

014

400

1450

014

600

1470

014

800

1490

015

000

1510

015

200

1530

015

400

1550

015

600

1570

015

800

1590

016

000

1610

0

Bituminous Concrete ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Dense Bituminous Macadam ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Wet Mix Macadam ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Granular Sub base ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Subgrade ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

EW - Embankment ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Pothole repair & patching

Pothole repair & patchingEW - Embankment ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Subgrade ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Granular Sub base ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Wet Mix Macadam ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Dense Bituminous Macadam ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Bituminous Concrete ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

RIG

HT

SID

E

Culverts & Bridges

Chainage (Km)

LEFT

SID

E

Page 22: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 22 

in Mile Stone III. Shifted up to date and 815 poles and some of the accessories are

received by the Contractor. Total 413 numbers of the trees have been cut till date 70 Nos

are balance. Contractor shifted 815 nos. of electric poles and 42 no. of transformer till

date.

4.11 Potential Issues The very poor cash flow of Contractor has seriously hampered the progress of works. No

improvement is observed in the progress of activities during the month also despite the

assurance given by the Contractor to Employer and CSC.

Lack of resources at site which reflected frequent change in planning of works at site,

There were delays in shifting of utilities. However Employer and the Contractors are

coordinating with various Service Providers like KSEB, KWA, BSNL and other service

providers for shifting of utilities and tree cutting along the project.

The Additional Chief Secretary, PWD has instructed complete the Project by 31.03.2017

Instructions are issued to the Contractor for taking stringent measures to enhance the

progress of works. Clause 15.1 Notice to Correct issued on 4.03.2016.

4.12 Payments to the Contractor Mobilization advance, Equipment advance and Interim payment Certificate for works

was paid to the Contractor amounting to Rs. 70.46 crores. Timely payments are released

to the contractor. The Steering Committee held on 28.06.2014 lowered the threshold limit

of minimum IPC amount for Rs. 1.5 crores from Rs. 3.00 crores to facilitate the cash flow of

contractor. There is no pending payment to contractor.

4.13 Implementation of EMP

4.13.0.1 Environment Management at work sites The progress of the work at site is unsatisfactory during the month. Contractor completed

19 km DBM and14km BC so far. Contractor has started another work front from CH 25 to

27km and culvert works and some road works completed, but drain works is pending.

Since the contractor was kept opened the construction fronts for long time without work,

the safety provisions at sites was also deteriorated. The environmental expert visited the

site on 26thth August and observations were communicated to the contractor for taking

Page 23: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 23 

action. The safety of construction site is a primary concern and requires further

improvement.

The drain connection and culvert connection remaining are to be completed. The

overlay works at Chandragiri bridge completed but the unsafe railing height is not

increased. The crash barriers are to be provided on the approaches and side road

connection to be improved. This was pending for a long time.

The junction improvement works at Kasergod town not completed. The culvert

construction at this junction is not started. Foot path and bus bays are also pending.

The drain work under the viaduct portion now completed but cover slab is to be provided

at hill bottom to avoid silting. Land scape and tree planting at this location has to be

started urgently.

The debris and cofferdam from the viaduct and Chithari bridge site is partially removed.

Though the contractor has been directed to take action to remove complete materials

before monsoon, contractor informed that revenue dept is not permitting transport of

materials.. Contractor has started planting trees and so far 240 Nos have been planted. It

is also noticed that the pit was backfilled and no tree guard placed. Direction issued to

the contractor to rectify the same. The protection works in the hill cutting area not fully

completed. Some sliding was occurred during last month and the traffic through the road

was stopped by Dist Collector. The protection works are still continuing .The slow pace of

the work at this location of high cutting side also contributed for the land slide.

The enhancement works in front of the Thrikanad temple in progress, Two light poles

installed at this location are to be shifted backwards to construct the bus bay.

All workers shall wear the required protection as per the job requirements. Safety shoes,

helmets, glosses shall be used where ever required. The statutory clearance obtained for

plants due to expire by January 2017. Contractor has to obtain extension of validity from

PCB before expiry of the above said date.

It is also noticed that no action taken report on the site visit observation of the

environmental expert was submitted by the contractor .The employer directed the

consultants to get the report from the contractors urgently. Action has been taken by the

consultant.

After improvement of the road lot of accidents reported most of the case the reason

pointed out is over speed. The local police have put some barricades to reduce the

speed but it is not in a scientific way. There for speed reduction by providing rumble strips

and warning sign boards, raised pedestrian crossings are urgently to be constructed.

Further the spacing of studs provided now is 18 m at center, this has to be reduced as 5m

Page 24: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 24 

as provided in the contract drawing. Information sign boards of all rivers, tourist places are

to be placed in the completed road stretches.

4.13.0.1 Traffic Management and Road Safety Measure The Contractor has not provided the required safety precautions such as flags, safety

signboards, traffic cones, blinkers and safety tapes at the work site as require Since the

construction works are very slow it also affected the traffic management measures.

Resident engineer has issued warning to improve the safety at sites and if not comply

penalty will be imposed.

Page 25: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 25 

4.14 Photograph

11+810 to 11+822.5 Temple Stepping work (RHS) +392 Viaduct P1-P2 Surface preparation for

Painting in progress

WMM top layer at km 27+160 to 27+625 (RHS) DD checking at km 26+480 to 26+800 (RHS)

Page 26: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 26 

15.1 Contract Package - 2

Upgradation of Road from Pilathara to Pappinissery of SH 67

15.2 Contract Details Letter of Acceptance Date :: 05.03.2013

Agreement Date :: 01.04.2013

Name of Contractor :: M/s RDS Projects Ltd, Kochi

Contract Price :: Rs.118,29,77,833/-

Notice to Commence :: 23.04.2013

Total Length :: 20.90 Km

Contract Period :: 24 months

Completion Date :: 22nd April 2015 extended to 20 June 2016

Defect Liability Period :: 365 days

1st Milestone :: Km. 0+000 – Km. 08+000 - 22nd February 2014 Revised to 30 September 2015

2nd Milestone :: Km. 0+000 – Km. 14+000 - 13 February 2016

3rd Milestone :: Km. 0+000 – Km. 20+900 - 22 April 2015 revised to 31.03.2017

Scope of Works New ROB – 2 Repair of Bridge – 2 New Box culverts _ 9 Widening Slab culverts – 20 Reconstruction _ 8 Drain – 26.04 Km Foot path _ 12.6 Km Solar Lights -

Page 27: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 27 

15.3 Progress of Works 15.3.0.1 Structure – Overall Progress

ROB @KM 7+420 (Thavam):

Railway Department has approved GAD in July-2014.

Test pile casting has been done for ROB @KM7+420 and initial load test on pile is

completed. Routine Pile load test for A2/B and P1/D completed and results are yet

to be submitted.

ROB at Km. 7+420 Piling Work started on 18/12/14, Piling Work 24 No’s out of 24 No’s

completed. Pile cap and abutment / pier up to abutment cap / pier cap bottom

level for A1 (new P3), P1 (new P4), and P4 (new P7) & A2 (new P8) completed.

KSTP has directed CSC to provide design and details of additional three spans

each on A1 and A2 sides of ROB at km7+420. The Confirmatory boring pier

locations of these span have been started by the agency M/s Geo Foundations &

Structures Pvt. Ltd on 29th Feb. 2016 and completed on 13th march 2016. The

reports has been submitted by Geo Foundations & Structures Pvt. Ltd on 08th April

2016.

GFC drawings for additional spans issued to the Contractor on 05thMay 2016.

Contractor mobilized the machineries for piling works during the first week of June

2016 and pile boring works for additional spans. 16 nos of pile (out of total 36 Nos)

casting completed for additional spans and boring for 2 Nos are in progress. The

reinforcement work for P7 & P8 (Old P4 & A2) are in progress

Railway gate shifting works completed during March 2016. The Piling works

complted commenced by railway department (railway span) and pier cap work

for Pappimissery side is in progress. Pile load testing loading is in progress.

ROB @KM 19+950 (Pappinissery):

Test pile casting has been done for ROB @KM19+950 and initial load test on pile

completed.

Piling and Pile Cap works completed.

Abutment / pier cap completed.

Girder and deck slab for A1-P1, P1 to P10 and P13-P22 and P22-A2 completed.

Girder & slab for 20 span completed out of 22 Nos. Girder concrete for P13-P14

completed.

Retaining wall works at A1 & A2 approaches are in progress.

Page 28: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 28 

Ramapuram Bridge @ Km.4+260:

Test piling work started for Ramapuram Bridge @ Km.4+260 on 24th June -2015 and

initial load testing completed on 23.01.2016. Dynamic load test for A1/B completed

on 17.03.2016.

Piling Work 16 No’s out of 16 completed. Pile cap work completed (Out of total 4

Nos, 4 completed). Pier cap / Abutment cap completed. The ground preparation

for superstructure work is in progress.

The status of CD works are stated below:

There are 38 Nos culverts in the project for widening / reconstruction. 22 Nos

completed except apron works. 3 Nos are in progress and 8 Nos are yet to be started.

Due to non- availability of outlet for disposing the water from culvert, the culvert at

km 08+560, 14+070, 15+110, 17+780 and 18+970 are deleted.

Drain cover slab 268 Nos. casting completed during this month.

Overall progress up to August 2016

For previous Month This Month Cumulative to end of this Month

Target Achieved Target Achieved Target Achieved 50.06% 47.93% 1.97% 2.85% 52.03% 50.78%

15.4 Work progress considering the contract price August 2016 A summary of progress for major items is as follows.

Length in km

20.9

Length handed over to contractor in km 20.9

Unencumbered land available to the contractor in km 20.9

Stretch completed in all respects in km -

FW HW

GSB completed in km 12.355 1.690

WMM completed in km 12.280 1.640

DBM completed in km 10.550 3.100

BC completed in km 9.100 0.100

CD completed in Nos. 22 Nos

Page 29: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 29 

15.5 Physical Progress

15.6 S-Curve

59781

12116

16402

30104

37375

6912

4189

8117

5274

58077

10780

10311

29120

31883

5747

3905

5741

5359

158361

42903

93145

42722

57501

12801

10442

21139

4839

180833

13583

93145

42722

57501

19202

10442

21139

5656

0 50000 100000 150000 200000

Excavation (cum)

Embankment (cum)

Subgrade (cum)

GSB (cum)

WMM (cum)

DBM (cum)

BC (cum)

Concreting (cum)

Bored Pile (Lm)

BOQ Quantity

Cumulative target to end of this Month (R5)

Cumulative target at the end of this month (Programme 07.07.2016)

Cumulative Achieved to end of this Month

Page 30: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 30 

15.7 Strip Chart

0 100

200

300

400

500

600

700

800

900

1000

1100

1200

1300

1400

1500

1600

1700

1800

1900

2000

2100

2200

2300

2400

2500

2600

2700

2800

2900

3000

3100

3200

3300

3400

3500

3600

3700

3800

3900

4000

4100

4200

4300

4400

4500

4600

4700

4800

4900

5000

5100

5200

5300

Bituminous Concrete ## 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Dense Bituminous Macadam 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Wet Mix Macadam 2nd 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Wet Mix Macadam 1st 1 1

Granular Sub base 1 1

Subgrade 1 1

EW - Embankment 1 1

EW - EmbankmentSubgradeGranular Sub base ## 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 ##

Wet Mix Macadam 1st ##

Wet Mix Macadam 2nd ## 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Dense Bituminous Macadam ## 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Bituminous Concrete ## 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

RIG

HT

SID

EL

EFT

SID

E

Chainage (Km)

Culverts & Bridges

5400

5500

5600

5700

5800

5900

6000

6100

6200

6300

6400

6500

6600

6700

6800

6900

7000

7100

7200

7300

7400

7500

7600

7700

7800

7900

8000

8100

8200

8300

8400

8500

8600

8700

8800

8900

9000

9100

9200

9300

9400

9500

9600

9700

9800

9900

1000

010

100

1020

010

300

1040

010

500

1060

010

700

Bituminous Concrete ## ## ## ## ## ## ## ## ## ## ## ##

Dense Bituminous Macadam ## ## ## ## ## ## ## ## ## ## ## ## 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Wet Mix Macadam 2nd 1 1 1

Wet Mix Macadam 1st 1 1 1

Granular Sub base 1 1 1

Subgrade 1 1 1

EW - Embankment 1 1 1

EW - EmbankmentSubgradeGranular Sub baseWet Mix Macadam 1stWet Mix Macadam 2ndDense Bituminous Macadam ## ## ## ## ## ## ## ## ## ## ## ## ##

Bituminous Concrete ## ## ## ## ## ## ## ## ##

RIG

HT

SID

E

Culverts & Bridges

Chainage (Km)

LE

FT S

IDE

1080

010

900

1100

011

100

1120

011

300

1140

011

500

1160

011

700

1180

011

900

1200

012

100

1220

012

300

1240

012

500

1260

012

700

1280

012

900

1300

013

100

1320

013

300

1340

013

500

1360

013

700

1380

013

900

1400

014

100

1420

014

300

1440

014

500

1460

014

700

1480

014

900

1500

015

100

1520

015

300

1540

015

500

1560

015

700

1580

015

900

1600

016

100

Bituminous ConcreteDense Bituminous MacadamWet Mix Macadam 2ndWet Mix Macadam 1stGranular Sub baseSubgradeEW - Embankment

EW - EmbankmentSubgradeGranular Sub baseWet Mix Macadam 1stWet Mix Macadam 2ndDense Bituminous MacadamBituminous Concrete

LE

FT S

IDE

RIG

HT

SID

E

Culverts & Bridges

Chainage (Km)

Page 31: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 31 

15.8 Utilities Utilities such as Electrical line, water lines, telephone cables and associated accessories

were remaining to be relocated/ removed / shifted. Entire trees in Milestone –I were cut

and removed from site as on date. Tree cutting work is now in progress between

Km.16+400 and Km.19+660 (Milestone-II and Milestone-III).

Total number of Electric poles and transformers to be shifted from the project corridor is

953 Nos. and 19 Nos. respectively and 616Nos. of Electric poles and 9 Nos. of Transformers

have been relocated till date in between Km.0+00 to Km.16+400 and Km.19+660 to

Km.20+000. Stringing of wire has been completed for 16.27 kilometer length between

Km.0+000 to Km.20+900. There are about 20 Nos are yet to cut within ROW which obstructs

the stringing of electrical line.

Water pipe line shifting works are in progress between km 16+100 to 17+100 and from km

18+670 to km 20+900.

Total number of telephone poles to be relocated along the project corridor is 451Nos.

However the work has not been affected so far since the shifting is being done along with

road work. Shifting of Water pipe line woks are in progress in Milestone-I, Milestone-II &

Milestone-III

15.9 Potential Issues • Lack of experienced staff at site which reflected in planning of works at site, delay in

preparing Mix designs, delay in submission of working cross sections, in preparation of

survey data etc.

• The contractor has established one quarry, crusher and HM Plant for contract I and II.

The aggregate production is not sufficient to meet the requirement of both packages.

• A Court case is prevailing at High court of Kerala for providing smooth access road to

the adjacent land owners Shri. Padamanabhan Nadakkal, Shri. Bhaskaran Nadakkal

and Smt. Vineetha claimed that their access road has been disturbed due the grade

improvement (High Embankment) of the Road between Km.3+280 to Km.3+460 of the

Project road and the case is still pending in the High court of Kerala.

15.10 Payments to the Contractor Mobilization advance and Equipment advance and IPC’s was paid to the Contractor

amounting to Rs. 55.03 crore The Steering Committee held on 28.06.2014 lowered the

threshold limit of minimum IPC amount for Rs. 1.5 crores from Rs. 3.00 crores to facilitate

the cash flow of contractor. There is no pending payment to the contractor.

Page 32: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 32 

15.11 Implementation of EMP

15.11.0.1 Environment Management at Work Sites The activities during the quarter were in a slow pace. Contractor completed 14 km DBM

and 10 km BC. The environmental expert visited the site on 26th August 2016 and

observations were communicated for corrective measures taken .Complaints from public

on dust emissions as the contractor has kept the work fronts for long periods. Contractor

has started tree planting works where ever possible and so far 260 trees have been

planted. Further avenue plantation is very minimal as the ROW is fully utilized for road

construction. The balance quantities can be planted and this is continuing. The

environmental enhancement measures such as construction of parking bus bays noise

barriers oxbow land development have been taken up. The side of the deck has to be

provided safety hand rails for the free movement of workers on deck. Since the bridge

work site is in town area pedestrian safety was not sufficient and direction issued to the

contractor to provide maximum safety during construction time.

The junction improvement works at Pappinassery was not started. Some mangrove and

trees at this location are to be affecting the construction and hence to be removed.

Contractor has prepared a plan showing the affected trees and mangroves and these

are marked at site and permission has to be obtained from the forest departments.

Contractor has taken action.This matter was already addressed to the employer for

obtaining the required permissions. Direction was also given to revalidate the consents

due to expire by end January.

15.11.0.2 Traffic Management and Road Safety Measures The contractor is required to provide safety precautions such as barricading, flags, safety

signboards and traffic cones at all work zones to ensure safety for all road users. Personal

safety equipment such as jackets, safety shoes, face shields and hand gloves are to be

provided to all workers as necessary. Instructions were given to provide adequate safety

sign boards and fencing all along the active work sites. The safety at Thavam ROB site is to

be increased.

Page 33: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 33 

15.12 Photographs

Kerb laying in progress at km 0+000 Junction WMM Top laying (km 16+000 to 16+140 RHS)

Pier cap work for P7 in progress at ROB 7+420 Bridge Works in progress at km 4+260 16.1 KSTP/PMT/UG – III A

(Thalassery – Kalaroad) 28.80 km

Page 34: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 34 

Scope of Work

Name of Contractor :: M/s Dinesh Chandra R. Agrwal

Date of Agreement :: 20.05.2016 Length :: 28.80 km Milestone – I :: Milestone – II :: Milestone – III ::

16.2 Executive Summary Commencement Date: 27th June 2016. Maintenance work of the project road is in

progress. Already 410m2 of pothole filling was done. For constructing balance portion of

half-done culverts, forming of approaches to divert traffic is going on at km 06+140

16.3 Pre-Construction Activities

16.3.0.1 Utilities Joint inspection conducted along with KSTP, KSEB, Kerala Water Authority, BSNL and other

private cable operators and list finalized.

Page 35: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 35 

16.4 Moblisation of Resources

16.4.0.1 Plant & Machinery Contractor has erected concrete Batching plant and calibration done. The plant is ready

for operation. Base Camp is situated at Valliyavellicham, which is 6km away from km

16+000 (Kuthuparamba) of the project road.160DPH WMM plant is ordered by the

Contractor and is expected by the end of September 2016.

16.5 Human resources Contractor has mobilized some supervising staff, skilled workers and unskilled workers.

16.6 Work Progress in detail for this month Maintenance work of the project road is in progress. Already 410m2 of pothole filling was

done. For constructing balance portion of half-done culverts, forming of approaches to

divert traffic is going on at km 06+140

16.7 Work Programme Contractor submitted work programme. Team Leader vide letter No: ET/1A/PJ/1858 dated

25.08.2016 has directed to submit certain additional details and the same is under

preparation by the Contractor.

16.8 Quality Control Field laboratory building construction is almost completed and Contractor procured

required equipment’s for quality control tests and the installation is in progress.

16.9 Source and Material Approval Source approval of steel given for Shyam steel industries ltd and JSW steel ltd.

Source approval of Admixture given for BASF India ltd.

Source approval of Coarse aggregates and Fine aggregates given for Geo sand crusher,KSIDC,Koothuparamba.

16.10 Mix Design Mix Design for M-25 grade concrete approved which is required for culvert works. The Mix

design for M-20, M-30, M-35, M-40 and M-45 are expected to be obtained from Govt.

Engineering College, Calicut by 15.09.2016.

Page 36: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 36 

16.11 Implementation of EMP - Contract Package - IIIA

16.11.0.1 General The letter of acceptance for contract 3A issued and agreement was also signed.

Even though the agreement was signed on 24th January2016,the mobilization is in a slow

pace.Errection of batching plant completed and the construction of laboratory in

progress. The contractor identified 5acres of land in Vellivelicham near Kuthuparamba

town about 5km from project road. The environmental expertof CSC visited the site on

27thAugust2016 and directed the contractor to obtain the required consents from PCB

and local panchayat. Contractor also informed that aggregate required for the project is

proposed to be purchased from local crusher. Contractor was also directed to submit the

management plan for approval before start any work. No Environmental and Safety

Officers are yet to be appointed.

Page 37: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 37 

17.1 KSTP/PMT/UG – III- B (Kalaroad – Valavupara) 25.20 km

1. Contract value in crores - Rs. 209.69 crores

2. Name of Contractor - M/s EKK Infrastructure Ltd.,

3. Date of Agreement - 29.04.2016

4. Time of Completion - 24 months

5. Length - 25.20 km

6. Milestone – I -

7. Milestone – II -

8. Milestone – III -

17.2 Executive Summary The contract of Package IIIB (Kalaroad – Valavupara) has been awarded toM/s GHV-EKK

(JV) on 29th April 2016.

Notice to Proceed has been issued to the contractor vide letter No. ET/1A/PJ/1842 dt 16th

August 2016 and thereby instructed to commence the work with effect from 18th August

2016.

A tentative construction programme up to December 2016 was submitted by Contractor

on 09th August 2016 vide letter no. GHV-EKK(JV)/KLR-VLPA/16/CL/048 considering site

handing over date as base date. CSC has reviewed the programme and asked to submit

a detailed programme with resource planning, S-Curve, monthly quantity distribution etc

vide Team Leader letter No. ET/1A/PJ/1859 dated 25th August 2016.

Summary of progress achieved during the month of August 2016 is as follows.

Page 38: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 38 

Iritty Bridge @ Km.42+198:- Contractor has started piling works at Iritty Bridge at Km

42 + 195. One balance pile at A1 side was casted. The boring in A2 side is in

progress.

Maintenance Works:-Maintenance work and drainage work is being executed in

various locations of the road.

17.3 Pre-Construction Activities

17.3.0.1 Mobilization of resources Contractor has started construction of Permanent base camp, casting yard, Concrete

Batching Plant, WMM Plant, Field laboratory, Store, Staff Quarters, Labour Camp,

Workshop, etc. at Kallyad on Poovam- Kallyad Road, 10 km away from Iritty bridge on the

Project road.

17.4 Human Resources Contractor has mobilized some technical staff, non-technical staff, skilled workers &

unskilled workers at site.

17.5 Quality Control/ Quality Assurance A Temporary Site laboratory for aggregate testing and concrete mix designs has been

established at 43/340 near the staff quarters. Construction of permanent field laboratory is

under speedy progress.

17.6 Source and Material Approvals Source approval for Cement (India Cements & Ramco Cements) Reinforcement steel

(VIZAG, SAIL, Jindal & Shyam Steel), Admixture (CHRYSCO), NP4 Hume pipe (Premier spun

pipe) and GI and PVC pipes (Kamal Pipes) has been given to the Contractor.

17.6.0.1 Implementation of EMP- Contract package IIIB: The agreement for contract IIIB signed on 30thApril .

No major activities in the Quarter. Contractor identified a site for establishing the base

camp and other facilities at Padiyur in Kalliad village near Irrity town (7Km.).contractor

was directed to submit the reporting formats for approval of the camp and management

plans and this was approved The CSC environmental expert visited the site on 27th August

2016 and comments attached as annexure.

Contractor has started mobilization at camp site. Construction of offices and other

facilities are in progress. The piling works of the Irrity Bridge has been started. Contractor

has been asked to obtain the consents from PCH and local panchayats.

Page 39: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 39 

18.1 Contract Package IVA Construction of Thiruvalla Bypass along Chengannoor - Ettumannoor Road (SH-1) from chainage 7+390 to 9+400

18.2 Contract Details

Letter of Acceptance Date :: 29.10.2013

Agreement Date :: 29.11.2013

Name of Contractor :: M/s EKK & Co, Kochi

Contract Price :: Rs. 31,80,45,071/-

Notice to Commence :: 19.12.2013

Total Length :: 2.3 Km

Contract Period :: 24 months

Completion Date :: 06 August 2014 revised to September 6, 2016

Defect Liability Period :: 365 days

Scope of Works Major Bridges - Nil

Minor Bridge - 1 no.

Flyovers - 1 no.

Culverts - 8 nos.

Pipe Culverts - 2 nos.

Solar lights - 1380 nos.

Page 40: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 40 

18.3 Work Progress

18.3.0.1 Summary of the progress up to the month Major works executed during the month are listed below.

Gravity wall at LHS of Ch : 1+126.4 - 1+150 km completed.

Gravity wall at LHS 1+120 Jn (0+000-0+006.15) RHS completed.

3 girders at P3-P4 span casted & casting of diaphragm of P2-P3 span is completed.

Casting of diaphragm of P3-P4 span in progress.

Concreting of A2 retaining wall of flyover completed.

16 nos. of drain top slab casted.

7 nos. of crash barrier along with friction slab casted.

Stressing of 3 girders of span P2-P3 & 1 girder of span P3-P4 completed

18.3.0.2 Progress achieved 4 box culverts completed.

2 Nos. Of 1200 mm dia pipe culvert completed

All 24 piles of minor bridge completed

All 42 piles of fly over at 1+350 completed

6 nos. Pile cap at flyover completed

1 no.of pilecap at minor bridge (0+380) completed.

All 6 nos of pier at flyover completed

4 nos of pier cap at flyover completed

2 nos of abutments at flyover completed.

1 no.of abutment at minor bridge completed.

184 m of concrete drain completed

Precasting of 304 number of RE wall panels completed.

Precasting of 110 nos of RCC crash barrier cum friction slab completed.

18 no.s of girder of Flyover at 1+350 completed

3 no.s of deck slab of flyover at 1+350 completed.

Embankent construction upto 15th layer completed for ch : 0+089 to 0+350 & 0+430 to

0+520 km

Embankment construction upto 4th layer completed for ch : 2+100 – 2+300 km.

Progress up to end of August 2016 is as follows:

Up to previous month This month Cumulative to end of this month

Target Achieved Target Achieved Target Achieved 78.10% 50.64% 5.03% 1.26% 83.1% 51.90%

Page 41: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 41 

18.4 Physical Progress

18.5 S-Curve

22532

123022

0

3100

0

0

0

7855

227000

9737

72701

0

3062

0

0

0

5045

227229

21960

148258

20109

8750

9275

1815

1452

6989

232000

0 50000 100000 150000 200000 250000

Excavation (cum)

Embankment (cum)

Subgrade (cum)

GSB (cum)

WMM (cum)

DBM (cum)

BC (cum)

Concreting (cum)

PVD

BOQ Quantity

Cumulative Achieved to end of this month

Cumulative target to end of this month

Page 42: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 42 

18.6 Potential Issues The following issues are very critical which may have adverse impact on the timely completion of the Project.

• Handover of unencumbered land at Km 1+450 to 1+750 pending and action taken

to acquire.

• Slow Progress of work due to Court order for 9 Months initially

18.7 Schedule of culverts and drainage works

18.8 Payment

Up to IPC-15 has been paid to the contractor Rs. 15.71 crore

18.9 Implementation of EMP

18.9.0.1 Environment Management at Work Sites The construction activities for Contract IV-A is in progress. Pile cap completed for A1. The

work was stopped now due to rain. The PVD for the embankment for first stage are

completed and the second stage embankments in progress. The proposal for viaduct is

under review. The safety provision at flyover is satisfactory .Form work for the third span of

the flyover is in progress and casting girder in progress.

Contractor was also directed to take measures to divert rain water from the campsite

and excavation trench for RE wall approach. The health checkup for the workers

arranged, but report awaited. Contractor was asked to submit the action taken report on

the site visit observation of the environmental expert. Contractor has submitted

application for renewing the consents from PCB.

Nature of work

Ori

gina

l num

ber

No.

dw

gs a

ppro

ved

Num

ber

com

plet

ed

Num

ber

in p

rogr

ess

Num

ber

rem

aini

ng

Rem

arks

Culverts

Pipe culvert 4 4 2 2

New Box Culvert 8 4 4 4

Total culverts 12 8 6 6

Fly over and Minor bridge 2 2 2Partly

Page 43: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 43 

18.10 Photographs

  

P2­P35th girder concreting (ch:1+301 – 1+340 km)  

P1­P2 deckslab after concreting (ch:1+262 – 1+301 km)  

  

P2­P3 2nd girder concreting (ch:1+301 – 1+340 km)  Staging Work for P2­P3 Span (1+301­1+340km)  

Page 44: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 44 

19.1 Contract Package IV Upgradation of Road from Chengannoor to Ettumannoor of SH-1

19.2 Contract details: Letter of Acceptance :: 21.08.2014

Agreement date :: 15.09.2014

Name of contractor :: M/s Delma-Sreedhanya JV

Contract amount :: Rs. 293,58,17987

Notice to commence :: November 25, 2014

Total length :: 45-80

Contract period :: 36 months

Completion date :: 24.11.2017

Defect liability period :: 365 days

I milestone

:: 10 km upto BC level 18 months from commencement date

II milestone

:: 25 km upto BC level 25 months from commencement date

III milestone

:: 47.80 km upto BC level 36 months from commencement date

Scope of Works (45.40 Km): Construction of Major Bridges – 3

Construction of Minor Bridge – 5

New Box culverts - 9

Widening Slab culverts – 8

Reconstruction of Culverts - 59

Page 45: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 45 

19.3 Pre-Construction Activities:

19.3.1 Utilities Utilities such as water lines, telephone cables and associated accessories, electrical lines

and associated accessories and trees are being removed / shifted.

Removal of stumps of trees cut by agencies engaged by KSTP is also the responsibility of

the Contractor.

Relocation of Electrical lines and Waterlines are included in the Contract.

3279 lm of 700mm, 5202 lm of 200mm & 10294 lm of 300mm DI pipe laid. 38758 lm of

160mm PVC pipe laid. Work in progress.

Electrical Utility shifted for approximately 25 km. Work in progress.

19.3.1.1 Progress Achieved - Bridges

Construction of bridges at km 0+750 and Km 11+235 have been completed and

opened to traffic

All the spans of bridge at km 39+709 have been cast. Crash barrier also completed.

Piling of Kallissey bridge completed @ 1+558. A1 and A2 abutment and bracket wall

completed. A1P1 1st & 2nd Girder casting and stressing completed. 3rd girder has

been cast. P1P2 1st & IInd Girders casting & stressing completed. 3rd girder casting is in

progress.

Excavation & PCC Completed at RHS side widening Bridge Ch. 2+500

Piling of Varattar bridge completed @ 4+008. A1-P1, P1-P2 & P2-A2 deck slab

Completed.

37 nos. of piles out of 37 nos completed of Thondara bridge 5+213. A2 abutment wall

completed. P4 Pier cap completed

RHS Side slab and crash barrier completed at widening bridge 24+965

GSB 27060 m (LHS) & 26710 m (RHS) completed

WMM 26330 m (LHS) & 26520 m (RHS) completed.

Drain cast – 32578 m

Drain placed – 31565 m

Slabcast – 13004 m

7462 m RR masonry retaining wall & 482 m Sound barrier completed

19.3.1.2 Retaining Walls Retaining wall completed in the following locations

10+960 to 10+970 (RHS), 11+070 to 11+125 (LHS), 12+650 to 12+660 (LHS),12+728 to

12+735 (LHS) , 12+780 to 12+810 (LHS),12+950 to 12+983 (LHS), 13+010 to 13+060

(RHS),13+950 to 13+990 (LHS),13+020 to 13+960 (RHS,14+260 to 14+270 (LHS),14+000 to

Page 46: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 46 

14+010 (RHS), 14+170 to 14+180 (LHS), 14+340 to 14+430 (LHS), 14+460 to 14+4740 (LHS),

14+470 to 14+490 (LHS), 14+510 to 14+570 ( LHS), 2+400 (LHS), 3+930 to 3+950 (LHS),

30+975 to 31+000 (LHS), 36+800 to 36+810 (LHS), 12+780 to 12+800 (RHS), 13+010 to

13+040 (RHS), 13+060 to 13+090 ( RHS) 13+515 to 13+585 (RHS), 13+740 to 13+770 (RHS),

14+010 to 14+030 (RHS), 14+470 to 14+430 (RHS), 24+945 (RHS), 24+960 (RHS), 44+830 to

44+850 (RHS), 44+900 to 45+000 ( RHS), 36+700, Ramp – 2+410 (LHS)

Box Culvert – 1 no. of box culvert half side completed & other culverts are work in progress 11+773 (RHS)

Progress up to August 2016 is as follows

For previous month This Month month Cumulative to end of this month

Target Achieved Target Achieved Target Achieved

51.64% 38.24% 3.12% 2.59% 54.76% 40.83%

Work progress is summarized in the S-curve in Annex 6.4, which compares programmed and actual progress.

A summary of progress for major items is as follows:

Milestone I

(Km 19+400 to 30+000 )

II (Km 30+000 to

47+700)

III (Km. 0+000 to Km. 19+400,

Excluding Thiruvalla bypass)

Length in km 10.600 17.700 17.500

Length handed over to contractor in km 10.600 17.700 17.500

Unencumbered land available to the contractor in km

10.600 17.700 17.500

LHS RHS LHS LHS RHS LHS

GSB completed in km 10.490 10.520 11.840 11.880 4.730 4.960

WMM completed in km 10.300 10.300 11.660 11.610 4.370 4.610

DBM completed in km 10.300 10.300 11.290 11.160 3.910 4.040

BC completed in km 9.530 8.910 0.800 0.500 1.560 1.830

Page 47: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 47 

19.4 Physical Progress

19.5 S-Curve

26268

1445

7521

21797

20931

7402

3262

3134

6221

70960

57228

14146

14000

17802

3594

3000

10406

26500

375826

67504

71921

96000

122071

30000

21000

37055

60500

0 50000 100000 150000 200000 250000 300000 350000 400000

Excavation

Embankment

Subgrade

GSB

WMM

DBM

BC

Concrete total

Precast Drains

BOQ Quantity

Cumulative target to end of this month

Cumulative Achieved to end of this month

Page 48: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 48 

19.6 Schedule of culverts and drainage works

19.7 Payments The contractor has been paid Rs. 105.58 crores

19.8 Implementation of EMP

19.8.1.1 Environment Management at Project Ancillary Facilities The scarified materials and concrete waste materials are using for developing the HM

and Batching plant site. Contractor was also directed to improve the Road safety during

construction along the road .Wearing of PPE by the workers at bridge site is also insisted to

avoid any accident.

Considering the restricted space constrains, additional safety measures are taken and

the movement of trucks inside the HM plant site is to be regulated properly.

The construction safety provisions are not sufficient as the above project road is having

high traffic. Contractor has to provide additional boards, reflectors barricades delineator

posts and flagmen for traffic control. The safety at bridge sites are also to be increased.

Contractor has provided life jackets for workers working in platform for piling as the water

depth is more. The absence of environmental engineer is also contributed for the poor

performance on implementing safety requirements. Contractor was directed to improve

safety at all bridges site urgently. Contractor was not submitted the action taken report

on the site visit observation of the environmental expert hence notice was also issued in

this regard. Post of the environmental engineer is vacant and no substitute posted so far.

Nature of work

Tota

l num

ber

No.

dw

gs a

ppro

ved

Num

ber c

ompl

eted

Num

ber i

n pr

ogre

ss

Num

ber r

emai

ning

Culverts

Pipe culvert 1 1 1

New Box Culvert 101 70 55 46

Total culverts 102 71 56 46

Major Bridge 2 2 2

Minor Bridge 4 4 3 1

Widening Bridge 3 1 1 2

Page 49: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 49 

19.9 Photographs

Slab concrete work in progress Slab concrete work in progress Retaining wall completed

@ Ch. 13+050 (RHS) at Minor Bridge Ch. 04+008

Retaining wall completed @ Ch. 13+050 (RHS)

BT dismantling completed @ Ch. 03+050 (LHS)

Page 50: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

20.1 C U

20.2 C Letter ofAccepta

Agreem

Name of

Contrac

Notice toComme

Total Len

Contrac

Complet

Defect LPeriod

1st Milest

2nd Miles

3rd Milest

Contract Upgradation o

Contract d

ance Date

ent Date

f Contracto

ct Price

o nce

ngth

ct Period

tion Date

Liability

one

tone

tone

Packageof Road from

details:

::

29.1

:: 30.1

or :: M/s

:: Rs.

:: 04.0

:: 40.6

:: 30 m

:: 03.0

:: 365

:: 10 k

:: 30 k

:: 40.9

e V Ettumannoor

11.2013

12.2013

s NAPC Ltd.

171.49

02.2014

60 km

months

08.2016

days

km – BC lev

km – 05.10.2

960 km who

to Muvattupu

.,

vel 01.05.20

2016

ole works by

Scope o Constru

Constru

New Bo

Widenin

Reconst

Foot pa

uzha of SH 1

16

y 23.03.2017

of Works (40

uction of Ma

uction of Mi

ox culverts

ng Slab culv

truction of

ath, Solar Lig

7

0.96 Km):

ajor Bridges

nor Bridge

verts

Culverts

ghts

s –

-

-

0

4

3

14

75

Page 51: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 51 

20.3 Work Progress

20.3.0.1 Progress Achieved - Structures Progress achieved

• Minor Bridge at km.3+877 – Works for widening the minor bridge on LHS is in progress. This minor bridge is in MS-I.

• Minor Bridge at km. 12+524.5 – Deck slab and crash barrier completed. This minor bridge is in MS-II.

• Minor Bridge at km. 22+187 – Reconstruction of bridge completed. This structure is in MS-II.

• Minor Bridge at km. 24+506 – Widening works on both sides are not yet started This minor bridge is in MS-II.

• Minor Bridge at km. 28+362 – Reconstruction of bridge is changed to widening which is not yet started. This structure is in MS-II. The widening proposal is changed to reconstruction based on public demand and location of structure.

• MS 1: Out of 27 nos. Box Culverts 27 nos. substantially completed. All slab culverts (5nos) completed. Protection works like apron, catch pit, quadrant pitching etc of all completed culverts remain incomplete in MS-I

• In MS II out of 36 nos. Box Culverts 30 nos. (protection work balance) substantially completed, 6 nos. Box Culverts are in progress. Four pipe culverts completed and one in progress.

A summary of progress for major items is as follows:

Milestone I

Km. 0+000 to Km. 10+000

II

Km. 10+000 to Km. 30+000

III Km. 30+000 to Km.

40+960

Length in km 10 20 10.960

Length handed over to contractor in km 10 20 10.960

Unencumbered land available to the contractor in km

10 20 10.960

Stretch completed in all respects in km 0 0 0

FW HW FW HW FW HW

GSB completed in km 9.650 0.300 5.275 1.900 0.000 0.000

WMM completed in km 9.620 0.300 4.770 1.290 0.000 0.000

DBM completed in km 9.620 0.040 4.710 1.210 0.000 0.000

BC completed in km 9.320 0.010 0.000 0.000 0.000 0.000

CD completed in Nos. 27/27 30/36

Page 52: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 52 

Up to previous month This month Cumulative up to end of

this month Target Achieved Target Achieved Target Achieved

58.09% 32.51% 2.80% 1.66% 60.89% 34.17%

20.4 Bar chart

20.5 S-Curve

208137

24394

21470

50850

48933

13382

4113

6551

452702

92200

81415

155981

160823

44186

10652

13277

483045

135501

64000

68921

134110

35840

19095

26691

0 50000 100000 150000 200000 250000 300000 350000 400000 450000 500000 550000

Excavation (cum)

Embankment (cum)

Subgrade (cum)

GSB (cum)

WMM (cum)

DBM (cum)

BC (cum)

Concreting (cum)

BOQ Quantity

Cumulative Target to end of this Month

Cumulative Achieved to end of this Month

Page 53: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 53 

20.6 Strip Map

0 100

200

300

400

500

600

700

800

900

1000

1100

1200

1300

1400

1500

1600

1700

1800

1900

2000

2100

2200

2300

2400

2500

2600

2700

2800

2900

3000

3100

3200

3300

3400

3500

3600

3700

3800

3900

4000

4100

4200

4300

4400

4500

4600

4700

4800

4900

5000

5100

5200

5300

Miscellaneous WorksBridges Nos Culverts Nos Drains and WallsBituminous ConcreteDense Bituminous MacadamWet Mix Macadam-IIWet Mix Macadam-IGranular Sub baseSubgradeEW - EmbankmentPothole repair & patching

Pothole repair & patchingEW - EmbankmentSubgradeGranular Sub baseWet Mix Macadam-IWet Mix Macadam-IIDense Bituminous MacadamBituminous ConcreteDrains and WallsCulverts Nos Bridges NosMiscellaneous Works

On going Work

(No./Km)

RIG

HT

SID

EL

EFT

SID

E

Chainage (Km)

Culverts & Bridges Cum. Completed Work

(No/Km)

5400

5500

5600

5700

5800

5900

6000

6100

6200

6300

6400

6500

6600

6700

6800

6900

7000

7100

7200

7300

7400

7500

7600

7700

7800

7900

8000

8100

8200

8300

8400

8500

8600

8700

8800

8900

9000

9100

9200

9300

9400

9500

9600

9700

9800

9900

1000

010

100

1020

010

300

1040

010

500

1060

010

700

Miscellaneous WorksBridges Nos Culverts Nos Drains and WallsBituminous ConcreteDense Bituminous MacadamWet Mix Macadam-IIWet Mix Macadam-IGranular Sub baseSubgradeEW - EmbankmentPothole repair & patching

Pothole repair & patchingEW - EmbankmentSubgradeGranular Sub baseWet Mix Macadam-IWet Mix Macadam-IIDense Bituminous MacadamBituminous ConcreteDrains and WallsCulverts Nos Bridges NosMiscellaneous Works

LE

FT S

IDE

RIG

HT

SID

E

Culverts & Bridges Cum. Completed Work

(No/Km)

On going Work

(No./Km)Chainage (Km)

1080

010

900

1100

011

100

1120

011

300

1140

011

500

1160

011

700

1180

011

900

1200

012

100

1220

012

300

1240

012

500

1260

012

700

1280

012

900

1300

013

100

1320

013

300

1340

013

500

1360

013

700

1380

013

900

1400

014

100

1420

014

300

1440

014

500

1460

014

700

1480

014

900

1500

015

100

1520

015

300

1540

015

500

1560

015

700

1580

015

900

1600

016

100

Miscellaneous WorksBridges Nos Culverts Nos Drains and WallsBituminous ConcreteDense Bituminous MacadamWet Mix Macadam-IIWet Mix Macadam-IGranular Sub baseSubgradeEW - EmbankmentPothole repair & patching

Pothole repair & patchingEW - EmbankmentSubgradeGranular Sub baseWet Mix Macadam-IWet Mix Macadam-IIDense Bituminous MacadamBituminous ConcreteDrains and WallsCulverts Nos Bridges NosMiscellaneous Works

LEFT

SID

ER

IGH

T SI

DE

Culverts & Bridges Cum. Completed Work

(No/Km)

On going Work

(No./Km)Chainage (Km)

Page 54: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 54 

20.7 Schedule of culverts and drainage works

20.8 Utilities

Relocation of electrical utilities and water supply line using materials issued by KSTP is the

responsibility of Contractor. Removal of stumps of trees cut by agencies engaged by KSTP

is also the responsibility of Contractor. KSTP/PMT has made arrangements with BSNL and

other private agencies for relocation of cables, telephone posts and telephone pillars.

KSTP has issued most of the items required for relocation of Electric and Water utilities and

relocation work is under progress.

20.9 Key issues: The following issues are very critical which may have adverse impact on the timely

completion of the Project.

• Insufficient teams, staging and shuttering materials are affecting protection works and CD works.

• Delay in mobilization of adequate labour and machineries to make up backlogs.

• Lack of resources at site which reflected in planning of works at site.

• The poor cash flow of Contractor has seriously hampered the progress of works.

20.10 Payment to the contractor The contractor has been paid Rs. 53.96 crores

Nature of work

Ori

gina

l num

ber

No.

dw

gs a

ppro

ved

Num

ber

com

plet

ed

Ori

gina

l num

ber

No.

dw

gs a

ppro

ved

Num

ber

com

plet

ed

Num

ber

in p

rogr

ess

Num

ber

rem

aini

ng

Ori

gina

l num

ber

No.

dw

gs a

ppro

ved

Num

ber

com

plet

ed

Num

ber

in p

rogr

ess

Num

ber

rem

aini

ng

Culverts

Widening Slab Culverts 5 5 5 7 3 2 2 3 6 6

Slab Culvert retained 2 2 2 2 2 2

Reconstruction Slab/Box 24 24 24 0 33 33 27 4 2 11 11

New Box Culvert 3 3 3 0 3 3 3 0 3 3

New Pipe Culvert 0 5 4 4 1 0 5 5

Total culverts 34 32 34 0 0 50 43 36 7 7 27 0 0 0 27

Bridges Retained 0 1 1 1 1

Widening Bridges 1 1 3 3 1 2 0 0

Reconstruction Bridges 0 1 1 0 0 0

Total Bridges 1 0 0 1 0 5 3 2 0 3 1 0 0 0 1

Num

ber

in p

rogr

ess

Num

ber

rem

aini

ng

Milestone - I Milestone - II Milestone - III

Page 55: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 55 

20.11 Implementation of EMP

20.11.0.1 Environment Management at Project Ancillary Facilities Contractor has obtained consent to operate for all the plants except crusher. . The

remaining works of parking area , bus bays, noise receptors are to be taken along with

the pavement works The disposal of excavated earth is an issue, as large quantities of cut

earth is available .Disposal site has to be provided to the contractor by the employer

Contractor has identified two private temporary disposal site. The major activities are

spread in the milestone 2.Lot of places high cutting are done. Additional safety boards

are required at these locations. The labor accommodation for new labors is to be

provided with ventilation. Cooking inside of living rooms is to be immediately taken

outside of the accommodation to the kitchen location. Contractor was also directed to

establish a biogas plant at labor camp for treating waste. Contractor has to install all

signage and marking in the completed road sections. Lot of protection works are to be

taken up in the sections @CH 30 to 40km. Location of the retaining wall and gabion wall

was identified and contractor has to start these works urgently to achieve the planned

target dates. Notice was issued to the contractor for not submitting the action taken

report on the site visit observation of the environmental expert.

20.11.0.2 Traffic Management and Road Safety Measures Traffic safety management at site has to be improved in locations where high cutting.

Considering the upcoming monsoon season direction was also issued to the contractor to

keep the construction zone lit during night with reflectors and flash lights., further in the

realignments where rock blasting is anticipated, safety provisions is to be increased.

Fencing the boundary was done but sign boards are missing.

Page 56: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 56 

20.12 Photographs  

DBM at 19+450 RHS DBM at 14+500

Bridge at 22+079 A2 Approach Slab Bridge at 22+079 A2 Approach Slab

Page 57: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 57 

21.1 Contract Package VI Upgradation of Road from Ponkunnam to Thodupuzha Scope of work (46.363 km)

Minor Bridge reconstruction - 1 no.

Culvert:

Reconstruction - 109 nos.

Widening - 44nos.

New Construction - 7 nos.

Drain - 65 km

Foot Path -

Solar Street Light -

21.2 Contract details:

Letter of Acceptance

date

:: 04.02.2014

Agreement date :: 05.05.2014

Name of Contractor :: M/s GHV-EKK (JV)

Contract price :: Rs. 227,13,73,548

Notice to Commence :: 10.06.2014

Total Length :: 46.363 km

Contract Period :: 30 months

Completion date :: 09.12.2016

Defect Liability Period :: 365 days

1st Milestone :: 10 km

2nd Milestone :: 25 km

3rd Milestone :: Completion of full stretch & Thodupuzha Bypass

Page 58: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 58 

21.3 Physical Progress: Summary of progress for major items is as follows:

Milestone I (85+000 to 95+000)

II (84+000 to 85+000)

Bypass 2.57 km (106+000 to 117+430)*

III (95+000 to 106+000)* (117+430 to 131+015)

Length in km 10.000 15.000 24.585

Side LHS RHS LHS RHS LHS RHS

GSB completed in km 10.00 10.00 15.00 15.00 18.33 20.66

WMM completed in km 10.00 10.00 15.00 15.00 17.35 18.61

DBM completed in km 10.00 10.00 15.00 15.00 15.02 15.89

SMA completed in km NIL NIL 5.94 5.94 0.38 0.38

BC completed in km 10.00 10.00 8.36 8.36 10.14 9.56 CD works completed in No.’s 20/20 43/43 79/79

Work progress considering the contract price:

Up to previous month This month Cumulative (till end of this month)

Target Achieved Target Achieved Target Achieved

87.06% 99.03% 3.55% 2.27% 90.61% 101.05%

21.4 Work Progress

21.4.0.1 Utility Shifting:

1590 Electrical Poles has been shifted up to the month.

17 km KWA Water pipe line has been shifted from the location.

9.0 km Panchayat Water line has been shifted up to the month.

Tree cutting has been completed in Milestone-I & II and work is in progress in

Milestone III.

49 No’s. Transformers have been shifted till date.

Page 59: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 59 

21.4.0.2 Quality Control

21.4.0.2.1 Report of Approval of Materials:

21.4.0.3 Material Test Results:

Work Status in Quality Control:

During the month total 572 Field Dry Density tests have been conducted for Earthwork

(EMB & SG) among them 522 tests has passed. Total 391 Field Dry Density tests have been

conducted for Granular Sub-base among them 376 tests has passed. Total 106 Field Dry

Density tests have been conducted for Wet Mix Macadam all of them have passed.

Item No. of Sources Located Submitted Approved RCC Hume Pipes 2 2 1 Cement 3 3 3 Steel 3 3 3 Admixture 3 3 3 Geotextile 1 1 1 Gabion 2 2 2 Elastomeric Bearing 1 1 1 Fine and Coarse aggregate (Cochin blue metals) 1 1 1

Strip Seal expansion joint 1 1 1 Stone Matrix 2 2 1 Bitumen 1 1 1 Emulsion 1 1 1 Fine & Coarse WMM Mana Crusher 1 1 1

Corrugated Pipe of 300mm dia 1 1 1 Road marking compound  1 1 1 Signalization, LED blinkers & LED standalone solar light 2 2 1

4 wire rope safety fencing 1 1 1 Flooring Tiles for bus shelter 1 1 1 Road Stud (White) 1 1 1 Interlock Tiles 1 1 1 Solar LED Blinkers 1 1 1

Page 60: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 60 

21.5 Bar Chart of Physical Progress:

21.6 S-Curve

371255

78912

94327

68770

133231

117241

58857

26764

2496

10582

19118

37699

2144

2665

0

0

397929

0

41194

215400

117000

132800

255685

28616

5000

12000

24922

42045

5092

3050

102

29

397929

25000

41194

222161

124075

145542

255685

28616

8000

14874

26862

42045

5092

3050

102

29

Excavation (cum)

Excavation (cum)  in hardrock

Embankment (cum)

Subgrade (cum)

GSB (cum)

WMM (cum)

Loosening and recompacting

DBM (cum)

SMA (cum)

BC (cum)

Concreting M‐15 (cum)

Concreting M‐20 (cum)

Concreting M‐25 (cum)

Concreting M‐30 (cum)

Concreting M‐35 (cum)

Concreting M‐40 (cum)

BOQ Quantity Cumulative target   to end of this month  Cumulative Achieved  to end of this month 

Page 61: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 61 

21.7 Schedule of Cross Drainage Works

21.8 Implementation of EMP

21.8.0.1 General Consultant’s supervision initiatives for compliance of environment management plan and

to strengthen mitigation efforts at construction site were in progress in various areas during

month August, 2016. Planning, monitoring and supervision for environment mitigation work

was been done for compliance of EMP along with up-gradation of road from Ponkunnam

(KM 84+000) to Thodupuzha (130+000) and Thodupuzha bypass of SH-08.

During the work progress the statutory compliance under environment regulations, Air

(Prevention &control pollution) act 1981, Water (Prevention & control of pollution) Act

1974, and Waste (Management and Handling) Act 1989 was emphasized. The traffic

management and safety has been practiced throughout. PAP’s issues are addressed;

grievance has been rectified by implementing the suggested action plans by KSTP.

Page 62: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 62 

21.8.0.2 EMP Monthly Progress Report A. Project Details Period of Reporting :August 2016

1. Name of project stretch and link no. Up-gradation of the Road from Ponkunnam (84+900) to Thodupuzha (131+016) and Thodupuzha Bypass of SH-08

2 Name and address of the Contractor M/s. GHV-EKK (JV), Perumbavoor

3 Contract date and duration 5th May, 2014, 30 Months (Commencement notice date 10th June 2014)

4 Status of completion of the project 9thDecember 2016 B. Physical Progress Report S. No. Enhancement/ Mitigation

Measures Physical target / (Achieved) (No’s.)

Units carried over from previous month

Units started in reporting month

Units completed in reporting month

Units carried over to next month

(a) (b) (c) (d) 1. Noise Barrier 19/ (7) 1 0 0 1 2. Hand pumps 6/(6) 0 1 1 0 3. Bus Shelter 35 1 0 0 1 4. Sign Boards 997/(726) 0 0 0 0

5.

Preserving and landscaping the cultural properties like shrines and Hyundai

7/(2) 0 0 0 0

6. Constructing new well 3/(1) 0 0 0 0 7. Providing new water taps 33 0 0 0 0

8. Parking space for auto rickshaws, cars and jeep

Quantity not estimated

9. Landscaping of type C oxbow lands 28 1 0 0 1

10. Planting trees along road side 864/(360) 0 80 80 0

11. Planting trees on inner side of sound insulating wall

440/(83) 0 0 0 0

12. Providing 1.2 m high fencing under via duct

Quantity not estimated

0 0 0 0

13. Concrete flooring with slope drains and oil interceptors

3/(1) 0 0 0 0

14 Water Sprinkling Not Estimated/ (825 hrs)

0 0 0 0

15 Air Quality Monitoring 36/(29) 0 0 0 0 16 Water Quality Monitoring 30/ (24) 0 0 0 0

Page 63: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 63 

C. Details of Sites for Project Ancillary Facilities S. No. Type of Camp/Site Cumulative No

of sites opened

No of sites operational

Cumulative No of sites redeveloped

Cumulative No of sites Closed*

1. Construction Camp 2 2 0 0 2. Labour Camp 2 2 0 0 3. Quarry & Stone

crusher unit 1 1 0 0

4. Borrow Area 0 0 0 0 5. Debris Disposal Site 0 0 0 0 6. Water Sources 3 3 0 0 * A site will be considered closed after redeveloping and obtaining closure certificate from CSC. D Reporting/Monitoring Formats to be annexed with this monthly report by the CSC S. No. Reporting/Monitoring Format Yes/No 1 Reporting Format for Enhancement and Mitigation of Common Property

Resources Yes

2 Reporting Format for Work Force Management Yes 3 Reporting Format for Occupational Health and Safety Measures Yes 4 Reporting Format for Road Safety Measures during Construction Yes

21.8.0.3 Environment, Health and Safety Road markings was restarted in the month and done at certain location of Section 1 and

2.

Guard post installation has been done along culverts.

Avenue plantation under environmental enhancement plan was in progress during the

month.

Cultural properties have been protected; access way, slope protection wall, stair way

reconstruction has been done in this month.

Grass cutting around camp has been done to prevent water stagnation and insect

proliferation. Mosquito menace has been prevented by spreading fogger (smoke) in the

camps.

Safety lapses were observed due to lack of manpower, same has been instructed to the

contractor.

During the month work progress and pace was very slow because of rain, the month was

declared as monsoon vacation for the employees/laborers by Contractor. Fewer work

forces were deployed.

21.9 Payment to contractor

Payment up to May 2015 is Rs. 206.61 crore

Page 64: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 64 

21.10 Photographs

Road line demarcated in section 1

Guard post Installation along the culverts has been

done

Laying of DBM at Ch. 125+640 to 126+240 RHS

FDD test conducted for GSB at Ch. 128+350 RHS

Page 65: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 65 

22.1 Contract Package VIII Upgradation of Road from Punalur to Ponkunnam Work has to be arranged under PPP mode (Modified Annuity). DPR submitted by

M/s CDM Smith Associates is under review. The Transaction Advisory has been selected

and assignment commenced. The Transaction Advisory is M/s L&T Ramboll in JV with M/s

Fortress. The review of DPR and RFQ, RFP and Financial modal are completed. Bidding

documents were placed before the Steering Committee and endorsed. The Government

had expressed willingness to include the project in the Infrastructure fund being mobilized.

Government have further informed that a “line item” in the State Budget will also be

included. The pre-qualification bids were published and the pre-bid meeting is over. The

bids were submitted on 02.06.2016 and evaluated and being placed to the Steering

Committee for decision.

23.1 Contract Package VII Upgradation of Road from Perumbilavu – Pattambi - Perintalmanna

Horizontal alignment finalized and boundary stone planted for land acquisition. The

original proposal was to upgrade the project under EPC mode. But due to the delay

anticipated in acquiring the land invoking the provision of the new LA Act for which rules

are being finalized by the Government, it has been decided to provide a modest level of

improvement to the surface. It is also proposed to make use of the savings due to the

change in the improvement proposals for providing overlay to the KSTP-I roads.

Accordingly proposals have been submitted to the Government and to the Bank after

obtaining approval of the Steering Committee on 28th July 2014. The work has been

awarded and agreement executed. The work commenced.

24.1 Proactive actions taken by employer:

1. The threshold limit of minimum IPC has been lowered to Rs. 1.50 crores from

Rs. 3.00 crores to facilitate cash flow of the contractors.

2. Extension of time limit for completion of Milestone-I has been granted for Package

I, II and V to compensate the delay caused due to reasons beyond the control of

the contractors. The contractor for Package III could not speed up the work and

hence terminated for non performance and re-arranged as 3A and 3B

Page 66: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 66 

25.1 Road Safety Component – Current Status

Road Safety Capacity Building and Program Management Project

The focus of Road Safety Program Comprises of the following tasks:

To strengthen the capacity of Kerala Road Safety Authority to introduce Sustainable

International Best Practice in designing, implementing and Evaluation of Road Safety.

Development of Safe Corridor Demonstration Project (SCDP) by implementing the Multi-

sectoral interventions to demonstrate the effectiveness of Road Safety Best Practices.

The Kazhakkoottam – Thaikod – Kottarakara – Adoor Corridor (80 km) improved during

KSTP-I is identified for this purpose having high density of traffic

To replicate the lessons learned from the Safe Corridor Demonstration Project to develop

another 10 safe corridors across the State through local partnerships using the challenge

fund and the matching fund from the KRSA

Road Safety Capacity Building of the institutions responsible for managing Road Safety in

the State.

The KSTP appointed M/s VicRoads, Australia, an internationally experienced consultant to

support in implementing the above programs. The consultant has conducted

stakeholders meetings and trained the Engineers and others in designing various Road

Safety interventions in the SCDP. The tender is being evaluated for placing before the

Steering Committee.

The proposal for strengthening the Kerala Road Safety Authority has been accepted by

the Executive Committee and the actions for procuring specialists, to various positions are

in progress.

Traffic counters were procured and installed at five locations, one in NH and four in

location in the project roads. These counters shall be utilized for planning of future road

geometrics requirements, capacity analysis, seasonal variations, daily variations of traffic

volume during festivals etc.,

Page 67: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 67 

The KSTP has entrusted the consultant to take actions for the procurement of Market

Research firms. The market research would support Development of the publicity and

education programs, including future campaigns.

Establish benchmarks on knowledge, attitudes, perception of road safety issues and self-

reported behaviors of road users for monitoring the impact of future road safety activities

and effectively support the task of the Road Safety Capacity Building and Program

Management Consultant

Proposals were invited for eight tasks based on separate ToRs from experienced five firms

and evaluation done to select suitable firms for assigning the tasks. The survey for Road

User Behavior and helmet and seat belt nearing completed. The overtaking studies

completed.

26.1 Institutional Strengthening Components – Current Status The key element in the Institutional Strengthening Component in the KSTP II is Road Sector

Modernization, which is designed to support strengthening of the institutional and

financial capabilities of Kerala PWD and related activities to effectively develop and

maintain the physical assets. The key action in this direction is to classify the Core Roads

Network which are strategically important, with options to finance and manage the same

effectively.

In order to achieve this objective of the Strategic Road Network (SRN) Program (SRNP) the

following actions are envisaged.

Identification of the SRN with options for Asset Management Process necessary for management and maintenance of physical assets in most efficient and sustainable manner. To evolve the financing and budgetary process that have an impact on management of the SRN, and also seek opportunities for enhanced finding resources. To determine the extent to which the PWD has Road Asset Management Capacity and to determine appropriate organizational context to ensure effective management of the SRN.

The GoK appointed the former Chief Secretary of the State

Shri. Babu Jacob as ‘Client Executive Program Sponsor’ to guide in implementing the

program. The bidding process to select Internationally Experienced Consultants to

support the Client Executive Program Sponsor is now underway. The Technical proposals

received are under evaluation and is due to poor response, it was decided by the

committee to invite re-bid for the assignments. Banks comments are sought.

Page 68: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 68 

A Review Group comprising senior Secretaries of Ministries Finance, Works, Planning and

Industry will be set up under the Chairmanship of the Client Executive Program Sponsor.

The developing of an Integrated Information Management System (IIMS) for PWD. It has

been decided to engage NIC for this assignment. However as they were not interested,

the ToR was limited the activities for improving the existing system in the PI Cell.

Improvement in Community Participatory Road Safety and Asset Safeguard Program.

This assignment could not be awarded due to settlement of a case in the Hon’ble High

Court of Kerala. The Hon’ble High Court has delivered the Judgment by upholding the

decision of the Steering Committee to rebid. The Bank had already expressed no

objection for re-bid. The Steering Committee also decided to invite re-bid. The KSTP has

conducted User Perception Surveys to verify the adequacy of the design and program of

implementation at the start of the project through an experienced agency. The Road

User Satisfaction survey at mid term is being arranged. The ToR has been prepared and

forwarded to Bank for review.

27.1 Payment to the consultants as on end August 2016: M/s Egis India JV - Rs. 222271283

M/s MSV International - Rs. 35927487

28.1 Restructuring of KSTP II A consolidated proposal for Re-structuring of KSTP II has been submitted to State

Government after detailed discussion with the Bank. Since savings in Bank Finance is

expected mainly due to difference in the Foreign Exchange Rate, there is need to

enhance the Bank Assistance to the Project from the present 56% to 63%, to cover up the

loan amount of US$ 216 million. The exchange rate considered in the Restructuring

proposal is INR 67 to US$ against INR 54 to US$ considered at the loan approval stage.

29.1 Meetings, Site visits & Inspection Package-I

Environmental Engineer inspected the Project site on 14th July 2016

Progress review meeting conducted by Additional Chief Secretary, PWD on 02nd

July 2016 at PMT, Thiruvananthapuram

Page 69: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 69 

Package-II

Progress review meeting conducted on 02nd July 2016 at PMT,

Thiruvananthapuram.

A meeting was convened by Hon’ble Minister for PWD on 12th July 2016 at

Thiruvananthapuram.

Package-IV

Progress review meeting was held on 02/07/2016 and 25/07/2016 at KSTP,

Thiruvananthapuram.

Package-IVA

The PWD secretary accompanied by Project Director and Team Leader have

visited the Project on 24/07/2016

Progress review meeting was held on 02/07/2016 and 25/07/2016 at KSTP,

Thiruvananthapuram.

Package-V

The Project Director convened a meeting at PMT on 2nd July 2016 and in

continuation the Secretary PWD convened another meeting at Secretary’s

chamber. It was decided to prepare realistic programme to complete the work

within the extended period.

30.1 Land Acquisition Status

SI. No

Name of road & Length (km)

Land proposed

for Acquisition

(Ha)

Land Acquired (Ha)

Land Pending

Acquisition (Hectare)

Present position/ Reasons for

delay

1 Kasargode – Kanhangad (24.00) 2.9177 2.9177 0 NA

2 Pilathara – Pappinssery (21.00) 7.3057 7.3057 0 NA

3 Thalasery – Valuvapara (53.78) 25.0312 24.9367 0.0945 (0.38%) LA in progress

4 Chengannur – Ettumanoor (47.00) 11.1815 11.1815 0 NA

5 Ettumanoor – Muvattupuzha (40.90) 15.6197 14.3591 1.2606

(8.07%)

DLPC is yet to negotiate for

direct purchase and new GO

awaited.

4A Thiruvalla Bypass (1.2) 5.5105 5.0404 0.4701 (8.53%)

Direct purchase, stalled due to

non-availability of funds

6 Ponkunnam – Thodupuzha (50.10) 26.7401 26.7049 0.0352

(0.13%)

LA & DP in progress – Lack

of funds

Page 70: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 70 

7 Punalur – Ponkunnam (82.12) 26.6518 26.1388 0.5130 (1.92%)

LA & DP in progress – Lack

of funds

8 Perimpilavu – Perintalmanna (41.00) 9.7013 0 9.7013

(100%)

Requisition given , LA not

yet started

32.1 Status on Critical Actions identified by World Bank Component A – Road Network Upgrading and Safety Improvement: 1. Improve site management, construction planning

and resource utilization to achieve consistent monthly progress of 5% for Contract 5

The contractor has been given time for completion up to 31.03.2017, subject to the condition to achieve 5% progress every month, failing which contract will be terminated.

2. Achieve a consistent monthly progress of 8% for

Contract 1 & 2 The contractor has been given time for completion up to 31.03.2017, subject to the condition to achieve 8% progress every month, failing which contract will be terminated.

3. Initiate construction in Tavam RoB in Contract-2 Design finalized 4. Finalize detailed design and estimation for the

Package 4A viaduct and submit to Bank Bank issued the No Objection Certificate for variation and this will be placed before the next Steering Committee.

5. Hire a group of Independent Quality Assurance

Specialists Proposal with ToR has been prepared for placing before the next Steering Committee

6. Finalize ToR for Independent Engineer for PPP

Concession ToR prepared and will be sent to Bank, subject to finalization of pre-qualification of bidders. The pre-qualification bids were re-invited

7. Complete evaluation for RFQ and Issue RFP for PPP

concession

The pre-qualification bids were re-invited. Fixing last date of receipt of RFQ on 24.10.2016

Component B – Road Safety Management: 8. Award contract for the Road Safety Demonstration

Corridor Civil Works LoA issued on 26.09.2016

9. Resume and complete the process of specialized

staff recruitment in KRSA Proposal sent to Secretary to Government PWD for discussion with the Transport Commissioner and the proposal accepted and selection in process is initiated.

10. Initiate identification of challenge fund projects in

the project influence area Actions to identify roads under progress

11. Engage Local Road Safety Advisor

Actions being taken

Page 71: KERALA STATE TR ANSPORT PROJ ECT - IIkeralapwd.gov.in/keralapwd/eknowledge/Upload/documents/...KS DE ENT O ANSPO N ROGRE UST 2 03 PARTM F KERA RT PR CE – Loa SS BR 016 ENT LA OJECT

Monthly Progress Brief – August 2016  Page 71 

Component C – Institutional Strengthening: 12. Institute Strategic Review group This is being formed 13. Evaluation of WPs and contract award Evaluation completed and due to

poor response to the bids, the Steering Committee has decided to rebid.

14. Award of IIMS ToR revised for rebidding limiting the

scope. 15. Technical advisor Actions taken and will be finalized

soon Financial Management

16. Submit claims Submitted 17. Submit IFR for period ended 15th June 2016 Submitted 18. Submit internal audit report for second half of FY 15-

16 Audit over and report forwarded to World Bank

19. Carry out physical verification of assets In progress 20. Appoint internal auditors for FY 16-17 Technical Proposal evaluation

completed. 21. Submit approved accounts of FY 15-16 to CAG Action will be taken on receiving

minutes of Steering Committee 22. Submit external audit report for FY 15-16 Will be submitted on time 23. Monitor receipt of counterpart funding Being taken up with State Government

for timely allotment General Project Administration Issues 24. Appoint dedicated Project Director Appointed

25. Submission of Project restructuring proposal to

Government of India Proposal submitted to State Government for approval and forwarding to DEA (Government of India)